INTEROFFICE MEMORANDUM
Date: June 1, 2018
To: The Honorable Mayor and City Council
Through: Harvey Robinson, Interim City Manager
From: Dr. Hani Tohme, P.E., Director of Utilities
RE: PR 20124—Accepting the Close-Out of Surface Water Treatment Plant
Improvements Project,Phase 1
Introduction:
The intent of this Agenda Item is to seek City Council's approval for close out of the Surface
Water Treatment Plant Improvements Project, Phase 1 and authorize the City Manager to pay
the final retainage invoice of $316,792.47. The final project cost of this phase is
$12,671,698.64.
Background:
In November of 2014, the Council passed Resolution #14-564, awarding the Improvement of
the Port Arthur Water Treatment Plant contract to ALLCO, LLC. The project was managed by
Arceneaux, Wilson, & Cole, LLC. This is the final invoice for the project and includes the
retainage.
Budget Impact:
The original contract amount was $12,373,311.00; the contract amount after Change Order 3
was $12,825,269.64. Change Order 4 includes a deduction of $153,571.00 for deleting the
following items: demo fencing/paving, grade area/swales, 4" casing for F.O., 8" limestone
drive, concrete paving, guard shack, testing, and a 42"temp. plug, resulting in the final project
cost being$12,671,698.64.
Recommendation:
It is recommended that City Council adopt Proposed Resolution No. 20124, which closes out
the project, authorizing the City Manager to accept the project pay the final retainage of
$316,792.47.
"Remember,we are here to serve the Citizens of Port Arthur"
P.R. No. 20124
6/1/18 ds/ht
RESOLUTION NO.
A RESOLUTION AUTHORIZING ACCEPTANCE OF THE
ENGINEER'S CERTIFICATE OF COMPLETION,
CONTRACTOR'S CERTIFICATE AND RELEASE,
CONTRACTOR'S CERTIFICATE OF GUARANTEE, FOR
IMPROVEMENTS OF THE PHASE I SURFACE WATER
TREATMENT PLANT AND AUTHORIZING THE CITY
MANAGER TO EXECUTE THE CERTIFICATE OF
ACCEPTANCE AND APPROVAL OF FINAL PAYMENT
IN THE AMOUNT OF $316,792.47 FROM ACCOUNT NO.
429-1258-532.59-00, PROJECT WSI-008.
WHEREAS,pursuant to Resolution No. 14-564 dated November 4,2014,the City Council
awarded a contract for the construction of the Surface Water Treatment Plant Project, Phase 1 to
ALLCO, LLC of Beaumont, Texas, in the amount of$12,373,311.00; and,
WHEREAS, Change Orders No. 1 thru 4 of this project has brought the final price of this
project to $12,671,698.64; and,
WHEREAS,ALLCO, LLC has completed the contracted project to the satisfaction of the
project engineer and the City staff; and,
WHEREAS, the City has received Engineer's Certificate of Completion (Exhibit "A");
Contractor's Certificate and Release(Exhibit"B"); Contractor's Certificate of Guarantee(Exhibit
"C"), Certificate of Acceptance (Exhibit "D") and Final Pay Invoice (Exhibit "E") for the
completion of the Phase I Surface Water Treatment Plant Project, executed by ALLCO, LLC;
and,
WHEREAS, the retainage for this project is two and a half percent (2.5%) of the work
completed and billed, and the project engineer, Arceneaux, Wilson, & Cole, LLC approves final
payment to ALLCO, LLC, in the amount of$316,792.47.
NOW THEREFORE,BE IT RESOLVED BY THE CITY COUNCIL OF THE
CITY OF PORT ARTHUR:
P.R. No. 20124
6/1/18 ds/ht
THAT,the facts and opinions in the preamble are true and correct.
