HomeMy WebLinkAboutPR 19616: CERTIFICATE OF GUARANTEE FOR CONSTRUCTION OF THE WATER STORAGE STANDPIPE ON 61ST STREET DERRICK FREEMAN,MAYOR RAYMOND SCOTT,JR.,MAYOR PRO TEM BRIAN MCDOUGAL CITY MANAGER • COUNCIL MEMBERS: City of f / SHERRI BELLARD,TMRC TIFFANY HAMILTON ` CITY SECRETARY MORRIS ALBRIGHT x KIETH RICHARD - VALECIA TIZENO WILLIE`BAE"LEWIS JR. n r t r t h tr r CITY ATTORNEY OSMAN SWATI CHARLOTTE MOSES Texas KAPRINA RICHARDSON FRANK Date: December 28, 2016 To: Brian McDougal, City Manager From: Jimmie Johnson, Ph.D., Assistant City Manager RE: Proposed Resolution No. 19616 • Nature of the Request: City Council awarded a contract, per Resolution #14-390, for the construction of a Water Storage Standpipe on 61St Street to BDS Constructors LLC dba MK Constructors of Vidor, TX, in the amount of$2,825,250.00. The project is complete. The project engineer, Arceneaux Wilson & Cole LLC, has approved the final pay, Invoice in the amount of $141,262.50. Arceneaux Wilson & Cole LLC, has also submitted the Engineer's Certificate of Completion, Contractor's Certificate of Guarantee, Contractor's Certificate of Release, and the Certificate of Construction Completion (Form 6-9) for the project. Staff Analysis, Considerations: None. Recommendation: We recommend that the City Council approve Proposed Resolution No. 19616 authorizing the City Manager to pay final invoice of$141,262.50, which is the retainage held by the City, to the contract between the City of Port Arthur and BDS Constructors LLC dba MK Constructors of Vidor, TX, for construction of the Water storage Standpipe on 61St Street. Budget Considerations: This project is funded by the General Land Office. This is Project No. I22SPW, from fund 145. P. R. No. 19616 01/20/17 ds Page 1 of 3 RESOLUTION NO. A RESOLUTION AUTHORIZING ACCEPTANCE OF THE ENGINEER'S CERTIFICATE OF COMPLETION, CONTRACTOR'S CERTIFICATE AND RELEASE AND CONTRACTOR'S CERTIFICATE OF GUARANTEE FOR CONSTRUCTION OF THE WATER STORAGE STANDPIPE ON 61st STREET AND AUTHORIZING THE CITY MANAGER TO SIGN THE CERTIFICATE OF ACCEPTANCE ON BEHALF OF THE CITY OF PORT ARTHUR AND APPROVAL OF FINAL PAYMENT (5% RETAINAGE FEE) IN THE AMOUNT OF $141,262.51; ACCOUNT NO. 145-1201-532.59-00,PROJECT I22SPW WHEREAS, BDS Constructors LLC dba MK Constructors has completed the contracted project to the satisfaction of the project engineer and the City staff; and, WHEREAS, the City has received the Engineer's Certificate of Completion, dated November 14, 2016 from Arceneaux Wilson & Cole of Port Arthur, Texas, stating that to the best of their knowledge, the Water Storage Standpipe on 61St Street project has been completed in general accordance with City standards, a copy is attached hereto and made a part hereof as Exhibit "A", together with a Contractor's Certificate and Release (Exhibit "B") and Contractor's Certificate of Guarantee (Exhibit "C"), executed by BDS Constructors LLC dba MK Constructors of Vidor, TX; and, WHEREAS, the retainage for this project is five percent (5%) of the work completed and billed, and the project engineer, Arceneaux Wilson & Cole LLC approves final payment to BDS Constructors LLC dba MK Constructors of Vidor, TX, in the amount of$141,262.51 (see within Exhibit"A"). P. R. No. 19616 12/28/16 ds Page 2 of 3 NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PORT ARTHUR: THAT,the facts and opinions in the preamble are true and correct; and, THAT, the City Manager of the City of Port Arthur is hereby authorized to execute on behalf of the City of Port Arthur a Certificate of Acceptance (Exhibit "F") for the completion of the Water Storage Standpipe on 61St Street. THAT, final payment be made to BDS Constructors LLC dba MK Constructors in the amount