INTEROFFICE MEMORANDUM
Public Works Department — Administrative Division
Date: December 19, 2017
To: Harvey Robinson, Interim City Manager
From: Armando Gutierrez, Jr., P. E., Public Works Director
RE: P. R. No. 20058, Installation of Scales
Introduction:
Authorize an agreement with SCS Engineers of Bedford, Texas for design services related to
the proposed installation of weight scales at the Landfill, reconfiguration of the entrance
driveway, new weight scale office building, and landfill permit modification accordingly for a
fee not to exceed $35,000.
Background:
In 2002, the City entered into a professional service agreement with SCS Engineers of
Bedford, Texas for engineering and technical services associated with the compliance
management plan for the Landfill. Since then SCS Engineers have assisted the City with
Landfill permitting, permit modifications, air quality and water monitoring and other landfill
management issues. As part of the plan, weight scales are to be installed to better measure the
purchase of daily cover soil, accurately measure the waste received, calculate TCEQ disposal
fees, and obtain better data for calculating remaining landfill life and related management and
operating plans.
Staff met with SCS Engineers to review the proposed scope and add geotechnical testing and a
30% design engineering report for better management of the final design. Staff also reviewed
cost and find it reasonable.
Budget Impact:
Funds are available in the Public Works Landfill Division Professional Services account no.
625-1801-533.92-00.
Recommendation:
Recommend approval of the agreement with SCS Engineers for the engineering services
related to the installation of scales at the City Landfill for a fee not to exceed $35,000.
/aw
"The vocation of Public Works is to serve the Public"
P.R.20058
12/19/17 aw
RESOLUTION NO.
A RESOLUTION AUTHORIZING THE CITY MANAGER TO EXECUTE
AN AGREEMENT WITH SCS ENGINEERS OF BEDFORD, TEXAS, FOR
ENGINEERING SERVICES PERTAINING TO THE INSTALLATION OF
SCALES AT THE CITY LANDFILL IN THE NOT TO EXCEED
AMOUNT OF $35,000.00; FUNDS ARE AVAILABLE IN THE PUBLIC
WORKS LANDFILL PROFESSIONAL SERVCIES ACCOUNT NUMBER
625-1801-533.92-00.
WHEREAS, the Texas Commission on Environmental Quality (TCEQ) has approved a
permit modification allowing for the implementation of scales at the Landfill; and,
WHEREAS, adding these scales will better measure the purchase of daily cover soil,
accurately measure the waste received, calculate TCEQ disposal fees, and obtain better data for
calculating the life of the landfill; and,
WHEREAS, an engineer will be required to perform the design phase for this
installation; and,
WHEREAS, SCS Engineers has performed numerous projects for the City regarding the
Landfill's compliance management plan; and,
WHEREAS, SCS Engineers of Bedford, Texas will perform the engineering service for
a total price not to exceed$35,000 billed according to Exhibit"A"; now,therefore,
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PORT ARTHUR:
THAT the City Manager is hereby authorized to execute an agreement with SCS
Engineers of Bedford, Texas to provide engineering services for the installation of scales at the
City Landfill for a total price not to exceed$35,000, as delineated in Exhibit"A".
THAT funding is available in FY2018 Budget Account No. 625-1801-533.92-00.
THAT a copy of the caption of this Resolution be spread upon the Minutes of the City
Council.
READ, ADOPTED, AND APPROVED this day of
P.R.20058
12/19/17 aw
A.D., 2018, at a Meeting of the City Council of the City of Port Arthur,
Texas, by the following vote: AYES:
Mayor: •
Councilmembers:
NOES:
Mayor
ATTEST: APPROVED AS TO FORM:
City Secretary City Attorney
APPROVED FOR ADMINISTRATION: APPROVED AS TO AVAILABILITY
OF FU N DS:
AP..
