INTEROFFICE MEMORANDUM
Date: March 19, 2018
To: The Honorable Mayor and City Council
Through: Harvey Robinson, Interim City Manager
From: Armando Gutierrez, Jr., P.E., Director of Public Works
RE: P.R. 20049 —Improvements Along Bluebonnet Avenue, Change Order#1
Introduction:
Acceptance of Change Order No. 1 involving a time extension of 58 days to the contract with
Excavation and Construction, LLC for the Improvements Along Bluebonnet Avenue from
Gulfway Drive (SH 87) to Memorial Blvd. (US 69) Project due to weather.
Background:
On July 27, 2017, City Council approved Resolution No. 17-154 executing a contract with
Excavation and Construction, LLC for the Improvements Along Bluebonnet Avenue in the
amount of $1,314,627.91. This award was for 270 calendar days commencing on July 17,
2017 to April 23, 2018. The request for time extension is for days due to flooding, delays
from existing water leaks, snow and below freezing temperatures and regular working days
between August 2017 and February 2018 due to heavy and/or steady rain that prevented the
Contractor from working at least 7 hours that day. This request is for 58 calendar days
extending the contract term to a total of 328 calendar days and to a new substantial
completion date of from April 23, 2018 to June 20, 2018.
Budget Impact:
N/A
Recommendation:
"Remember,we are here to serve the Citizens of Port Arthur"
444 4`h Street Port Arthur,Texas 77641-1089 s 409.983.8182 x FAX 409.983.8294
Approval of P. R. No. 20049 authorizing the Interim City Manager to execute Change Order
No. 1 to the contract with Excavation and Construction Co., Inc. for the Improvements Along
Bluebonnet Avenue Project.
"Remember,we are here to serve the Citizens of Port Arthur"
P.O.Box 1089 x Port Arthur,Texas 77641-1089 x 409.983.8101 x FAX 409.982.6743
P.R. 20049
02/02/17 rtb
RESOLUTION NO.
A RESOLUTION AUTHORIZING THE CITY MANAGER TO EXECUTE
CHANGE ORDER NO. 01 TO THE CONTRACT BETWEEN THE CITY
OF PORT ARTHUR AND EXCAVATION AND CONSTRUCTION, LLC
OF NEDERLAND, TEXAS FOR THE CITY STREET IMPROVEMENTS
ALONG BLUEBONNET AVENUE FROM GULFWAY DRIVE TO
MEMORIAL BLVD. (US 69), INCREASING THE CONTRACT TERM
BY 58 DAYS TO A NEW TOTAL OF 328 DAYS.
WHEREAS, per Resolution No. 17-154, the City Council awarded a contract for
the City Street Improvements Along Bluebonnet Avenue project from Gulfway Drive (SH
87) to Memorial Blvd. (US 69) to Excavation and Construction, LLC, of Port Arthur,
Texas in the projected budgetary impact amount of $1,314,627.91 and a contract term
of 270 calendar days from July 17, 2017 to April 23, 2018; and,
WHEREAS, the proposed extension consist of 18 days due to flooding, 6 days
due to delays from existing waterline breaks and material delivery delays and 4 days
due to snow or below freezing and 22 regular working days between August 2018 and
February due to heavy and/or steady rain that prevented the Contractor from working
at least 7 hours that day. The time extension formula will be used up to the month of
November; and,
WHEREAS, this agreement will eliminate 13 calendar days following the request
for 58 calendar days increasing the contract time to a new total of 328 calendar days
and to a new substantial completion date of June 20, 2018, attached hereto as Exhibit
"A"; and,
P.R. 20049
Page 2
WHEREAS, approval of Change Order No. 01 will increase the contract term by
58 calendar days to a new contract term of 328 calendar days and to a new completion
date of June 20, 2018 herein deemed an appropriate action; now, therefore,
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PORT
ARTHUR:
THAT, the facts and opinions in the preamble are true and correct; and,
THAT, Change Order No. 01 is herein approved and the Interim City Manager
and is authorized to execute said Change Order No. 01 (attached as Exhibit "A") to the
contract between the City of Port Arthur and Excavation and Construction, LLC, of Port
Arthur, Texas; and,
THAT, Change Order No. 01 increases the contract term by 58 days to a new
total of 328 days and to a new completion date on June 20, 2018; and,
THAT, a copy of the caption of this Resolution No. be spread upon the Minutes
of the City Council.
READ, ADOPTED AND APPROVED this the day of , A.D. 2018
at a meeting of the City of Port Arthur, Texas by the following vote:
Ayes: Mayor:
Councilmembers:
Noes:
P.R. 20049
Page 3
Derrick Ford Freeman
Mayor
Attest:
City Secretary
Sherri Bellard
APPROVED AS TO FORM: APPROVED FOR ADMINISTRATION:
Valecia Tizeno Harvey Robinson
City Attorney Interim City Manager
APPROVED AS FOR AVAILABILITY OF
FUNDS:
Andrew Vasques, CPA
Director of Finance
Armando Gutierrez, Jr., P.E.
