INTEROFFICE MEMORANDUM
Date: July 11, 2018
To: The Honorable Mayor and City Council
Through: Harvey Robinson, Interim City Manager
From: Armando Gutierrez,Jr., P.E., Director of Public Works
RE: P.R. 20328—Storm Sewer Improvements along Woodworth Blvd. from
Thomas Blvd.to 7th Street—Change Order No. 2
Introduction:
Acceptance of Change Order No. 2 for a 10 day extension in the proposed city street Storm
Sewer Improvements along Woodworth Blvd. from Thomas Blvd. to 7th Street.
Background:
Proposed Change Order No. 2 is a request of additional time due to delays occurring on May
2, 3, & 18 of 2018 due to AT&T utility installations and on June 6, 7, 8, 12, 13, 14, 15 of 2018
extra work was performed outside of the scope of the original contract; concrete repairs,
removal and replacement of sidewalks, installation of handicap ramps and replaced storm
sewer pipes and tie-ins.This work will not increase the total contract price.
Change order No. 1 increased the contract term from 270 calendar days to 294 calendar days.
This change order would increase the revised term of 294 calendar days to 304 calendar days
and a new substantial completion date from June 28, 2018 to August 1, 2018.
Budget Impact:
There is no budget impact.
"Remember,we are here to serve the Citizens of Port Arthur"
P.O.Box 1089 x Port Arthur,Texas 77641-1089 x 409.983.8102 x FAX 409.983.8294
Recommendation:
Approval of P.R. No. 20328 authorizing the City Manager to execute Change Order No. 2 to
the contract with Norman Highway Constructors for the Storm Sewer Improvements along
Woodworth Blvd.
"Remember,we are here to serve the Citizens of Port Arthur"
P.O.Box 1089 x Port Arthur.Texas 77641-1089 x 409.983.8101 x FAX 409.982.6743
P.R. 20328
07/11/18 anw
RESOLUTION NO.
A RESOLUTION AUTHORIZING THE CITY MANAGER TO EXECUTE
CHANGE ORDER NO. 2 TO THE CONTRACT BETWEEN THE CITY OF PORT
ARTHUR AND NORMAN HIGHWAY CONSTRUCTORS OF ORANGE, TEXAS
FOR THE STORM SEWER IMPROVEMENTS ALONG WOODWORTH BLVD.
FROM 7TH STREET TO THOMAS BLVD. INCREASING THE CONTRACT
TERM BY 10 DAYS TO A NEW TOTAL OF 304 DAYS.
WHEREAS, per Resolution No. 17-188, the City Council awarded a contract for
the Storm Sewer Improvements along Woodworth Blvd. from Thomas Blvd. to 7th Street
to Norman Highway Constructors of Orange, Texas in the projected budgetary impact
amount of $1,186,728.00 and a term of 270 calendar days; and,
WHEREAS, per Resolution No. 18-147, the City Council authorized Change Order
No. 1, increasing the initial term of the contract from 270 to 294 calendar days; and,
WHEREAS, proposed Change Order No. 2 is a request for a time extension of 10
days due to delays by a local utility contractor and extra work performed outside of the
scope of the original contract; concrete repairs, removal and replacement of sidewalks,
installation of handicap ramps and replaced storm sewer pipes and tie-ins. This work
will not increase the total contract price; and,
WHEREAS, Change Order No. 2 will increase the revised contract term from 294
to 304 calendar days, extending the substantial completion date from July 22, 2018 to
August 1, 2018 herein deemed an appropriate action; now, therefore,
P.R. 20328
Page 2
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PORT ARTHUR:
THAT, the facts and opinions in the preamble are true and correct; and,
THAT, the City Manager of the City of Port Arthur is hereby authorized and
directed to execute said Change Order No. 2 to the contract between the City of Port
Arthur and Norman Highway Constructors of Orange, Texas; and,
THAT, Change Order No. 2 increases the contract term from 294 calendar days
to 304 calendar days and extends the substantial completion date from July 22, 2018 to
August 1, 2018; and,
THAT, a copy of the caption of this Resolution be spread upon the Minutes of the
City Council.
READ, ADOPTED AND APPROVED this the day of , A.D. 2018
at a meeting of the City of Port Arthur, Texas by the following vote:
Ayes: Mayor:
Councilmembers:
Noes:
Derrick Freeman
Mayor
Attest:
Sherri Bellard
City Secretary
P.R. 20328
Page 3
APPROVED AS TO FORM: APPROVED FOR ADMINISTRATION:
\l Z
Valecia Tizeno Harvey Robinson
City Attorney Interim City Manager
APPROVED AS FOR AVAILABILITY OF
FUNDS:
Andrew Vasquez, CPA
Director of Finance
Armando Gutierrez, Jr., P.E.
Dire or of Public Works
stir,/ (f4A.4.3
Clifton Williams, CPPB
Purchasing Manager
Alm.
•
.vi roll Hiouc
A/ ARCENEAUX WILSON&COLE
enyu 1eern+y I,UI veying I plunnil y
June 22, 2018
Mr. Armando Gutierrez, PE
Director of Public Works
City of Port Arthur
444 Fourth Street
Port Arthur. Texas 77640
RE; PROPOSAL FOR CHANGE ORDER NO. 2
PROPOSED CITY STORM SEWER IMPROVEMENTS ALONG
WOODWORTH BLVD.