Harvey Robinson Andrew Vasquez
Interim City Manager Director of Finance
ilt
Armando Gutierrez, Jr., P. E. Cli 'on Williams
Director of Public Works Purchasing Manager
P.R.20058
12/19/17 aw
Exhibit "A"
Solid Waste Management Consultants 1901 Central Drive,Suite 550
Offices Nationwide • Bedford, Texas 76021
www.scsengineers.com
817.571.2288 Main
SCS ENGINEERS
November 10, 2017 Proposal No. 160093216
Mr. Armando Gutierrez Jr., PE, CFM
Director of Public Works
City of Port Arthur
444 4th Street
Port Arthur, TX 77640
Subject: Scope of Engineering Services to Provide
Plans, Specifications and Bid Documents for the Installation of Scales and Related Services
at the City of Port Arthur Landfill
Dear Mr. Gutierrez:
Per your request, SCS Engineers (SCS) has revised this proposal to include geotechnical testing and a
30% design engineering report with recommendations. This report will provide assurance that all parties
agree with the design approach prior to proceeding into preparation of the plans, specifications, and bid
documents for the installation of scales at the Port Arthur landfill. With the recent issuance of TCEQ's
approval of the related permit modification, this is the next step in the process of implementing the
installation of scales at the landfill. As you know, the scales will assist the City in (1) controlling the cost
of purchasing soil, (2) accurately determining the tonnage of waste received, and (3) improved accuracy
of calculating the TCEQ disposal fees.
Our proposed scope of services also includes assistance during bidding and construction phases of the
project.
We appreciate the opportunity to be of continued service to the City of Port Arthur. Please call with any
questions or comments.
Sincerely, , ,
J
1
Kevin D. Yard, P.E., BCEE Jeffrey Arrington, P.E.
Vice President Project Manager
SCS ENGINEERS SCS ENGINEERS
TBPE Registration No. F-3407
Attachments: Project Approach
cc: Mr. Rawetts Baaheth, Sr., City of Port Arthur City Hall
Mr. Justin Thomas, City of Port Arthur Landfill
.K'BD'P'vposalslPod Mh..,2016-IT.160261216.Scaly c-pla.ub,d doo P11101?Pt An SM.biO C-Phos docs
City of Port Arthur Landfill Engineering Services for Prep of Bid Documents for New Scales
PROJECT APPROACH
ENGINEERING SERVICES FOR PREPARATION
OF BID DOCUMENTS FOR NEW SCALES AT THE
CITY OF PORT ARTHUR LANDFILL
BACKGROUND
SCS has developed the following scope of services to assist the City with installing scales at the
Port Arthur Landfill. This scope includes the preparation construction plans, specifications and bid
documents as well as providing technical support in bidding, award and construction representation.
SCOPE OF SERVICES
Task 1: Prepare 30% Design Engineering Report
This task will include compiling the background information required to expand on the preliminary
design of the scales and to prepare the bid documents for the construction of the scales and related
facilities. This will include consideration of the currently permitted location and an alternate
location. These locations will be assessed in terms of the following:
• Efficiency of obtaining the tare weights of the empty vehicles
• Overall traffic efficiency
• Need to relocate the gatehouse and related utilities
• Consistency with currently approved TCEQ permit documents
• Other considerations that the City deems appropriate.
It should also be noted that a relocation of the location of the scales as proposed in the recently
approved permit application would not only entail the relocation of the gate house but also a permit
modification requiring the approval of the Texas Commission on Environmental Quality.
Following completion of this draft 30% report, we will discuss the report contents, including the
discussion of alternate scale and scalehouse locations.
It is assumed that an above-ground type scale with a concrete deck and a standard readout
instrument for the scale house would be most appropriate for the City's landfill. Necessary
background information will include:
• Standard(boilerplate) front-end bid documents from the City's purchasing department.
• Reviewing pertinent operational data from the City.
• Develop a short list of scale manufacturers for bidding.
• Summarizing desirable characteristics of scales from short-list of manufacturers.
• Verify entrance road geometry with the City
As a cost saving measure, it is assumed that this communication with the City can be managed with
a conference call, at which time an agreement can be reached on the location of the scales and
scalehouse.
.N:'BO'Pmpemn b'.P. 111.2a l6-ITI602812I6.Scale c-plono-bid do.PI 110I P.%Et Sealca NdC-Plnn..do. SCS ENGINEERS
City of Port Arthur Landfill Engineering Services for Prep of Bid Documents for New Scales
Task 2: Geotechnical Testing of Subsurface for the Design of the Scale Support
Structure
SCS will subcontract with Science Engineering LTD to perform 2 soil borings up to 25 feet deep at
the proposed location of the scales to determine the subsurface conditions and provide foundation
recommendations for the scale platform.
Task 3: Preparation of Plans, Specifications, and Bid Documents for the
Installation of Scales
In view of the turn-key installation services provided by a number of the scale manufacturers, SCS
will prepare bid documents that will enable the scale manufacturers to respond to this procurement
opportunity. This project also includes the widening of the landfill site entrance road to facilitate
smooth flow of traffic.
