HomeMy WebLinkAboutPR 19593: PA PHASE III PERFORMANCE CONTRACT- METERS & AMI, WITH SIEMENS INDUSTRY, INC. MEMORANDUM CITY OF PORT ARTHUR UTILITY OPERATIONS DEPARTMENT TO: Brian McDougal, City Manager FROM: Jimmie Johnson, Ph D, Assistant City Manager DATE: December 05, 2016 RE: Proposed Resolution No. 19593 RECOMMENDATION I recommend that the City Council approve Proposed Resolution No. 19593 acknowledging the acceptance of the Certificate of Substantial Completion and Certificate of Final Completion for the City of Port Arthur Phase III Performance Contract — Meters & AMI (Project No. 440P-139862) with Siemens Industry, Inc., Building Technologies Division. BACKGROUND Per Resolution 14-406, the City of Port Arthur contracted with Siemens Industry, Inc., Buildings Technologies Division, for the replacement of fire hydrants, large water meter replacements, and city-wide retrofit to a fixed base system and automatic meter reading system upgrade, in an amount not-to-exceed $8,021,021.00. A Certificate of Substantial Completion was also submitted with a punch list, the items on the punch list have all been resolved. BUDGET/FISCAL EFFECT This project was funded through an agreement with Siemens pursuant to Resolution No. 14-406. SUMMARY I recommend that the City Council approve Proposed Resolution No.19593. P. R. No. 19593 12/09/16 ds/gt Page 1 of 3 RESOLUTION NO. A RESOLUTION AUTHORIZING THE CITY MANAGER TO ACCEPT THE CERTIFICATE OF SUBSTANTIAL COMPLETION AND CERTIFICATE OF FINAL COMPLETION FOR THE CITY OF PORT ARTHUR PHASE III PERFORMANCE CONTRACT — METERS & AMI (PROJECT NO. 440P-139862) WITH SIEMENS INDUSTRY, INC., BUILDING TECHNOLOGIES DIVISION WHEREAS, per Resolution No. 14-406, the City entered into a contract for Phase III of a Performance Contract with Siemens Industry, Inc., Building Technologies Division, for the replacement of fire hydrants, large water meter replacements, and city- wide retrofit to fixed base system and automatic meter reading system upgrade, in an amount not-to-exceed $8,021,02100; and, WHEREAS, this project was funded by the City through a Tax Exempt Term Lease Agreement, which is authorized pursuant to Chapter 302 of the Texas Local Government Code, and will provide water and operational cost savings as that can offset the cost of the project; and, WHEREAS, Siemens Industry, Inc., Building Technologies Division, has submitted a Certificate of Substantial Completion with a punch list attached as Exhibit "A"; and, WHEREAS, the Utilities Operation Department has inspected the completion of the punch list, and it is hereby declared that all items on the punch list, attached as Exhibit "A", have been resolved; and, P. R. No. 19593 12/09/16 ds/gt Page 2 of 3 WHEREAS, Siemens Industry, Inc., Building Technologies Division, has fulfilled the terms of the contract executed for the City of Port Arthur Phase III Performance Contract — Meters & AMI (Project No. 440P-139862); and, WHEREAS, Siemens Industry, Inc., Building Technologies Division, has submitted a Certificate of Final Completion, dated September 20, 2016 attached hereto as Exhibit"B" for the City of Port Arthur Phase III Performance Contract — Meters & AMI (Project No. 440P-139862). NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PORT ARTHUR: THAT, the City Council hereby authorizes