THAT, the City Manager of the City of Port Arthur is hereby authorized to execute on
behalf of the City of Port Arthur, subject to review and approval by the City Attorney, an
Engineer's Certificate of Completion; Contractor's Certificate and Release; Contractor's
Certificate of Guarantee, Certificate of Acceptance and Final Pay Invoice for the completion of
the Surface Water Treatment Plant Project, Phase 1; and,
THAT, final payment be made to ALLCO, LLC in the amount of$316,792.47; and,
THAT, a copy of the caption of this Resolution be spread upon the minutes of the City
Council.
READ, ADOPTED,AND APPROVED THIS day of , 2018 at
a Regular Meeting of the City Council of the City of Port Arthur, Texas,by the following vote:
AYES: Mayor:
Councilmembers:
NOES:
Derrick Freeman
Mayor
ATTEST:
Sherri Bellard
City Secretary
P.R. No. 20124
6/1/18 ds/ht
APPROVED AS TO FORM:
Valecia Tizeno
City Attorney
APPROVED FOR ADMINISTRATION:
Harvey Robinson Clifton Williams, CPPB
Interim City Manager Purchasing Manager
Dr. Hani Tohme, P.E.
Interim Director of Utilities Operations
APPROVED AS TO AVAILABILITY OF FUNDS:
Andrew Vasquez, CPA
Director of Finance
ENGINEER'S CERTIFICATE OF COMPLETION
Project: PHASE I SURFACE WATER TREATMENT PLANT UPGRADES
Date Of Issuance: 4/3/2018
Owner(s): CITY OF PORT ARTHUR
Owner's Project No.: CPA-681
Engineer: ARCENEAUX WILSON & COLE LLC
Contractor: ALLCO, LTD
This Engineer's Certificate of Completion applies to all Work under the Contract Documents or to
the following specified parts thereof:
TO CITY OF PORT ARTHUR
[OWNER]
AND TO ALLCO, LTD
[CONTRACTOR]
The Work to which this Certificate applies has been inspected by authorized representatives of
Owner, Contractor and Engineer, and that Work is hereby declared to be complete in accordance
with the Contract Documents on
11/30/2017
DATE OF COMPLETION
e�
ZEOFr1
Executed by Engineer on 04/03/2018
ig�Q• •.1.11'1
e*. .*/
CALVIN D. PROSEN
Il11+0,, 70405 •40,1
II;Fs F?rSTEILI'c"'
BY: e4,1,,L, g44-4.-- ,‘si0 �1
ARCENEAUX WILSON & COLE CONSULTING ENGINEERS, INC. [SEAL]
1I1
EXHIBIT B
(AW&C Contractor's Certificate and Release)
CONTRACTOR'S CERTIFICATE AND RELEASE
FROM: ALLCO, LTD
TO: CITY OF PORT ARTHUR
REFERENCE CONTRACT NO. CPA-681
ENTERED INTO THE 18TH DAY OF NOVEMBER, 2014 BETWEEN THE
CITY OF PORT ARTHUR AND
ALLCO, LTD O BEAUMONT, TEXAS
FOR THE PHASE I SURFACE WATER TREATMENT PLANT UPGRADES
LOCATED IN THE CITY OF PORT ARTHUR,TEXAS
KNOW ALL MEN BY THESE PRESENTS:
1. The undersigned hereby certifies that there is due from, and payable by, the Owner to the
Contractor under the contract and duly approved Change Orders and modifications the balance of
THREE HUNDRED SIXTEEN THOUSAND SEVEN HUNDRED NINETY-TWO AND 47/100 DOLLARS($316,792.47).
2. The undersigned further certifies that in addition to the amount set forth in Paragraph 1, there are
outstanding and unsettled the following items which he claims are just and due and owing by the
Owner to the Contractor:
(a) NONE
(b)
(c)
(d)
3. The undersigned further certifies that all work required under this contract,including work required
under Change Order(s)numbered *1 w"'"FINAL has been performed in
accordance with the terms thereof, and that there are no unpaid claims for materials, supplies, or
equipment and no claims of laborers or mechanics for unpaid wages arising out of the performance
of this contract, and that the wage rates paid by the Contractor were in conformity with the contract
provisions relating to said wage rates.