of$141,262.51; and, THAT, a copy of the caption of this Resolution be spread upon the Minutes of the City Council. READ,ADOPTED AND APPROVED THIS day of , 2017 at a Regular Meeting of the City Council of the City of Port Arthur, Texas, by the following vote: AYES: Mayor - Council members , NOES: . Derrick Freeman Mayor P. R. No. 19616 01/20/17 ds Page 3 of 3 ATTEST: APPROVED AS TO FORM: • Sherri Bellard Valecia Tizeno � City Secretary City Attorney I APPROVED FOR ADMINISTRATION: it)/ ItAsp Brian McDougal Clifton Williams City Manager Acting Purchasing Manager Jimmie Johnson, Ph.D. Assistant City Manager APPROVED FOR FUNDING: ,4114d1 AP• Harold Hankins City Comptroller EXHIBIT "A" (Arceneaux Wilson& Cole, LLC, Recommendation for Final Payment) ARCENEAUX WILSON&COLE engineering I surveying I planning November 15, 2016 Dr.Jimmie Johnson City of Port Arthur 444 4d, Street Port Arthur,Texas 77642 RE: RECOMMENDATION for FINAL PAYMENT and RELEASE of RETAINAGE Water Storage Standpipe on 61st Street AWC NO.CPA-865 Dear Dr.Johnson: Attached for your records are the project completion documents for the Water Storage Standpipe on 61st Street Water Project. These documents include the Engineer's Certificate of Completion, Contractor's Certificate of Guarantee, Contractor's Certificate of Release and the Certificate of Construction Completion(Form 6-9). These documents were executed showing a balance due the Contractor from the City. This balance is the retainage withheld from the monthly estimates as well as any payments due from completion of work. As stipulated in the contract documents the retainage for this project is five percent (5%) of the work completed and billed. It is our recommendation that the retainage held by the City be released to the Contractor and final payment made. This will result in a final payment to BDS Constructors LLC dba MK Constructors from the City of Port Arthur in the amount of One Hundred Forty-One Thousand Two Hundred Sixty-Two Dollars and Fifty- One Cents ($141,262.51). Should you have any questions or require further information please do not hesitate to contact me at 409-724-7888. Very truly yours, ARCENEAUX WILSON&COLE LLC eestan Cole, PE Vice-President Attachments. Engineer's Certificate of Completion Contractor's Certificate of Guarantee Contractor's Certificate and Release Final Pay Estimate No 17 409.724.7888 2901 Turtle Creek Dr.,Suite 320 Port Arthur,TX 77642 Engineering Surveying awceng.com 10194049 10194049 EXHIBIT "B" (Arceneaux Wilson& Cole, LLC, Final Invoice) CPA-865 Contract Amount $ 2,825,250.00 Invoice No.1 $ 116,066.25 Invoice No.2 $ 22,823.75 Invoice No. 3 $ 313,980.70 Invoice No.4 $ 218,405.00 Invoice No.5 $ 59,389.25 Invoice No.6 $ 511,586.40 Invoice No.7 $ 531,262.80 Invoice No.8 $ 203,097.17 Invoice No.9 $ 98,382.00 Invoice No. 10 $ 59,029.20 Invoice No.11 $ 59,029.20 Invoice No.12 $ 37,814.75 Invoice No. 13 $ 125,705.90 Invoice No. 14 $ 151,049.52 Invoice No. 15 $ 119,413.10 Invoice No. 16 $ 56,952.50 Total $ 2,683,987.49 Invoice No. 17 (Final) $ 141,262.51 (Estimate No:_ _if17 Retainage Only 365 Calendar days allowed begin 20 calendar days used as of this estimate. 365 Amount of days used for total project. %Complete Work Done To Date Mobilization,Bonds, Insurance,Onsite Facilities,Project Sign,Complete. $ 162,900.00 100% $ 162,900.00 Foundation(including design,site prep,fill materials,concrete,pile cap,finishing grading),Complete in Place. $ 92,450.00 100% $ 92,450.00 Test pile 16" Diameter x 80',Complete in Place. $ 4,000.00 100% $ 4,000.00 Production Piles(number&size determined by design),Complete in Place. $ 241,150.00 100% 5 241,150.00 Design&Construction of 2,400,000 Gallons coated steel Water Standpipe as specified and shown on