HomeMy WebLinkAboutPR 20195: STORM SEWER IMPROVEMENTS ALONG WOODWORTH BLVD. FROM THOMAS BLVD. TO 7TH STREET - CHANGE ORDER NO. 1 ( el, 4) ort rtlru — www.PortArthurTx.gov INTEROFFICE MEMORANDUM Date: April 5, 2018 To: The Honorable Mayor and City Council Through: Harvey Robinson, Interim City Manager From: Armando Gutierrez, Jr., P.E., Director of Public Works RE: P.R. 20195 —Storm Sewer Improvements along Woodworth Blvd. from Thomas Blvd. to 7th Street—Change Order No. 1 Introduction: Acceptance of Change Order No. 1 for a 24 day extension in the proposed city street Storm Sewer Improvements along Woodworth Blvd. from Thomas Blvd. to 7th Street. Background: Proposed Change Order No. 1 is for request of additional time during the months from October 2017 to February 2018 including 12 regular working days due to inclement weather and 5 working days due to Mardi Gras activities. The time extension formula stating 7 calendar days for every 5 calendar days lost equals to a total of 24 calendar days. This change order increases the contract term from 270 calendar days to 294 calendar days and a new substantial completion date from June 28, 2018 to July 22, 2018. Budget Impact: Funds are available in the following account: N/A Recommendation: Approval of P.R. No. 20195 authorizing the City Manager to execute Change Order No. 1 to the contract with Norman Highway Constructors for the Storm Sewer Improvements along Woodworth Blvd. "Remember,we are here to serve the Citizens of Port Arthur" P.O. Box 1089 x Port Arthur.Texas 77641-1089 x 409.983.8102 x FAX 409.983.8294 P.R. 20195 04/5/18 rtb RESOLUTION NO. A RESOLUTION AUTHORIZING THE CITY MANAGER TO EXECUTE CHANGE ORDER NO. 1 TO THE CONTRACT BETWEEN THE CITY OF PORT ARTHUR AND NORMAN HIGHWAY CONSTRUCTORS OF ORANGE, TEXAS FOR THE STORM SEWER IMPROVEMENTS ALONG WOODWORTH BLVD. FROM 7TH STREET TO THOMAS BLVD. INCREASING THE CONTRACT TERM BY 24 DAYS TO A NEW TOTAL OF 294 DAYS. WHEREAS, per Resolution No. 17-188, the City Council awarded a contract for the Storm Sewer Improvements along Woodworth Blvd. from Thomas Blvd. to 7th Street to Norman Highway Constructors of Orange, Texas in the projected budgetary impact amount of $1,186,728.00 and a term of 270 calendar days; and, WHEREAS, proposed Change Order No. 1 is for the request for time extension due to inclement weather and Mardi Gras activities from October 2017 to February 2018 including 12 regular working days for inclement weather and 5 regular working days for Mardi Gras activities; and, WHEREAS, the City of Port Arthur's Time Extension Formula states to award seven calendar days for every five regular days of work lost added another 7 calendar days that can be added to the actual 17 regular days that were lost bringing the total amount requested to 24 calendar days (attached as Exhibit "A"); and, WHEREAS, Change Order No. 1 will increase the total term of the contract from 270 calendar days to 294 calendar days and extending the substantial completion date from June 28, 2018 to July 22, 2018 herein deemed an appropriate action; now, therefore, P.R. 20195 Page 2 BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PORT ARTHUR: THAT, the facts and opinions in the preamble are true and correct; and, THAT, the City Manager of the City of Port Arthur is hereby authorized and directed to execute said Change Order No. 1 to the contract between the City of Port Arthur and Norman Highway Constructors of Orange, Texas; and, THAT, Change Order No. 1 increases the contract term from 270 calendar days to 294 calendar days and extending the substantial completion date from June 28, 2018 to July 22, 2018; and, THAT, a copy of the caption of this Resolution be spread upon the Minutes of the City Council. READ, ADOPTED AND APPROVED this the day of A.D. 2018 at a meeting of the City of Port Arthur, Texas by the following vote: Ayes: Mayor: Councilmembers: Noes: Derrick Freeman Mayor Attest: Sherri Bellard City Secretary P.R. 20195 Page 3 APPROVED AS TO FORM: APPROVED FOR ADMINISTRATION: )///l tt() Valecia zen Harvey Robinson City Attorney Interim City Manager APPROVED AS FOR AVAILABILITY OF FUND j.77 / Andrew Vasquez, CPA Director of Finance Armando Gutierrez, Jr., P.E. Director of Public Works Cli on Williams, CPPB Purchasing