4. Except for the amounts stated under Paragraphs 1 and 2 hereof, the undersigned has received from
the Owner all sums of money payable to the undersigned under, or pursuant to, the above
mentioned contract or any modifications or change thereof.
1/2
5. That in consideration of the payment of the amount stated in Paragraph 1 hereof, the undersigned
does hereby release the Owner and Operator from any and all claims arising under or by virtue of
this contract, except the amount listed in Paragraph 2 hereof due from the Owner; provided,
however, that if for any reason the Owner does not pay in full the amount stated in Paragraph 1
hereof, said deduction shall not affect the validity of this release, but the amount so deducted shall
be automatically included under Paragraph 2 as an amount which the Contractor has not released
but will release upon payment thereof The Contractor further certifies that upon the payment of the
amount listed in Paragraph 2 hereof, and of any amount which may be deducted from Paragraph 1
hereof, he will release the Owner and Operator from any and all claims of any nature whatsoever
arising out of said contract or modification thereof, and will execute such further releases or
assurances as the Owner and Operator may request.
IN WITNESS WHEREOF, the undersigned has signed and sealed this instrument this 36 44`-day
of A�IAM,+� , 2018 •
` ,
\,--..- 4"
••: � ALLCO, LTD
<.
/S
'. ' BY: , President
T.W. Harrison , being first duly sworn on oath, deposes and says, first, that
he is the President of ALLCO, LTD
second, that he has read the foregoing certificate by him subscribed as President
of ALLCO, LTD
Affiant further states that the matterp,otiditltiyigs stated herein are true.
.,.\—,
>`AGO, t'i ,,
--"k•F.09" 1 _ w,
r/ a i..
S
Subscribed and sworn to before me this O)�'1 day of MAY ,2018,
1 ,‘,9-75 .;\~ . Y BETH DELORD i
My commission expires 1 ?firk. Notaiy Public,State OfTexast
t q foft��o
My Commission t
t
LINAOCt-k) Le diefiot
2/2
EXHIBIT C
(AW&C Contractor's Certificate of Guarantee)
CONTRACTOR'S CERTIFICATE OF GUARANTEE
FROM: ALLCO, LTD
(Name of Contractor)
TO: CITY OF PORT ARTHUR
REFERENCE CONTRACT NO. CPA-681
ENTERED INTO THE 18TH DAY OF NOVEMBER, 2014 BETWEEN THE
CITY OF PORT ARTHUR AND
- --(owner) ---
ALLCO, LTD OF BEAUMONT, TEXAS
(Name of Contractor) (City,Texas)
FOR THE PHASE I SURFACE WATER TREATMENT PLANT UPGRADES •
(Name of Project)
LOCATED IN THE CITY OF PORT ARTHUR, TEXAS
KNOW ALL MEN BY THESE PRESENTS:
1. ALLCO, LTD does hereby guarantee all of the work done under
the above referenced contract to be free from faulty materials in every particular, and free from improper
workmanship,and against injury from proper and usual wear;and agrees to replace or re-execute without cost
to the Owner and Operator such work as may be found to be improper or imperfect, and to make good all
damage caused to other work or materials,due to such required replacement or re-execution.
2. This guarantee shall cover a period of one (1) year from the date of acceptance of all work under this
Contract,as evidenced by the Engineer's Certificate of Completion.
3. This Certificate is given in connection of the final payment under the contract between the Owner and
ALLCO, LTD and with the knowledge that it will be relied upon in
making such payment and that such payment would not be made except upon the truth of the matter
contained in this affidavit.
IN WITNESS WHEREOF,the undersigned has signed and sealed this instrument this 3" I day
of ,
MA� 2018.