the drawings,and in accordance with supplier design,Complete in place. $ 2,071,200.00 100% $ 2,071,200.00 Connection to existing 16" PVC Waterline incuding 16-Inch,Gate Valve and Box{GV&B), 16" DI Tee,and associated appurtenances, Complete in Place $ 16,100.00 100% $ 16,100.00 Manifold incuding all DI Piping,Di fittings,all Gate Valves,16"Altitude Valve,supports,and all associated appurtenances,Complete in Place $ 105,850.00 100% $ 105,850.00 Site Work incuding but not limited to clearing &grubbing,grading(including any required excavation and/or backfill),access road,chain- link fence and 10'gate,and associated appurtenances,complete in place. $ 80,200.00 100% $ 80,200.00 Painting,Complete in Place. $ 5,000.00 100% $ 5,000.00 Disinfection of Standpipe and Piping, Complete in Place. $ 5,000.00 100% $ 5,000.00 Electrical and Instrumentation,Complete in Place. $ 16,900.00 100% $ 16,900.00 SCADA System,Complete in Place. $ 18,000.00 100% $ 18,000.00 Storrnwater Prevention Pollution Plan including all required maintenance and inspections $ 5,500.00 100% $ 5,500.00 Design&Implementation of Trench Safety System,Complete in place. $ 1,000.00 100% $ 1,000.00 Total of Project $ 2,825,250.00 $ 2,825,250.00 5%Retalnage _, $ Total of Previous Payments $ (2,683,987.50) Amount Due Contractor this Estimate _ $ 141,262,50 EXHIBIT "C" (Engineers Certificate of Completion) ENGINEER'S CERTIFICATE OF COMPLETION Project: Water Storage Standpipe on 61'Street Date Of Issuance: November 15,2016 Owner(s): City of Port Arthur Owner's Project No.: CPA-865,Contract No. 1 Engineer: Arceneaux Wilson&Cole LLC Contractor: I3DS Constructors LLC dba MK Constructors This Engineer's Certificate of Completion applies to all Work under the Contract Documents or to the following specified parts thereof: TO City of Port Arthur [OWNER] AND TO BDS Constructors LLC dba MK Constructors ]CONTRACTOR] The Work to which this Certificate applies has been inspected by authorized representatives of Owner, Contractor and Engineer, and that Work is hereby declared to be complete in accordance with the Contract Documents on November 14,2016 DATE OF COMPLETION 417, Executed by Engineer ony�ww 7r �!,/` /6 , 2016 g'�P''"~�r- tt$j r KEESTAN X.COLE k 114225 .1„, BY: RCENEAUX WILSON 8 COLE LLC [SEAL] 1/] LnA>I '. M DAVIS-BACON ACT/LABOR STANDARDS kill(' > \,/ `ji Certificate of Construction Completion (Form 6-q) (Revised: 6/5/12) (SUBMIT ONE FOR EACH PRIME CONSTRUCTION CONTRACT) Grantee: 13BS Constructors LLC dba MK Constructors Land Office-DR Contract No: DRS220148 This is to certify that a final inspection of the project described below was conducted on the 14th day of_ November 2016 Contract was entered into on the 8t11 day of October,2014 between the city/county of Port Arthur Orange County and DDS Constructors LLC dba for the Construction of Water Storage Standpipe on 61st Street MK Constructors This is to further certify that: 1. The work has been completed in accordance with the plans and specifications and all addenda, change orders and supplemental agreements thereto, with the following exceptions: 2. The sum of$ 0.00 , deducted from the final payment to the Contractor is a fair and equitable settlement for the foregoing excepted work. 3. The Contractor has presented on behalf of itself and its sureties, satisfactory evidence that he or she will repair, replace and make good any faulty workmanship and/or materials discovered in the work within a period of 12 months from this date,as provided in the Contract. 