HomeMy WebLinkAbout(3) STREET UPDATE NOVEMBER 20, 2018City of Port Arthur
Streets Update Presentation
Nov. 20, 2018
1
Types of Street Projects
Reconstruction Projects – Projects that address the entire street structure plus drainage improvements, utility replacement or realignment and sidewalks.
Remedial Projects – Projects that can extend the life of the streets by 3 to 5 years by reclaiming and resurfacing the streets for a fraction of the cost of reconstruction. This method
will provide better streets for the citizens while providing the City time to fund their reconstruction projects in the future.
Rehabilitation Projects – Streets that show extensive pavement distress but not to the point that reconstruction is necessary.
2
Reconstruction Street Projects
The following Reconstruction Projects are in the Design Phase:
15th Street from Stillwell to Vicksburg
60th Street from West Port Arthur to Canal
Willow Avenue from Maple to 60th Street
Nashville Street from 7th to Proctor
Sunken Court from Wilson to Twin City
8th Ave from 32nd Street to Dead End
Carolina Avenue from Gulfway to Dead End
-With an accelerated time line these projects are due for review and bid outs by December 2018
3
Status of Reconstruction Street Projects
4
Reconstruction Street Projects Summary
The City will have two projects ready for the bid phase by the end of the year (15th Street and 8th Ave)
The other 6 streets will follow shortly in Jan. 2019. These projects are scheduled to be completed in June 2019
5
Remedial Street Projects
The following streets are to be remediated:
12th Street from 6th Ave. to Woodworth
24th Street from Gulf Ave. to Memorial
9th Street from Houston to Fort Worth
Marshall from 10th St to Gulfway
El Paso from Lakeshore to Howard
8th Street from Williams to Duff
5th Street from Stadium to Duff
6th Street from Brazos to Duff
38th Street from Rachel to Lansing
Forest Dr. from Griffing to Evergreen
42nd Street from 9th Ave to Wentworth
Evergreen Drive from North Park to Tyrrell
3rd Ave from 32nd St to 36th St
Cedar Street from 58th St. to North End
64th Street from Garnett to W. Port Arthur
58th Street from Ray Ave. to Cedar St.
Pine Ave from 60th St. to Dead End
Sharon Dr. from Cambridge to Queens
Waco Ave. from Gulfway to Thomas
6
Status of Remedial Street Projects
7
Status of Remedial Street Projects
8
Status of Remedial Street Projects
9
Status of Remedial Street Projects
10
38th Street
Reclaiming
11
38th Street
Applying Cement Lime
12
38th Street
Mixing Cement Lime
13
38th Street
Compact and Grade
14
Status of Remedial Street Projects
15
Remedial Street Projects Summary
The City has 19 remedial streets to be completed by October 2019
Of the 19 streets, 5 are designated for contractors to accomplish in 28 days of award of contract.
The 14 left on the list are to be completed by City Crew
The City has a new employee starting on Dec. 3 to operate the asphalt machine
With the addition of the new employee, the Street Division will have a dedicated crew for laying down asphalt and will perform the work in-house.
Street Division is equipped with the right equipment To Do the work in-house
16
The Street Division Equipment Inventory
Asphalt Paver
Motor Grader
Padfoot Roller Compactor
Steelwheel Roller Compactor
Bomag Recycler
17
Asphalt Paver
18
Motor Grader
19
Padfoot Roller Compactor
20
Steelwheel Roller Compactor
21
Bomag Recycler
22
Rehabilitation Street Projects
The following streets are for Rehabilitation:
New Orleans Ave. from Thomas to 12th St
New Orleans Ave. from 15th St to Gulfway
Pearl St. from S. 15th Ave. to S. Gulfway
St. Augustine from Procter to 4th St
Bufford St. from S. Gulfway to s. 15th Street
Williams Ave. from Lakeshore to Procter
T.B. Ellison Pkwy from Bridge to Lakefront Dr.
South St. from 8th St. to Delaware
Redbird St. from Dead End to PAISD Aux.
Ferndale Dr. from Highland Dr. to S. Park
Northpark Dr. from W. Park to Evergreen
Wilson Dr. from Evergreen to Woodrow
Griffing Dr. from R/R Tr. To Las Palmas
63rd St. from Diamond to Dead End
Anne St. from Jade to Dead End
Susie St. from Jade to Dead End
Viterbo Rd. from Spur 93 to Dead End
23
Status of Street Rehabilitation Projects
Repaired a 100 foot section of Backridge Rd. (Sabine Pass) (Completed Nov. 9, 2018)
24
Rehabilitation Photo of
Pearl Street
25
Status of Street Rehabilitation Projects
* Repaired a 100 foot section of T.B. Ellison (Completed Nov. 12, 2018)
26
Rehabilitation photos of Redbird and South Street
South Street
Redbird Street
27
Status of Street Rehabilitation Projects
28
Status of Street Rehabilitation Projects
Repaired a 60 foot section of 60th Street (Completed Nov. 9, 2018)
29
Rehabilitation Photos of 63rd , Susie and Anne
Susie
63rd Street
Anne
30
Rehabilitation Projects
The City has 17 Streets designated to be rehabilitated
The City completed 10 streets.
Four Streets were reclassified as Reconstruction because we wanted to improve the drainage system as well as the street pavement.
One Street was reclassified as a Preventative Maintenance Street (Normal Patching and Sealing Work)
In one street, we revised the limits to a *100 foot section
One Street will be completed jointly with Jefferson County Precinct 2
* Repaired a 100 foot section of T.B. Ellison (Completed Nov. 12, 2018)
31
Status update of the PERMA-PATCH material
The Street Division has applied the material on several places in the City and will regularly check on the locations for documentation purposes.
32
Perma-Patch in 6315 Hazel Ave.
33
Perma-Patch in 6315 Hazel Ave.
34
Conclusion
The City will have 2 reconstruction streets ready to be reconstructed by the end of the year. The other 6 streets will follow shortly in Jan. 2019. These projects are scheduled to
be completed in June 2019
The City has 19 remedial streets. Five will be completed in 2019 by contractors. The remaining 14 will be accomplished by City Crew by the end of October 2019.
The City had 17 rehabilitation projects. 10 have been completed and five have been reclassified. One project will be completed jointly with Jefferson County Precinct 2. And for another,
we revised the limits of the project.
The Total Cost to accomplish these projects will be $14.3 Million dollars by the end of Oct. 2019
35
Questions?