ALLCO, LTD
`� ' t.•• � � (Name of Contractor)
s • f
•
�—/` , BY: , President
\ (AZPLA)
/// *
/'11j0‘♦
1/2
T.W. Harrison , being first duly sworn on oath, deposes and says, first that he is the President
(Affiant) (Title)
of ALLCO, LTD
(Name of Contractor)
second,that he has read the foregoing certificate by him subscribed as President
(Title)
of ALLCO, LTD
(Name of Contractor)
Affiant further states that the mattSro etkd thiiigs stated herein are true.
\\‘ �LC0:
(Affiants Signature)
' •
''1lt,l1t'``-�
Subscribed and sworn to before me this day of MAY , 2018.
V•
. pb YMARY BETH DELORD
Notary public,State Of Texas/
My commission expires: My N�fnF`�FQ Commission r Expires
1212019
(Notary Publi
2/2
EXHIBIT D
(Certificate of Acceptance)
City of Port Arthur, Texas
Department of Utility Operations
CERTIFICATE OF ACCEPTANCE FOR
SURFACE WATER TREATMENT PLANT
PROJECT FOR THE CITY OF PORT ARTHUR
To: ALLCO, LLC of Beaumont, Texas
This document is to certify that the City of Port Arthur, Texas accepts the completion of
the Surface Water Treatment Plant Project, Phase 1, on the basis of the City of Port
Arthur, Texas Utility Operations Department, the Engineer's Certificate of Completion,
the Contractor's Certificate and Release, and Contractor's Certificate of Guarantee from
ALLCO, LLC of Beaumont, Texas.
Harvey Robinson
Interim City Manager
ATTEST:
Sherri Bellard
City Secretary
EXHIBIT E
(Final Invoice)
Oa=
CONTRACT FOR CONSTRUCTION
OF
PROJECT 4, PHASE I SURFACE WATER TREATMENT PLANT UPGRADE
TO SERVE
CPA-681
OWNER: City of Port Arthur CONTRACTOR: ALLCO
444 4th Street P.O. Box 3684
Port Arthur, TX 77642 Beaumont,TX 77704
AWC Job No. CPA-680 Date: May 22, 2018
AWC Construction Phase No. CPA-681 Invoice Period: 11/30/2017 - 11/30/2017
Monthly Invoice No. 31 & Final Contract Date: November 18, 2014
Contract Amount $ 12,373,311.00 Notice to Proceed: December 29, 2014
Change Orders: Contract Time: 400 Calendar Days
1 Change Order No. 1 $ 44,575.00
2 Change Order No. 2 $ 186,301.64
3 Change Order No. 3 $ 221,082.00
4 Change Order No. 4 $ (153,571.00)
$
Total Contract Amount
to Date: $ 12,671,698.64 Approved Time Extensions: 668 Days
Amount Placed to Date: $ 12,671,698.64 Revised Contract Time: 1068 Calendar Days
Material on Hand Not $ - Days to Date: 1070 Days
Subtotal: $ 12,671,698.64 Original Completion Date: February 1, 2016
Less 0.00% Retainage $ - Revised Completion Date: November 30, 2017
Balance: $ 12,671,698.64 Percent Time Used: 100%
Less Amounts on $ 12,354,906.17 Percent Complete: 100%
TOTAL AMOUNT DUE $ 316,792.47
