HomeMy WebLinkAboutPR 19859: CHANGE ORDER NO. 1, MIKE BARNETT CONSTURCTON . , , ,,, ,, ,,, ,, :: (inn oo ,0 or! rthu.� Te,.rns www.PortArthurTx.gov INTEROFFICE MEMORANDUM Date: August 1, 2017 To: The Honorable Mayor and City Council Through: Brian McDougal, City Manager From: Adam Saunders, Civic Center Director RE: (PR 19858) Introduction: The intent of this Agenda Item is to seek the City Council's approval for the City Manager to increase the contract for removing and replacement of flooring and sub flooring at the Sabine Pass Community Center in the amount of$1,500. Background: Mike Barnett Construction was awarded to the contract to remove and replace flooring and sub flooring at the Sabine Pass Community Center in the amount of$28,950. Once Mike Barnett began removing the flooring, it was discovered that the original flooring was incorrectly installed. Civic Center agreed for a Change Order in the amount of$1,500 to install 6 rows, 75' long, of 2" x 4"YP attached to floor joists for supporting end of plywood joints. The new total will be $30,450. Budget Impact: Civic Center will charge the additional amount to Civic Center Building Maintenance Account #001-1061-518.32-00. Recommendation: It is recommended that City Council approve the City Manager to agree to the change order for $1,500, as discussed and/or outline above. "Remember,we are here to serve the Citizens of Port Arthur" P.O.Box 1089 x Port Arthur,Texas 77641-1089 x 409.983.8101 x FAX 409.982.6743 PR No. 19859 07/24/2017 CEWJ PAGE 1 of 2 RESOLUTION NO. A RESOLUTION AUTHORIZING THE CITY MANAGER TO EXECUTE CHANGE ORDER NO. 1 TO THE CONTRACT BETWEEN THE CITY OF PORT ARTHUR AND MIKE BARNETT CONSTRUCTION OF PORT NECHES, TEXAS, FOR THE REMOVAL AND REPLACEMENT OF FLOORING & SUB FLOORING AT THE SABINE PASS COMMUNITY CENTER, INCREASING THE CONTRACT BY $1,518.00 TO A NEW TOTAL OF $30,468.00; FUNDING AVAILABLE IN CIVIC CENTER BUILDING MAINTENANCE ACCOUNT NUMBER 001-1061-518.32-00. WHEREAS, per Resolution No. 17-113, the City entered into an agreement with Mike Barnett Construction of Port Neches, Texas, for the removal and replacement of flooring & sub flooring at the Sabine Pass Community Center, in the amount of$28,950; and WHEREAS, the Civic Center discovered during current construction that the original flooring was constructed wrong; and WHEREAS,the current contractor has to install 6 rows, 75' long, of 2" x 4"YP attached to floor joists for supporting end of plywood joints, see Change Order 1 attached hereto as Exhibit"A". NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PORT ARTHUR: Section 1. That the facts and opinions in the preamble are true and correct. Section 2. That the City Council hereby authorizes the City Manager to execute Change Order No. 1 to the contract between the City of Port Arthur and Mike Barnett Construction of Port Neches, Texas, for the removal and replacement of flooring & sub flooring at the Sabine Pass Community Center, increasing the contract by $1,518.00 to a new total of $30,468.00, in substantially the same form as attached hereto as Exhibit "A", with funding available in Civic Center Building Maintenance Account No. 001-1061-518.32-00. Section 3. That a copy of the caption of this resolution shall be spread upon the Minutes of the City Council. READ, ADOPTED AND APPROVED on this day of August, A.D., 2017, at a Regular Meeting of the City Council of the City of Port Arthur, Texas, by the following vote: AYES: PR No. 19859 07/24/2017 CEWJ PAGE 2 of 2 Mayor: Councilmembers: NOES: Derrick Freeman, Mayor ATTEST: Sherri Bellard, City Secretary A' ' ' I VED • TO FORM: Val Tizeno, City A orney APPROVED FOR ADMINISTRATION: Brian McDougal, City Manager Adam Saunders, Civic Center Director APPROVED AS TO AVAILABILITY OF FUNDS: Rosie Vella, CPA/CGFO Inter'm Director of Finance 41/ CIA/4w Clifton Williams, CPPB Purchasing Manager EXHIBIT "A" CHANGE ORDER# 1 DATE: July 21, 2017 ORIGINAL AGREEMENT DATE: 5-9 - M,K E A 4 4,4 E.-rr' ,CONSTRUCTION PROJECT DESCRIPTION: Removing and replacement of flooring and sub flooring at the Sabine Pass Community Center ORIGINAL CONTRACT TERM: NEW CONTRACT TERM including the CHANGE ORDER will be: CHANGE TO CONTRACT AMOUNT: r,S i ORIGINAL CONTRACT AMOUNT:$ )76° 00 CONTRACT AMOUNT due to this CHANGE ORDER vi ill be: .ft 56, 16e. coo MIKE BARNETT CONSTRUCTION ignatureq..P.- /,4 Ale£ BAVALE7C-F Printed Name CITY OF PORT ARTHUR Brian McDougal City Manager a + MIKE BARNETT CONSTRUCTION 7/20/17 City of Port Arthur Attn: Clifton Williams /Adam Saunders Sabine Pass Community Center Re: Flooring Support We propose to furnish all labor, materials and insurance to perform the scope of work below, for a sum not to exceed fifteen hundred eighteen dollars and no cents ($1,518.00.00). 1. Install 6 rows, 75' long, of 2" x 4"YP attached to floor joists for supporting end of plywood joints. Thank you for the opportunity to bid on this project. If we can be of any further assistance please feel free to call me at anytime. If you would like for us to perform the above scope of work, please sign below and return to us as soon as possible. At that time, you will be added to the work to perform list. Payment is due upon completion. MIKE BARNETT CONSTRUCTION Lance Barnett Accepted General Manager Mike Barnett Construction,Inc.,1701 Port Neches Ave.,Port Neches,TX 77651 Phone(409)727-5673 Fax(409)727-2905