This task assumes that we will refine the concept design of the scale facility included in the permit
documents in a manner suitable for inclusion in the bid documents. Drawings to be incorporated
into the bid package will include, at a minimum,the following:
• Cover sheet and Location Map
• Dimension Control and Paving Plan
• Site Grading and Drainage Plan
• Sections and Details
This task will also include compiling the general and technical specifications for the construction.
For this Scope of Services, SCS has assumed that the City will provide the front-end documents that
are applicable and current. The technical specifications will be developed by SCS for the project.
This task includes development of an engineer's cost estimate including performing the necessary
quantity take-offs for line items included in the scope of work for the project. Line items for this
project will include such items as: mobilization/demobilization, scale equipment, scale installation,
ancillary equipment, paving, etc. The engineer's estimates of probable cost of construction will be
supported by volume quantity calculations for each line item.
Task 4: Bidding Assistance
This task includes assistance to the City during bidding, including:
• Preparation of bid document packages for distribution to contractors and manufacturers.
• Distribution of bid documents to contractors. For this task, SCS has assumed that the bid
documents can be distributed electronically to contractors and manufacturers that are
interested in bidding the job.
• We have assumed that a pre-bid conference will not be required for the project.
• Receiving written comments and questions from bidders, and coordinating responses with
City staff.
• Review of bidders' qualifications.
• Review and compilation of bids, and submittal of award recommendation to City.
Bpo
DoProwls Pon Arthurt201,1,14028121fi.Scala c-Plon.-bld does\PI I IP,' VI SooIn PIno.doc< SCS ENGINEERS
City of Port Arthur Landfill Engineering Services for Prep of Bid Documents for New Scales
Task 5: Construction Representation
SCS will assist the City during the construction phase to provide coordination with the scale
contractor and interpretation of plans and specifications. Our services during this phase will consist
of the following:
• Attendance by a SCS representative at the pre-construction meeting with City staff and the
selected contractor.
• Review and response to clarification requests or change order requests received from
contractor.
• A construction site visit during critical stage of the scale construction.
• Review of scale shop drawings.
• SCS will conduct a final walk-through with City and Contractor. If necessary, SCS will
provide the contractor with a punch list of items that need to be addressed prior to final
acceptance by the City.
• Confirmation of final acceptance of the completed project by SCS.
Allowance
The above scope is based on our years of experience with similar projects and our current
understanding of site conditions. As you know, with construction projects and bidding,
unanticipated issues may arise. To provide support to address such issues if they arise, we have
established this Allowance task with a budget of$3,000. This budget will only be used with the
City's prior authorization on a time-and-materials basis using the SCS fee schedule in effect at that
time. Further, any charges to this task will be fully detailed in our invoice.
PROJECT SCHEDULE
We are ready to proceed with the project upon receiving authorization to proceed.
FEE
SCS proposes to provide these services for the lump sum fee noted in the following table. Task 1-5
services will be initiated upon the City's approval and will be invoiced on a lump sum. Charges to
the Allowance, which will require the City's prior authorization, will be on a time-and-materials
basis using SCS' current Schedule of Fees.
Task Task Description Fee
1 Prepare 30%Design Engineering Report $4,000
2 Geotechnical Testing of Subsurface for Design of Scale Support Structure $2,500
3 Preparation of Plans, Specs., and Bid Documents for Installation of Scales $15,000
4 Bidding Assistance $4,000
5 Construction Representation $6,500
Subtotal Tasks 1 - 5 $32,000
Allowance $3,000
Total $35,000
M:¢uabw�t,Pon:wsu..aoisir.I6o2SIne.Scold-alar.medocsP111017 Ft So soaia nte.c-vmo..a� SCS ENGINEERS
City of Port Arthur Landfill Engineering Services for Prep of Bid Documents for New Scales
This fee and proposed scope of services are based on information available to SCS at this time. If
conditions change, unforeseen circumstances are encountered, or work efforts are redirected, the fee
estimate may require modification. Any costs in excess of the amount authorized by the City would
require City's prior approval.
CLOSING
SCS appreciates this opportunity to continue providing these services at the City of Port Arthur
Landfill. If you have any questions related to this proposal, please feel free to contact Kevin at
(817) 358-6105 or Jeff at (817) 358-6111.
N'BDRopoulYart,4Th 2OI64T16028B1G,$cpla c-plans-bidd& Fl 1017Pt ti 5mlo bid.0 Phm.dam SCS ENGINEERS
SCS Project No.:
AGREEMENT BETWEEN SCS AND CLIENT
FOR PROFESSIONAL SERVICES
This Agreement is made by and between the City of Port Arthur(hereafter"Client"),and Stearns,
Conrad and Schmidt Consulting Engineers, Inc. dba SCS Engineers(hereafter"SCS").