TEXAS REGISTERED EDD EN INEERINC FIRM
16i.94 * 0.F \
rd;•
*• • *'#
Recommended for Approval: %*. �\ •*,
CALVIN D. PROSEN
/`IP,,,G10
405
f�OSTE�ff'o *40
CAL: 06/Oinoiss q2;;;:L�t
Calvin D. Prosen, PE [SEAL]
0 COW
Monthly Invoice No. 31 & Final
PROJECT 4, PHASE I SURFACE WATER TREATMENT PLANT UPGRADE
CITY OF PORT ARTHUR
CPA-681
May 22, 2018
Approx. Quantity Total Amount This
Item Description of Bid Item QTY Unit This Quantity To Unit Price INVOICE Total Amount To Date
INVOICE Date
Base Bid Items
1. 1 MOBILIZATION 1 LS 1 $ 893,000.00 $ - $ 893,000.00
2. 2 FURNISH/INSTALL SI/VIP IMPROVEMENTS $ - S - $ -
3. A MISC SITE WORK/PAVING/FENCING $ - $ - S -
4. Al Set Up Laydown Area @ Office Trailers 1 LS 1 S 75.000.00 S - S 75.000.00
5. A2 Set Up Grinder Pump System/Force Main S - 5 - S -
6. Grinder Pump System 1 LS 1 S 12.200.00 $ - S 12.200.00
7. 1-1/2"&4"Force Main 1 LS 1 $ 10,500.00 $ - S 10,500.00
8. A3 New Service Entrance $ - $ - S -
9. Demo Fencing/Paving 1 LS 1 $ 4,011.00 5 - $ 4,011.00
10. Grade Area/Swales 1 L5 1 $ 2,500.00 5 - $ 2.500.00
11. 4"HDPE Casing for Future Fiber Optic 1 LS 1 $ 10,000.00 $ - 5 10.000.00
12. 8"Limestone Driveway 1 LS 1 $ 30,000.00 S - S 30.000.00
13. Replace Concrete Paving @ Entrance 1 LS 1 5 12,000.00 $ - 5 12.000.00
14. Guard Shack-Install 1 LS 1 5 10,000.00 $ - 5 10,000.00
15. A4 Limestone Access Road Around Site 1 LS 1 $ 85.000.00 $ - 5 85,000.00
16. A5 Misc Paving/Sitework $ - $ - S -
17. Remove/Replace Paving @ Ductbanks 1 LS 1 $ 5.000.00 $ - $ 5,000.00
18. Place Lightpole Bases 1 LS 1 $ 2.500.00 S - $ 2,500.00
19. Relocate Fuel Tank 1 LS 1 $ 6.000.00 $ - $ 6,000.00
20. Final Grading/Seeding 1 LS 1 S 5.000.00 5 - $ 5.000.00
21. A6 Fencing 1 LS 1 5 15.000.00 $ - 5 15.000.00
22. A7 Final Grading/Seeding1 LS 1 S 5,000.00 $ S 5.000.00
23. B CONSTRUCT PRE-STRESSED GST S - $ - $ -
24. B1 Tank Excavation/Foundation Prep/Backfill 5 - $ - $ -
25. Tank Subgrade Excavation 1 LS 1 S 600,000.00 S - $ 600,000.00
26. Re-Grade Bottom of Tank After Piling is Completed 1 LS 1 S 75,000.00 5 - $ 75,000.00
27. Place 2"Sealcoat @ Bottom 1 LS 1 S 160,000.00 S - $ 160.000.00
28. Place Leveling Base @ Tank Bottom 1 LS 1 S 150,000.00 S - $ 150.000.00
29. Track @ Tank Bottom 1 LS 1 S 95,000.00 S - S 95.000.00
30. Backfill 1 LS 1 5 200,000.00 5 - S 200,000.00
31. B2 Track/Crane Pads/Casting Beds S - S - S -
32. Track @ Top of Tank Excavation 1 LS 1 S 95,000.00 $ - $ 95,000.00
33. Crane Pads/Casting Bed Areas 1 LS 1 $ 95.000.00 $ - $ 95,000.00
34. B3 Tank Piping-Underslab $ S - S -