Manager EXHIBIT A CRAW ARCENEAUX WILSON&COLE engineering!surveying plannmg April 2, 2018 Mr. Armando Gutierrez, PE Director of Public Works City of Port Arthur 444 Fourth Street Port Arthur, Texas 77640 RE: PROPOSAL FOR CHANGE ORDER NO. I PROPOSED CITY STORM SEWER IMPROVEMENTS ALONG WOODWORTH BLVD, Job No, CPA-855 Dear Mr. Gutierrez: Attached is Change Order No. 1 for the Proposed City Street Strom Sewer Improvements along Woodworth Blvd. This change order includes the request for time extension of 24 days from October to the end of February due to weather and Mardi Gras. The City of Port Arthur's Contract Documents lists several factors that are deemed justified for a Contractor to request a time extension. Unforeseeable causes hurricanes, rainy weather when sixty percent of the workforce cannot work for seven hours or more, and inclement weather resulting in material or any work damages are some examples. Though the days requested all meet the criteria, the City of Port Arthur's Time Extension formula to award seven calendar days for every five regular days of work lost added another 7 calendar days that can be added to the actual 17 regular days that were lost. The Contractor lost 12 regular working days between the months of October until the end of February resulted from either a heavy rain or a steady rain that prevented the Contractor from working and lost 5 days due to the request of the City to be closed during Mardi Gras. We recommend the City of Port Arthur authorize the change to the contract by adding 24 calendar days to extend the contract end date from June 28, 2018 to July 22, 2018. I have attached Change Order No. 1 which modifies the contract to reflect this revision for your consideration and 409.724.7888 2901 Turtle Creek Dr,Suite 320 Port Arthur,TX 77642 Engineering Surveying awceng.com 7 1 101,4049 AK& CRAM vsly action. Should you have any questions or require additional information, please contact our office. Very truly yours, Arceneaux Wilson & Cole LLC TEXAS REGISTERED ENGINEERING FIRM F-16194 estan Co -, °E Vice President ARCENEAUX WILSON&COLE engineering I surveying I planning CHANGE ORDER No.1 DATE: March 14, 2018 JOB NO. CPA-855 AGREEMENT DATE: July 25,2017 NAME OF PROJECT: Storm Sewer Improvements along Woodworth Blvd. OWNER: City of Port Arthur CONTRACTOR: Norman Highway Construction Inc. The following changes are hereby made to the CONTRACT DOCUMENTS: 1. Add/Delete to Adjust the following Bid Items to actual quantities used: a. Extend contract time by 24 days 409.724.7888 2901 Turtle Creek Dr.,Suite 320 Port Arthur,TX 77642 Engineering Surveying awceng.com F-16194 10194049 RECEIVED crouc APR 3 2018 fc.) Public Works .. Engineering-City Hall CHANGE TO CONTRACT PRICE: ORIGINAL CONTRACT PRICE: $ 1,186,728.00 CURRENT CONTRACT PRICE adjusted by previous CHANGE ORDER(S): $ 1,186,728.00 The CONTRACT PRICE due to this CHANGE ORDER will be [incrcoscd] [dccrcascd] by: $ 0.00 Dollars The new CONTRACT PRICE, including this CHANGE ORDER, will be $ 1,186,728.00 CHANGE TO CONTRACT TIME: ORIGINAL CONTRACT TIME: 270 Calendar Days CURRENT CONTRACT TIME adjusted by previous CHANGE ORDERS: 0 Calendar Days CURRENT DATE OF COMPLETION: June 28, 2018 CONTRACT TIME due to this CHANGE ORDER will be increased by 24 Days CURRENT CONTRACT TIME adjusted by CHANGE ORDERS (1): 294 Calendar Days The New DATE OF COMPLETION: July 22, 2018 No other Terms and Conditions of the Contract are changed as a result of this Change Order. Contractor's acceptance of Change Order relieves OWNER of any liability for additional costs incurred by Contractor in his performance of the work covered by the Change Order. RECOMMENDED BY ENGINEER. ACCEPTED : -: — //fill ARCENEAUX WILSON &COLE LLC [CONTRACT*.• OFFICER OR OWNER] Norm.