the City Manager to accept of the Certificate of Substantial Completion, in substantially the same form as attached hereto as Exhibit "A", for the City of Port Arthur Phase III Performance Contract — Meters & AMI (Project No. 440P-139862) with Siemens Industry, Inc., Building Technologies Division; and, THAT, the City Council hereby authorizes the City Manager to accept the Certificate of Final Completion, in substantially the same form as attached hereto as Exhibit "B", for the City of Port Arthur Phase III Performance Contract — Meters & AMI (Project No. 440P-139862) with Siemens Industry, Inc., Building Technologies Division; and, THAT, a copy of the caption of this resolution be spread upon the minutes of the City Council. P. R. No. 19593 12/09/16 ds/gt Page 3 of 3 READ, ADOPTED AND APPROVED THIS day of 2016 at a Regular Meeting of the City Council of the City of Port Arthur, Texas, by the following vote: AYES: Mayor: Councilmembers: • NOES: Derrick Freeman, Mayor ATTEST: APPROVED AS TO FORM: 10 1/qD Sherri Bellard Tizen City Secretary City Attorney APPROVED FOR ADMINISTRATION: Brian McDougal Dr. Jimmie Johnson, PhD City Manager Assistant City Manager APPROVED AS TO THE AVAILABILITY OF FUNDS: }/t.tAIN) ,4044t, Jerry Dale, CPA/CGFO Clifto Williams, CPPB Director of Finance Acting Purchasing Manager Exhibit "A" (Certificate of Substantial Completion) Exhibit D-1 — Form of Certificate of Substantial Completion SIEMENS Certificate of Substantial Completion PROJECT NAME: City of Port Arthur Phase 3 Performance Contract— Meters &AMI CLIENT: City of Port Arthur CERTIFICATE DATE (mm/dd/yyyy): September 15, 2016 CLIENT's RESOLUTION #: 14-406 PROJECT NUMBER: 440P-139862 The following portions of the Work are at Substantial Completion in accordance with the Agreement. Warranty dates below are for Siemens workmanship and do not include manufactures warranty and associated terms. Work Item: Fire Hydrants Warranty Start Date: July 1, 2016 Work Item: AMI Infrastructure (Repeaters, Poles, Collectors) Warranty Start Date: July 1, 2016 Work Item: Water Meter Retrofits Warranty Start Date: September 1, 2016 The Building Technologies Division of Siemens Industry, Inc. guarantees the workmanship and materials of the above Substantially Complete Work in accordance with the Agreement. The Work indicated above has been reviewed by the CLIENT and has been found, to the best of the CLIENT's knowledge, to be Substantially Complete. Substantial Completion is the milestone in the progress of the Work at which time the Work is sufficiently complete and available for the CLIENT to have beneficial use of the Work for its intended purpose. A list of items to be completed and corrected (if any)shall be identified as the Outstanding Items List, attached to this form, and indicated by checking the appropriate box below: Outstanding Items List Attached: ® No Outstanding Items Noted: ❑ Water Meter Punch List Items Spreadsheet—Attachment#1 The failure of the CLIENT to note items requiring completion or correction does not relieve the contractual responsibility of Building Technologies Division of Siemens Industry, Inc. to complete or correct the Work. Work found to require completion or correction after the Certificate Date of this Page 1 of 2 Siemens Industry, Inc., Building Technologies