4. Amount of Original Contract $ 2,825,250.00 Cumulative Change Orders $ 0.00 Final Amount of Contract $ 2,825,250.00 Less Previous Payments $ 2,683,987,49 Less Deductions (from #2 above) $ 0.00 FINAL PAYMENT(Balance) $ 141,262.51 5. The Final Payment in the amount above is now due and payable. One Hundred Forty One Thousand Two Hundred Sixty-I wo Dollars and Fitly One Cents (5141,262.51) 6. Final Quantities: Activity Code Category Project Name Description Metric(Qty) P21427-1a Water Facilities-la Water Storage Standpipe on 61st Street Install 2.5M gallon Tank 1 See Attachment 1 for assistance with completing the above table Certified b : ngtneer pntrac Chief Executive Officer Vice President Title Title Title ARCENEAUX WILSON&COI E LI.0 BUS Constructors l LC dba MK Constructors Firm Firm City/County of (;CA) — Disaster Recover' Program Forms Page 1 of 1 EXHIBIT D (Contractor's Certificate and Release) CONTRACTOR'S CERTIFICATE AND RELEASE FROM: BDS Constructors LLC dba MK Constructors (Name of Contractor) �M TO: City of Port Arthur (Owner) REFERENCE CONTRACT NO CPA-865, Contract No. 1 ENTERED INTO 8th DAY OF October, 2014 BETWEEN THE City of Port Arthur AND BDS Constructors LLC dba MK Constructors (Name of Contractor) OF Vidor. Texas (CKY1 (Stale) -------------- - FOR THE Water Storage Standpipe on 61' Street (Name of Project) KNOW ALL MEN BY THESE PRESENTS: 1. The undersigned hereby certifies that there is due from, and payable by, the Owner to the Contractor under the contract and duly approved Change Orders and modifications the balance of One Hundred Forty One Thousand Two Hundred Sixty-Two Dollars and Fifty One Cents ($141262.511 -- ----- 2. The undersigned further certifies that in addition to the amount set forth in Paragraph 1, there are outstanding and unsettled the following items which he claims are just and due and owing by the Owner to the Contractor: (a) (b) — -- -- -- (c) — (d) __---. (Itemize claims and amounts due) (If none,so state) 3. The undersigned further certifies that all work required under this contract,including work required under Change Order(s)numbered 1 , has been performed in accordance with the terms thereof, and that there are no unpaid claims for materials, supplies, or equipment and no claims of laborers or mechanics for unpaid wages arising out of the performance of this contract, and that the wage rates paid by the Contractor were in conformity with the contract provisions relating to said wage rates. 4. Except for the amounts stated under Paragraphs 1 and 2 hereof, the undersigned has received from the Owner all sums of money payable to the undersigned under, or pursuant to, the above mentioned contract or any modifications or change thereof. 5. That in consideration of the payment of the amount stated in Paragraph 1 hereof, the undersigned does hereby release the Owner and Operator from any and all claims arising under or by virtue of this contract, except the amount listed in Paragraph 2 hereof due from the Owner; provided, however, that if for any reason the Owner does not pay in full the amount stated in Paragraph 1 hereof, said deduction shall not affect the validity of this release, but the amount so deducted shall be automatically included under Paragraph 2 as an amount which the Contractor has not released but will release upon payment thereof. The Contractor further certifies that upon the payment of the amount listed in Paragraph 2 hereof, and of any amount which may be deducted from Paragraph 1 hereof, he will release the Owner and Operator from any and all claims of any nature whatsoever arising out of said contract or modification thereof, and will execute such further releases or assurances as the Owner and Operator may request. IN WITNESS WHEREOF, the undersigned has signed and sealed this instrument this VI day of "al CIL, ` ,20\LR [SEAL] BDS Constructors LLC dba MK Constructors (Contractor) BY: ItA.4 4 J---- - (Signature and Title of Officer)Vice