35. 42"Fill Line 1 LS 1 $ 45,000.00 S - 5 45,000.00
36. 42"HSP Line 1 LS 1 $ 45,000.00 S - $ 45,000.00
37. 6"Drain Line 1 LS 1 $ 15,000.00 S - 5 15.000.00
38. 54 Overflow Tank Slab/Structure 1 LS 1 5 10,000.00 .$ - $ 10,000.00
39. B5 Overflow Piping 1 LS 1 $ 5,000.00 $ - 5 5,000.00
40. 66 Mowstrip Around Tank 1 LS 1 S 20.000.00 $ - $ 20,000.00
41. B7 Tank Construction-DN Tanks 5 - $ - $ -
•UVIE
Monthly Invoice No. 31 & Final
PROJECT 4, PHASE I SURFACE WATER TREATMENT PLANT UPGRADE
CITY OF PORT ARTHUR
CPA-681
May 22, 2018
Approx. Quantity Total Amount This
Item Description of Bid Item QTY Unit This Quantity To Unit Price INVOICE Total Amount To Date
INVOICE Date
42. Engineering Design Drawings/Calcs/Insurance 1 LS 1 5 84,000.00 $ - S 84,000.00
43. Deep Foundation System 1 LS 1 S 668,000.00 $ - S 668,000.00
44. Form/Reinf/Pour Floor 1 LS 1 S 737,000.00 S - 5 737,000.00
45. Casting Wall Panels 1 LS 1 $ 405,000.00 $ - $ 405,000.00
46. Erect Wall Panels 1 LS 1 5 250,000.00 S - $ 250,000.00
47. Form/Pour Wall Slots 1 LS 1 $ 210,000.00 S - $ 210,000.00
48. Form/Reinf/Pour Wall Cap 1 LS 1 $ 170.000.00 S - $ 170,000.00
49. Core Wall Shotcrete 1 LS 1 $ 275,000.00 5 - $ 275,000.00
50. Pre-Stressing 1 LS 1 $ 320,000.00 $ - $ 320,000.00
51. Covercoat 1 LS 1 $ 192,000.00 5 - 5 192,000.00
52. Tank Exterior Coating 1 LS 1 $ 25,000.00 $ - $ 25,000.00
53. Tank Appurtenances 1 LS 1 $ 32,000.00 5 - 5 32,000.00
54. 88 Disinfect Tank!Testing 1 LS 1 $ 25,000.00 $ - $ 25.000.00
55. C STRUCTURAL CONCRETE/MISC METALS $ - $ - S -
56. Cl Filter Control Box-Structure $ - S - S -
57. Excavation/Seal Slab 1 LS 1 5 30,000.00 5 - $ 30,000.00
58. Foundation-Form/Reinf/Place 1 LS 1 S 80,000.00 5 - $ 80.000.00
59. Walls/Stairs-Form/Reinf/Place 1 LS 1 5 175,000.00 $ - S 175.000.00
60. Elevated Platform/Slab-Form/Reinf/Place 1 LS 1 S 95,000.00 5 - 5 95,000.00
61. C2 Electrical Equipment Slab S - S - $ -
62. Excavation/Fine Grading 1 LS 1 S 3,000.00 5 - 5 3.000.00
63. Slab-Form/Reinf/Place 1 LS 1 5 15.000.00 $ - 5 15,000.00
64. C3 Miscelleaneous Metals S - S - S -
65. Handrails @ FCB 1 LS 1 S 2,200.00 S - S 2.200.00
66. Stair Nosing @ FCB Stairs 1 LS 1 S 1,500.00 $ - S 1,500.00
67. Hatches @ FCB 1 LS 1 $ 6,500.00 $ - 5 6,500.00
68. Aluminum Stairs/Handrails/Platforms @ New GST 1 LS 1 $ 20,000.00 $ - 5 20.000.00
69. D EQUIPMENT SETTING $ - $ - $ -
70. Chemical Induction System/Davit Cranes 1 LS 1 S 130,000.00 $ - 5 130,000.00
71. Vertical Turbine Pumps 1 LS 1 $ 900,000.00 $ - S 900.000.00
72. Sample Pump @ Tank 1 LS 1 $ 5,000.00 $ - S 5,000.00