Job No. CPA-855
Dear Mr. Gutierrez:
Attached is Change Order No. 2 for the Proposed City Street Strom Sewer
Improvements along Woodworth Blvd. This change order includes the request for time
extension of 10 days from delays and extra work performed from May to June. The
Contractor completed work outside the original scope of the contract and encountered
delays due to a local utility contractor. The added work includes full depth concrete
repairs, remove and replace sidewalks. install handicap ramps and replace storm sewer
pipe at an inlet tie-in. These items will be paid under existing items and will not increase
the total contract price. We recommend the City of Port Arthur authorize the change to
the contract by adding 10 calendar days to extend the contract end date from July 22,
2018 to August 1, 2018. I have attached Change Order No. 2 which modifies the
contract to reflect this revision for your consideration and action. Should you have any
questions or require additional information, please contact our office.
Sincerely,
Arceneaux Wilson & Cole LLC
TEXAS REGISTERED ENGINEERING FIRM F-16194
Keestan Cole. PE
Vice President
409.724.7888
2901 Turtle Creek Dr.,Suite 320
Port Arthur,TX 77642 Engineering Surveying
awceng.com 7-'o'>.1 10194049
oRAL
C24:4044- tia
Texas General Land Office
crW �► 0- Disaster Recovery
lt)m
PS �6
rge�isHco �
Construction Contract Change Order Request Form
Engineer: Owner(Contractor Locality): Contractor:
Arceneaux Wilson&Cole LLC Norman Highway Construction,
2901 Turtle Creek Dr.,Suite 320 City of Port Arthur Inc.
Port Arthur,TX 77642 444 4th Street P.O.Box 2440
Port Arthur,TX 77642 Orange,TX 77631
Phone No.: 409-724-7888 phone No.:409-983-8100 Phone No.:409-988-0326
Agreement Date:
July 25,2017
Date:June 22, 2018 Contract For(Project Description): GLO Contract No.:
Project Code No.: P21432C-5 Storm Sewer Improvements 12-403-008-7654
along Woodworth Blvd.
Bid Package No.:11 Change Order No.: 2
You are hereby requested to comply with the following changes from the contract plans and specifications:
Item Description of Changes: Quantities, Units, Unit Prices, Decrease in Increase in
No. Change in Completion Scheduled, Etc. Contract Price Contract Price
Change in Contract Price Change in Contract Time (Calendar Days)
Original Contract Price: $1,186,728.00 Original Contract Time: 270 days
Previous Change Order(s): Net Change From Previous
No. 1 to No.1 $ 0.00 Change Orders: 24 days
Contract Price Prior to Contract Time Prior to
this Change Order: $1,186,728.00 this Change Order: 294 days
Net Increase/Decrease of Net Increase/Dccrcase of
this Change Order: $0.00 this Change Order: 10 days
Contract Price With all Contract Time With all
Approved Change Orders: $1,186,728.00 Change Orders: 304 days
Cumulative Percent Change in Contract Price Grantee Contract End Date:
(+/-): + 0.0% (mm/dd/yy) 12 /31/2018
Construction Contract Start Date: Construction Contract End Date:
(mm/dd/yy) 10/27/14 (mm/dd/yy) 08/01/18
Construction Contract Change Order Request Form Page 1 of 3
CDBG Disaster Recovery Program May 2012
6. Is the Texas Commission on Environmental Quality(TCEQ)
clearance still valid?(if applicable) 0 Yes ❑ No
7.Is the TCEQ permit approval still valid? (sewer projects only) 0 Yes 0 No
8.Are the handicapped access requirements/approval
still valid? (if applicable) 0 Yes 0 No
9.Are other Disaster Recovery contractual special condition clearance
still valid? 0 Yes ❑ No
(If no,specify):
NOTE:
* Generally, a cumulative change in the contract price in excess of 25% cannot be
reviewed (18%decrease for counties).
Construction Contract Change Order Request Form Page 2 of 3
CDBG Disaster Recovery Program May 2012
I
IREQUEST FOR EXTENSION OF TIME DUE TO WEATHER OR SUPPLIES
CITY OF PORT ARTHUR
I DATE: 2 2r z
_ , 20 14
I MONTH OF: ITIA c '27,a2. , 20 t
CITY of PORT ARTHUR, TEXAS
I PUBLIC WORKS DEPARTMENT
P.O. BOX 1089
CITY of PORT ARTHUR, TEXAS 77641-1089
IATTENTION: Public Works Department
1 Gentlemen:
We request extension of completion time on our Contract due to the days of
I work lost as specified (list dates actually lost: do not include days not normally
worked such as Saturdays, Sundays, or holidays):
Dates Lost: MAI 2,3, i eg PC 2-0 le,
I �'u in- C., "T. 4i► 11-, V5, 14.)-147r- r ZD l ab
Contractor is requesting 10 working days
1 Days Los 5 x 7+ Calendar Days Requested
Reasons for Request:I 1
m,.A 2, 3, t� - �T 2 G4c3t.-(t 1 �4.--z-- .
iss49I3 ,,r,a - 46, 12- t5 �,(—Fcr.., .-.-� Z.- . re �..e..1 cJ,.-ni..� A C:57- 6 ..l .J ,
Contractor 02 � �l. -s)-' &...)se d ra. jam.
I By:
�
/ 1-3 4-12_,c) 4 11, .�-
l
IApproved for extension of calendar days.
Disapproved.
Date: , 20CITY OF CITY OF PORT ARTHUR,
I TEXAS
BY:
City Manager
I Distribution by City
Original: Public Works Department
xc: Engineer
IContractor
1 CPA Federally Funded