President 'i\\ C \ ..a, 46\...)0L.)3(\, being first duly sworn on oath, deposes and says, first, that (Arrant) he is the Vice-President of _ BDS Constructors LLC dba MK Constructors (Title) (Name of Company) second,that he has read the foregoing certificate by him subscribed as Vice-President (Title) of_ BDS Constructors LLC dba MK Constructors (Name of Company) Affiant further states that the matters and things stated herein are true. Subscribed and sworn to before me this day of �� 2014. ------ — My commission expires 141 3 it 20 ' (Date) I - 4 4 I. '1 .�l"""" CARRIE EVE VINCENT ����"`���`: (Notary Pu Ire �,4� �,:NOto1y PubllC,State of Texos M ry ) 3�y• f Comm.Expires 04-132020 ':f„•,j,,;9 Notary ID 128955139 EXHIBIT "E" (Contractor's Certificate of Guarantee) CONTRACTOR'S CERTIFICATE OF GUARANTEE FROM: BDS Constructors LLC dba MK Constructors TO: City of Port Arthur FOR: Arceneaux Wilson&Cole LLC REFERENCE CONTRACT NO, CPA-865 , Contract No. 1 ENTERED INTO THE 8'h DAY OF October, 2014 BETWEEN THE City of Port Arthur AND BDS Constructors LLC dba MK Constructors OF Vidor, Texas FOR: Water Storage Standpipe on 6151 Street KNOW ALL MEN BY THESE PRESENTS: 1. BDS Constructors LLC dba MK Constructors does hereby guarantee all of the work done under the above referenced contract to be free from faulty materials in every particular, and free from improper workmanship, and against injury from proper and usual wear; and agrees to replace or re- execute without cost to the Owner and Operator such work as may be found to be improper or imperfect, and to make good all damage caused to other work or materials, due to such required replacement or re-execution. 2. This guarantee shall cover a period of one (1) year from the date of acceptance of all work under this Contract, as evidenced by the Engineer's Certificate of Completion. 3. This Certificate is given in connection of the final payment under the contract between the Owner and BDS Constructors LLC dba MK Constructors and with the knowledge that it will be relied upon in making such payment and that such payment would not be made except upon the truth of the matter contained in this affidavit. 1/2 IN WITNESS WHEREOF, the undersigned has signed and sealed this instrument this rl day of 211L_ l v ts— -_, 20 k . [CORPORATE SEAL] BDS Constructors LLC dba MK Constructors (Contractor) BY: ‘' {\1 .Y3( , being first duly sworn on oath, deposes and says, first that he is the Vice President of BDS Constructors LLC dba MK Constructors second,that he has read the foregoing certificate by him subscribed as Vice President of BDS Constructors LLC dba MK Constructors Affiant further states that the matters and things stated herein are true. tk4,10 L------ (Affiant) Subscribed and sworn to before me this 9 day of ItarldacLS , 20 i . My commission expires - I '3 I W (Date) o,"" '�•, CARRIE EVE VINCENT acoi, ?_: :Notary Public.State of Texos av�.� �;Comm.Expires 04-13-2020 %rte' Notary ID 128955139 (Notary Public) 2/2 EXHIBIT "F" (Contractor's Certificate of Acceptance) City of Port Arthur, Texas Department of Utility Operations CERTIFICATE OF ACCEPTANCE FOR THE WATER STORAGE STANDPIPE ON 61st STREET PROJECT IN THE CITY OF PORT ARTHUR To: BDS Constructors LLC dba MK Constructors This document is to certify that the City of Port Arthur, Texas accepts the completion of the construction of the Water Storage Standpipe on 61st Street Project on the basis of the City of Port Arthur, Texas Utility Operations Department, the Engineer's Certificate of Completion, the Contractor's Certificate and Release, and Contractor's Certificate of Guarantee from BDS Constructors LLC dba MK Constructors. Brian McDougal City Manager ATTEST: Sherri Bellard City Secretary