73. E YARD/PLANT PIPING S - $ - $ -
74. 54"Fill Line From Filter Box to Tie Ins At 42" 1 LS 1 S 275,000.00 $ - S 275,000.00
75. 54"Wall Spool Pieces @ Filter Box 1 LS 1 $ 36,000.00 $ - $ 36,000.00
76. 42"Fill Line to New GST Tie-In 1 LS 1 $ 75,000.00 $ - $ 75,000.00
77. 42"Fill Line to Existing GST Tie-In 1 LS 1 $ 75,000.00 $ - $ 75,000.00
78. 18"DI Piping from HS Pump to Tie Ins 1 LS 1 $ 75,000.00 $ - $ 75,000.00
79. ARV/Pressure Gauge Piping @ HS Pumps 1 LS 1 $ 6,000.00 $ - 5 6,000.00
80. Perform 18"Tie-ins @ Ex 36"Line 1 LS 1 $ 25.000.00 $ - S 25,000.00
81. 4"High Service Pump PVC Drain Piping 1 LS 1 $ 4,000.00 $ - S 4.000.00
82. 2"Chlorine Gas PVC Piping 1 LS 1 S 3.000.00 $ - $ 3,000.00
83. 1" Amonia PVC Piping 1 LS 1 S 3,000.00 S - $ 3,000.00
VICUNA.WILS9N.1.01,
Monthly Invoice No. 31 & Final
PROJECT 4, PHASE I SURFACE WATER TREATMENT PLANT UPGRADE
CITY OF PORT ARTHUR
CPA-681
May 22, 2018
Quantity Total
Approx. Amount This
Item Description of Bid Item QTY Unit This Quantity To Unit Price INVOICE Total Amount To Date
INVOICE Date
84. 1"Sample Line Piping 1 LS 1 S 1,500.00 $ - $ 1,500.00
85. F ELECTRICAL $ - $ - $ -
86. Mobilization 1 LS 1 S 30,000.00 $ - $ 30,000.00
87. Switchgear 1 LS 1 S 651,000.00 $ - $ 651,000.00
88. Pad Mt Transformers 1 LS 1 S 94,000.00 S - $ 94,000.00
89. T1/T2 Switches 1 LS 1 $ 162,000.00 5 - $ 162,000.00
90. Fixtures 1 LS 1 $ 24,000.00 5 - $ 24,000.00
91. Sand/Concrete/Rebar 1 LS 1 $ 137,000.00 5 - $ 137,000.00
92. Pull Boxes 1 LS 1 $ 99,000.00 $ - $ 99,000.00
93. Conduit&Fittings 1 LS 1 $ 345,000.00 $ - $ 345,000.00
94. Equipment 1 LS 1 5 87,000.00 $ - S 87.000.00
95. Temp Power Locations 1 LS 1 $ 32,000.00 $ - 5 32,000.00
96. Controls 1 LS 1 5 96,000.00 $ - 5 96.000.00
97. Linework 1 LS 1 S 28,000.00 5 - $ 28,000.00
98. Line Poles/Misc Materials 1 LS 1 $ 16,000.00 S - $ 16.000.00
99. Cable&Wire 1 LS 1 $ 345,000.00 S - $ 345,000.00
100. Labor 1 LS 1 $ 615,000.00 S - S 615,000.00
101. 3 DESIGN OF TRENCH SAFETY SYSTEMS 1 LS 1 $ 3.000.00 S - S 3,000.00
102. 4 TRENCH SAFETY SYSTEMS 5000 LF 5000 S 2.00 $ - 5 10,000.00
103. 5 SPECIAL SHORING 14000 SF 14000 5 2.00 $ - S 28.000.00
104. 6 SWPP/NOI IMPLEMENTATION 1 LS 1 S 5,000.00 5 - S 5.000.00
105. 7 INSPECTIONS FOR SWPP 1 LS 1 $ 4,900.00 S - S 4.900.00
Supplemental Items $ - $ - $ -
106. 8 ALLOWANCE-TESTING 1 LS 1 $ 100,000.00 S - $ 100,000.00
107. 9 ALLOWANCE-ELECTRIAL GEAR/ENTERGY 1 LS 1 S 150,000.00 $ - $ 150,000.00
108. 10 ALLOWANCE-CONTROL SYSTM SPLY/INSTL 1 LS 1 S 155,000.00 $ - $ 155,000.00
Alternate Bid Item S - $ - $ -