• ighway Construction, Inc. ACCEPTED BY. CITY of PORT ARTHUR REQUEST FOR EXTENSION OF TIME DUE TO WEATHER OR SUPPLIES CITY OF PORT ARTHUR DATE: March 3, 2018 MONTH OF: February, 2018 CITY of PORT ARTHUR, RECEIVED TEXAS PUBLIC WORKS DEPARTMENT APR 3 2018 P.O. BOX 1089 CITY of PORT ARTHUR, TEXAS 77641-1089 Public Works Englnecrfng_City flail ATTENTION: Public Works Department Gentlemen: We request extension of completion time on our Contract due to the days of work lost as specified (list dates actually lost: do not include days not normally worked such as Saturdays, Sundays, or holidays): Dates Lost: (See Attached Sheet) Days Lost (17) / 5 x 7 = 24 Calendar Days Requested Reasons for Request: (See Attached Sheet) Contractor: Norman icihwa Constructors Inc. By: Approved for extension of— calendar days. Disapproved. Date: , 20 CITY OF CITY OF PORT ARTHUR, TEXAS BY: Distribution by City Original: Public Works Department City Manager xc: Engineer Contractor CPA Federally Funded SER A L 4.1 RECEIVED 0400- Texas General Land Office APR 3 2018 '1,(1 l clue Recovery ict Public Works t Engineering-City Hall � T ,/} leCISHEO `3.. e Construction Contract Change Order Request Form Engineer: Owner(Contractor Locality): Contractor: Aceneaux Wilson&Cole LLC City of Port Arthur Norman Highway Construction, 2901 Turtle Creek Dr.,Suite 320 c. 444 4th Street P.O.Box 2440 Port Arthur,TX 77642 Port Arthur,TX 77642 Orange,TX 77631 Phone No.: 409-724-7888 Phone No.:409-983-8100 Phone No.:409-988-0326 Agreement Date: July 25,2017 Date: March 14, 2018 Contract For(Project Description): GLO Contract No.: Project Code No.: P21432C-5 Storm Sewer Improvements 12-403-008-7654 along Woodworth Blvd. Bid Package No.: 11 Change Order No.:1 You are hereby requested to comply with the following changes from the contract plans and specifications: Item Description of Changes: Quantities, Units, Unit Prices, Decrease in Increase in No. Change in Completion Scheduled, Etc. Contract Price Contract Price Change in Contract Price Change in Contract Time (Calendar Days) Original Contract Price: $1,186,728.00 Original Contract Time: 270 days Previous Change Order(s): Net Change From Previous No. 1 to No.1 $0.00 Change Orders: 0 days Contract Price Prior to Contract Time Prior to this Change Order: $1,186,728.00 this Change Order: 0 days Net Incr ose/Decrease of Net Increase/Decrease of this Change Order: $ 0.00 this Change Order: 24 days Contract Price With all Contract Time With all Approved Change Orders: $1,186,728.00 Change Orders: 294 days Cumulative Percent Change in Contract Price Grantee Contract End Date: (+/-): + 0.0 % (mm/dd/yy) 12 /31/2016 Construction Contract Start Date: Construction Contract End Date: (mm/dd/yy) 10/27/14 (mm/dd/yy) 7/22/18 Construction Contract Change Order Request Form Page 1 of 3 CDBG Disaster Recovery Program May 2012 Reimbursements of costs included in this change order are subject to review by the GLO-DR program. * This document may be executed prior to submission for GLO-DR program review, but all parties involved will be held responsible if the change order or the amendment warranted as a result of this change order is not in compliance with CDBG or HUD requirements. RECOMMENDED: APPROVED: ACCEPT A?: By: _ — --J By: BY: _ GINEER OWNER CONTO OR Date: 3 7,20 /8 Date: Date: 12c:eheGq/ 2J/6 JUSTIFICATION FOR CHANGE 1. Will this Change Order increase or decrease the number of beneficiaries? ❑ Increase ❑ Decrease 0 No Change If there is a change, how many beneficiaries will be affected? Total L/M 2. Effect of this change on scope of work: 0 Increase 0 Decrease RI No Change 3. Effect on operation and maintenance costs: 0 Increase 0 Decrease 0 No Change 4. Are all prices in the change order dependent upon unit prices found in the original bid? IBJ Yes 0 No If"No",explain: 5. Has this change created new circumstances or environmental conditions which may affect the project's impact,such as concealed or unexpected conditions discovered during actual construction? 0 Yes 2 No If"Yes", is an Environmental Re-assessment required? Construction Contract Change Order Request Form Page 2 of 3 CDBG Disaster Recovery Program May 2012 6. Is the Texas Commission on Environmental Quality(TCEQ) clearance still valid? (if applicable) El Yes 0 No 7. Is the TCEQ permit approval still valid? (sewer projects only) 0 Yes 0 No 8.Are the handicapped access requirements/approval still valid? (if applicable) 0 Yes ❑ No 9.Are other Disaster Recovery contractual special condition clearance still valid? RI Yes 0 No (If no,specify): NOTE: * Generally, a cumulative change in the contract price in excess of 25% cannot be reviewed (18%decrease for counties). Construction Contract Change Order Request Form Page 2 of 3 CDBG Disaster Recovery Program May 2012