WITNESSETH
That for the considerations set forth below, the parties agree as follows:
1. Scope of Services: SCS shall provide professional services(hereafter"Services")for the
project entitled, "Providing Plans, Specifications and Bid Documents for the Installation of Scales and
Related Services at the City of Port Arthur Landfill",(hereafter"Project")as set forth in the attached 11/10/17
letter in accordance with the terms and conditions of this Agreement.
2. Basis of Compensation: as defined in SCS' 11/10/17 letter
3. Method of Invoicing: monthly as defined in SCS' 11/10/17 letter
4. Professional Retainer: not applicable
5. Other Terms:
6. General Conditions:
a. Payments for invoices prepared by SCS are due and payable within 30 days of receipt.
b. Client agrees to pay all costs and expenses of SCS, including reasonable attorney fees,arising out of or in
connection with collecting amounts for which Client is responsible pursuant to this Agreement
c. This Agreement may be terminated by either party upon 15 days'written notice to the other party. Upon
termination, SCS shall be paid for all Services rendered to the date of termination together with any
termination expenses incurred.
d. Any work in addition to that described in Article 1 above performed at the request of the Client shall be
compensated on a time-and-materials basis at the rates contained in SCS' Standard Fee Schedule in effect at
the time of performance of the Services,said schedule being attached hereto.
e. The parties hereto shall each maintain in full force and effect Commercial General Liability insurance
with coverage limits which are reasonable in light of the Services to be undertaken, and Workers'
Compensation Insurance as required by law. SCS will maintain liability insurance in the minimum amount of
$1,000,000.
f. Any drawings, specifications, reports,, data and notes developed pursuant to this Agreement are
instruments of service, and as such the original documents, tracings, and field notes are and remain the
property of SCS. Copies will be made available to the city upon request.
M:BDNrop1Pt ArlM,r2016-17\..\C-121917 Agrmt,Scale C-plans-Ind does ineamirirrnin
g. Neither party shall delegate its duties under this Agreement without the written consent of the other party.
Each party binds itself to the successors, administrators and assigns of the other party in respect of all
covenants of this Agreement.
h. The parties agree that the following allocation of liability in the projects undertaken hereunder. The
parties agree that SCS' liability under this Agreement and for the Project shall be limited to the amount
covered, if any, by SCS' liability insurance then in effect, or the amount of SCS' total fees hereunder
(whichever is greater). The Client may pay for the assumption of additional liability by SCS as a separate line
item in Article 2 above.
i. Unless otherwise expressly stated in the Scope of Services,SCS shall have no responsibility for site health
and safety, except with respect to the activities of SCS and its subcontractors. In no event shall SCS be
responsible for the means, methods or manner of performance of any persons other than SCS and SCS'
subcontractors.
j. Client agrees that SCS will not be responsible for liability caused by the presence or release of hazardous
substances or contaminants at the site, unless the release results from the sole negligence of SCS or its
subcontractors. The Client will either make others responsible for liabilities due to such conditions, or will
indemnify,defend and save harmless SCS from such liabilities. At no time shall title to hazardous substances,
solid wastes,petroleum contaminated soil or other regulated substances pass to SCS,nor shall any provision of
this Agreement be interpreted to permit or obligate SCS to assume the status of a "generator," "owner,"
"operator,""transporter,""arranger"or"treatment,storage or disposal facility"under state or federal law. The
provisions of this Article 6j shall survive any termination of this Agreement.
k. SCS shall be entitled to rely on information provided by Client. SCS shall be entitled to an equitable
adjustment in the price and schedule,as agreed by the Client,if conditions differ materially from information
provided by Client, or differ from what could reasonably be anticipated given the nature of the Services.
7. For the purposes of this Agreement,the term"SCS Engineers"shall mean Stearns, Conrad
and Schmidt Consulting Engineers, Inc.
8. This contract is subject to the annual budget process of the City and the availability of funds. If
the City is not able to budget funds,then SCS will be notified accordingly.
IN WITNESS WHEREOF,the parties have caused this Agreement to be executed by their duly authorized
representatives as of the last date written below.
SCS ENGINEERS: CITY OF PORT ARTHUR,TEXAS
BY: / BY:
NAME: Kevin D. Yard, P.E., BCEE NAME:
TITLE: Vice President TITLE:
DATE: December 19, 2017 DATE:
2