109. AB1 ALUM GEODESIC DOME @ GST S - $ - S -
110. Engineering/Calcs/Submittal Package 1 LS 1 S 87.000.00 S - 5 87,000.00
111. Shipment of Materials/Mobilization 1 LS 1 S 750,000.00 5 - S 750.000.00
112. Installation 1 LS 1 S 92,000.00 S - $ 92.000.00
Change Orders
Change Order No.1
113. New Access Road/Entrance 1 LS 1 $ 36,700.00 $ - $ 36,700.00
114. Bore(4)Electrical Conduit Underground 1 LS 1 S 11,275.00 $ - $ 11,275.00
115. F&I Alum.Winding Transformer in Lieu of Copper 1 LS 1 S (3,400.00) $ - 5 (3,400.00)
Change Order No.2 S - S - S -
116. 18"Tie-on @ HSP 1 LS 1 5 6,160.64 5 - $ 6.160.64
117. Furnish Speed Limit Signs 1 LS 1 $ 835.00 S - S 835.00
118. Testing of all 15kV Cables 1 LS 1 $ 10,017.00 $ - $ 10,017.00
119. H-Frame Bracing 1 LS 1 $ 8,125.00 S - $ 8,125.00
120. Type B Fixture @ Sample Pump 1 LS 1 $ 2,884.00 S - $ 2,884.00
CIIAIC
Monthly Invoice No. 31 & Final
PROJECT 4, PHASE I SURFACE WATER TREATMENT PLANT UPGRADE
CITY OF PORT ARTHUR
CPA-681
May 22, 2018
Approx. Quantity Total Amount This
Item Description of Bid Item Unit This Quantity To Unit Price Total Amount To Date
QTY INVOICE
INVOICE Date
121. 42"Temp Plug At Effluent Line 1 LS 1 $ 6,380.00 S - $ 6,380.00
122. Furnish Evoqua Water Champ 1 LS 1 $ 20,930.00 S - 5 20,930.00
123. Fumish/Install Pre-lubrication System @ HSP 1 LS 1 S 130,970.00 $ - $ 130,970.00
124. Weather days-56 Calendar Days S - $ - S -
Change Order No.3 $ - S - S -
125. Electrical Relocate @ HSP Tie-In 1 LS 1 5 65,863.00 $ - $ 65,863.00
126. Tie-In Modification @ HSP 1 LS 1 5 58,927.00 $ - S 58,927.00
127. Clearwell Tie-in Modifications 1 LS 1 S 40,954.00 $ - $ 40,954.00
128. Clearwell Safety Walkway 1 LS 1 5 55,338.00 S - S 55.338.00
129. Time Extension-75 Days $ - $ - $ -
Change Order#4 $ - $ - $ -
130. Delete Item 9,Demo Fencing/Paving 1 LS 1 5 (4.011.00) S - S (4,011.00)
131. Delete Item 10,Grade Area/Swales 1 LS 1 S (2,500.00) S - $ (2,500.00)
132. Delete Item 11,4"Casing for F.O. 1 LS 1 $ (10,000.00) $ - S (10,000.00)
133. Delete Item 12,8"Limestone Drive 1 LS 1 $ (30,000.00) $ - $ (30,000.00)
134. Delete Item 12,Concrete Paving 1 LS 1 $ (12.000.00) $ - $ (12,000.00)
135. Delete Item 14,Guard Shack 1 LS 1 $ (10,000.00) $ - 5 (10,000.00)
136. Delete Supplemental Item-Testing 0.7868 LS 0.7868 $ (100,000.00) 5 - $ (78,680.00)
137. Delete Item 121,42"Temp.Plug 1 LS 1 $ (6,380.00) $ - $ (6,380.00)
138. Time Extension for Weather Days-73 Days 1 LS S - $ - S -
139. Time Extension for Time Suspension-446 Days 1 LS S - $ - S -
S - $ - S -
TOTAL $ - $12,671,698.64