Director of Public Works
Clifton Williams, CPPB
Purchasing Manager
V II9IHX3
A.MA
V41 '
VffAr ARCENEAUX WILSON&COLE
engineering I surveying I planning
March 15, 2018
Mr. Armando Gutierrez, PE
Director of Public Works
City of Port Arthur
444 Fourth Street
Port Arthur, Texas 77640
RE: PROPOSAL FOR CHANGE ORDER NO, I
PROPOSED CITY STREET IMPROVEMENTS ALONG BLUEBONNET
AVENUE
Job No, CPA-826
Dear Mr. Gutierrez:
Attached is Change Order No. 1 for the Proposed City Street Improvements along
Bluebonnet Avenue. This change order includes the request for time extension of 58
days from August to the end of February due to weather, hurricane and delays from
existing water leaks on Bluebonnet Avenue requiring repairs. The City of Port Arthur's
Contract Documents lists several factors that are deemed justified for a Contractor to
request a time extension. Unforeseeable causes or hurricanes, rainy weather when sixty
percent of the workforce cannot work for seven hours or more, and inclement weather
resulting in material or any work damages are some examples. Though the days
requested all meet the criteria, the City of Port Arthur's Time Extension formula to award
seven calendar days for every five regular days of work lost added another 21 calendar
days that can be added to the actual 50 regular days that were lost. The Contractor
(Excavation & Construction) have been onsite every regular working day and if weather
permitted has worked each Saturday and some holidays. The Contractor lost 18 regular
days because of flooding, loss of equipment and materials caused by Hurricane Harvey,
6 days caused by a water leak and material delivery delays, and 4 days as a result of
snow or below freezing temperatures. The remaining 22 regular working days the
Contractor lost between the months of August until the end of February resulted from
409.724.7888
2901 Turtle Creek Dr.,Suite 320
Port Arthur,TX 77642 Engineering Surveying
awceng.com F-16194 10194049
A.MAI lk CNC
Vfly
either a heavy rain or a steady rain that prevented the Contractor from working at least 7
hours that day. After a February meeting with the Contractor and City of Port Arthur Public
Works Department we came to an agreement that the Time Extension formula will only
be used up to the month of November. This agreement with Excavation & Construction
will eliminate 13 calendar days and consequently we recommend the City of Port Arthur
authorize the change to the contract by adding 58 calendar days to extend the contract
end date from April 23, 2018 to June 20, 2018. I have attached Change Order No. 1 which
modifies the contract to reflect this revision for your consideration and action. Should you
have any questions or require additional information, please contact our office.
Very truly yours,
Arceneaux Wilson & Cole LLC
TEXAS REGISTERED ENGINEERING FIRM F-16194
eestan Cole, PE
Vice President
1.`
$410.
.. ARCENEAUX WILSON&COLE
engineering!surveying IPlanning
CHANGE ORDER NO. 1
DATE: March 15, 2018 JOB NO. CPA-826
AGREEMENT DATE: June 27, 2017
NAME OF PROJECT: PROPOSED CITY STREET IMPROVEMENTS ALONG
BLUEBONNET AVENUE
OWNER: CITY of PORT ARTHUR
CONTRACTOR: EXCAVATION & CONSTSRUCTION, LLC.
The following changes are hereby made to the CONTRACT DOCUMENTS:
1. Add the following Items to the Contract and Scope of Work:
a. Extend contract time by 58 calendar days
CHANGE ORDER NO. 1
''.` March 15, 2018
1`'. Job No. CPA-826
.. ARCENEAUX WILSON&COLE
engineering I surveying I planning
CHANGE TO CONTRACT PRICE:
ORIGINAL CONTRACT PRICE: $1.314,627.91
CURRENT CONTRACT PRICE adjusted by previous CHANGE ORDER(S): $1,314,627.91
The CONTRACT PRICE due to this CHANGE ORDER will be {increased} [decreased]
by: $0.00 Dollars
The new CONTRACT PRICE, including this CHANGE ORDER, will be $ 1,314,627.91
CHANGE TO CONTRACT TIME:
ORIGINAL CONTRACT TIME: 270 Calendar Days
CURRENT CONTRACT TIME adjusted by previous CHANGE ORDER: 0 Calendar Days
CURRENT DATE OF COMPLETION: April 23, 2018
CONTRACT TIME due to this CHANGE ORDER will be increased by 58 Days
The New DATE OF COMPLETION: June 20. 2018
No other Terms and Conditions of the Contract are changed as a result of this Change Order.
Contractor's acceptance of Change Order relieves OWNER of any liability for additional costs
incurred by Contractor in his performance of the work covered by the Change Order.
RECOMMENDED BY ENGINEER: ACCEPTED BY:
ARCENEAUX WILSON & COLE LLC [CON CTOR,OFFICER OR OWNER]
EXCAVATION & CONSTRUCTION, LLC.
ACCEPTED BY:
CITY of PORT ARTHUR