Division Exhibit D-1 —Certificate of Substantial Completion v.2014 Exhibit D-1 —Form of Certificate of Substantial Completion Certificate, but within the warranty period shall be corrected in accordance with the Agreement's warranty provisions. Building Technologies Division of Siemens Industry, Inc. agrees to complete or correct all items indicated on the Outstanding Items in a timely manner. Building Technologies Division of Siemens Industry, Inc. Representative: Chad Nobles Signature: Date: 9-13-2016 The CLIENT accepts the Work indicated above as Substantially Complete and assumes possession and beneficial use of the Work on the Warranty Start Date indicated above. CLIENT: CLIENT Representative: Signature: Date: Note: The CLIENT shall, upon execution of this Certificate of Substantial Completion, assume all contractual responsibilities for maintenance, insurance, operation, and protection of the Substantially Complete Work in accordance with the Agreement. Page 2of2 Siemens Industry, Inc.,Building Technologies Division Exhibit D-1 —Certificate of Substantial Completion v.2014 C a) E A' _ o _ o v a ) v v _ 0 E a) — — N o E 4t- iz y v o E Y v o f a., a o f a) 7 — , oo a a 'a-, m rn a ° to O. > Ea) � v > Ea+ > Ea o > Eua a 3 ° cE - c ,> E u v U .y > L, y c x u a)YavN c '' E . uE N Z a C 7, a) C c y u — , 3 c y U 43 v u = c = 43 i-,-, a) ✓ oc v A Z Y cN v oo ° \ a Y m voo ° a Y N z, oo ° O_-G c v o z o ° re n 2 3 a, 3m 3rn 3m o s 0 CO D > o 0 0 0 0 o v a m Q _ — — _ c ;n w Z 01 i Ti i i CO J >.a C to ., j N V Q Y `cii 0 LL i i LL U G La/ 0J 0 a 0 a Z -a gri y- V' w w w w -O �j V j > as L L 01 L L a a) Z ' m N U U U U O -D o C n N vl of vl N a o a Q Q Q 3 ✓ ' ao `) a a a a a a - a (a -o to w w o a w 3 c u w 1.L1 0.1 w E C7 0 0 U C Y Ya/ Q Q Q Q 0 Y 0 a D O c K K C K w N o co ~ o a v 3 O O O O a w o • m u ,-' an -1 v O. � a _ ; vG 0 o OG o v 0 in u..“, N a E z z z z z z z Z Z 2_ a 0 a W N V CO V VI N M N N O ,n co J cc ."I V O N M M co N N N N N t -0 00 O� Vl Vl N un to La c ID 0 CO 00 CO CO CO C 5 .-I a) co 00 00 0o 00 7 0 m oo co co co co co O. c,. `a 10 L 1D 1D IC 10 1D CC, LC, w 1"1 ti r1 'i e-I .--I .--I d v o O O o O O O N N N N N N 2 O 00 00 \ an \ a\i \ a\i ac W \ \ \ \ L a1 a1 a1 a1 at al al 7 .L, o 0 0 0 w Q O z .E z Z z Z z Z O 0 v 2 Z ai a w c. w a' w a' w O. v Z O O u Z O a m a io a w O Z •O ' 2 O a O Q O Q O Z ai 00 " "O "O F "O ~ -o ~ .•�, v CO a c as E Z 0, 0 aa)i O a°1i O _ LL V ,i Q a Z o0 t0 Z Z Z Z Z Z LU C N w w w 0 a`) O w O a) 0 N a ) 0` aL a `) `) L Z 3 pm co ffi, Z Z Z L• 00 U w w U U U ✓ U w a w v 0 �0) w N w w w a nQ ami 2 ap y w Z n0 a0 a � viii U Z H in 2 E 0 u .- , v"i 2 v, 2 .^-I o N o Laco00 N ea 00 V ON NN N N N N 00 CA 00 00 a1 O 00 Ui 00 00 00 to N 10 CO 00 10 La 10 ,D 1D M Zvj M O Ln 00 N V m 00 N M .-I '-1 a) N O .-I 0o N m V) N M o enn in N n`n'1 M o 2 co rn 0o 0o 0o M m 00 00 00 00 O al CO N N N N fp CC ✓ r >- > > Z00 > -0 g 2 z > > > ,,, Q I— O c7 t7 C7 u l7 > LL Q 00 N V1 V) VI Vf = H y m .. 5 Z O O O 0 O U r, La laat 0 V N m -. N O N O N 0 NN 0 i-L cc cc rn cc NN 1- N CO 10 V V V d' a! O 01 z to ..-I N N 00 N IC ` Ci CO al 01 Ol a, MN 0000 Ua Q Nrt. M f1 a1 al to 00 , M co co co co 0al N oo Lo 000 N N a! e 0 M .--1 m .5 M O Ln Lo tD CO .-'1 N N = N co 10 CD N V f0 O of N O O O O t0 a V co M m M M 00 L a 00 00 00 00 00 00 00 t 0 D a 2 r+ N (Ni a ,n CO N o H > CD C a. E a, 7, a) a) v a( o f a, , :c. o f v o f v ° Ea, . v v F O �O —N H O , O —N ~ o , ° —N H o o nv y Em ami, Y Eat n�v E01 c,. .1,+,35 EQ1 c,..T cu 2 0 v 02220 v o o w 2 u m 022 g 0 v 0 o - u L y as > N O L To (a > N U L Y N >, to U L N fa > N x - �' C ti E_ • c ._,•• E_ • c 6• E- C c' E Z 3 0 c u =� 3 S c (�= 0 3 u _� 3 S c (�_ a Y - N N a Y - (a a Y - N To a S N K O y0 c O C o o ( O K o o c O O o ( Fs,' 3 m 3 m 3 ccm 0 a a' `'' 3 3 3 3 Co - 0 0 0 0 a7., v v v (v1 >- >- >- >- v,v, v T, .( T, it a a o: o: Lu w w w 0 Y Y Y U U U U a) a) aJ a. L L L L ✓ u U u U > v1 v1 v1 v1 O a a a a v a a a a a O w w w w C7 (.0 (7 0 CQ Q Q a ID cu H . K C K K W W W W N ro > > > > 0 0 0 0 .M-N a O G O b b b01 in zz zz zz zz 0 N "E, ,--I N. CO to t0 N N J cc (/1 N - N L 'o to to 03 to ✓ C Ol O1 01 O1 = D CO 0 tto t(0 tto tto 00 CO7 to t0w tO 1-1 1-11-1 - y�a 0 0 0 0 N N NI 2 p m O\ mcn 0\t 0\1 O\i 0\1 t i ..;:1:-.: O O a Z OLL Q 0 Z Z a+ z i - m aai N i, ioC v iw u .3- L.- w om a O g o O O Z c v a) ai V w 0 Z Z Z Z j L Zu o v w (7 `w O as Z v• 3 v u v z -o v1 w n p n p n a a ce a- a 0 a 2 a 0 Yi1 3 (Yi1 c .-2 n H L7 0 vv a N .-N N to Lo h (n N ti O e-1 ey N N VD t0 t0 CV K co co co UD UD t0 t0 Cr, W LID Z N n N n m O N CO LnN D Cr ✓ ttOO O Ln CO 2 V M Cr t0 ✓ u1 co O m v . al ca N CO01 z C A Z _, 2 w co a L9 = 'O 2 0 y 3 V F N V N V Loo a O N o O 2 K ao a a - N al D 2 N 0 .-N c 2 tD co e-1 N v1 0 O 0 N 01 N O Z 1-1 Cr e-- m a ii .-1 01 - 01 u A N o M a Q V1 M N m M O V1 ey 0 CO t0 N N a! O O O N m ~ e-I e-1 CO N t0 N 2 LID to to Lr, 0 O1 O O1 O1 5 NIn M N NLn L a CO CO CO CO a t o 2W 01 0 O 1- T 0 Exhibit "B" (Certificate of Final Completion) Exhibit D-2 — Form of Certificate of Final Completion SIEMENS Certificate of Final Completion PROJECT NAME: City of Port Arthur Phase 3 Performance Contract— Water Meters &AMI CLIENT: City of Port Arthur, Texas , CERTIFICATE DATE (mm/dd/yyyy): September 20, 2016 PROJECT NUMBER: 440P-139862 (Client#= 14-406) All elements of the project Work have been reviewed by the CLIENT and have been found, to the best of the CLIENT's knowledge, to be at Final Completion. All items noted in the Outstanding Items Lists associated with Certificate(s) of Substantial Completion have been resolved, and all Work as defined in Exhibit A of the Agreement is complete. The failure of the CLIENT to note items requiring completion or correction does not relieve the contractual responsibility of Building Technologies Division of Siemens Industry, Inc. to complete or correct the Work. Work found to require completion or correction after the date of this Certificate, but within the warranty period shall be promptly corrected in accordance with the Agreement's warranty provisions. Building Technologies Division of Siemens Industry, Inc. has reviewed the project Work, as well as all contractual requirements, and the requirements for Final Completion have been met. Building Technologies Division of Siemens Industry, Inc. Representative: Chad Nobles Signature: MG`p/ 414— Date: 9-20-2016 The CLIENT accepts the project Work as meeting the requirements for Final Completion. CLIENT: CLIENT Representative: Signature: Date: Page 1 of 1 Siemens Industry, Inc., Building Technologies Division Exhibit D-2—Certificate of Final Completion v. 2014