Streets Update Presentation
Nov. 20, 2018
Types of Street Projects
Reconstruction Projects – Projects that address the entire street
structure plus drainage improvements, utility replacement or
realignment and sidewalks.
Remedial Projects – Projects that can extend the life of the streets by
3 to 5 years by reclaiming and resurfacing the streets for a fraction of
the cost of reconstruction. This method will provide better streets for
the citizens while providing the City time to fund their reconstruction
projects in the future.
Rehabilitation Projects – Streets that show extensive pavement
distress but not to the point that reconstruction is necessary.
Reconstruction Street Projects
The following Reconstruction Projects are in the Design Phase:
– 15th Street from Stillwell to Vicksburg
– 60th Street from West Port Arthur to Canal
– Willow Avenue from Maple to 60th Street
– Nashville Street from 7th to Proctor
–Sunken Court from Wilson to Twin City
–8th Ave from 32nd Street to Dead End
–Carolina Avenue from Gulfway to Dead End
-With an accelerated time line these projects are due for review and bid outs by December 2018
Status of Reconstruction Street Projects
Street Projects Design Status
District 1
15th Street 100%
Nashville Ave 95%
District 2
Carolina Ave. 95%
District 3
8th Ave 100%
Sunken Court Ph1 95%
Sunken Court Ph2 95%
District 4
Willow Avenue 95%
60th Street 95%
Reconstruction Street Projects Summary
The City will have two projects ready for the bid phase by the end of
the year (15th Street and 8th Ave)
The other 6 streets will follow shortly in Jan. 2019. These projects are
scheduled to be completed in June 2019
Remedial Street Projects
The following streets are to be
remediated:
–12th Street from 6th Ave. to Woodworth
–24th Street from Gulf Ave. to Memorial
–9th Street from Houston to Fort Worth
–Marshall from 10th St to Gulfway
–El Paso from Lakeshore to Howard
–8th Street from Williams to Duff
–5th Street from Stadium to Duff
–6th Street from Brazos to Duff
–38th Street from Rachel to Lansing
–Forest Dr. from Griffing to Evergreen
–42nd Street from 9th Ave to Wentworth
–Evergreen Drive from North Park to Tyrrell
–3rd Ave from 32nd St to 36th St
–Cedar Street from 58th St. to North End
–64th Street from Garnett to W. Port Arthur
–58th Street from Ray Ave. to Cedar St.
–Pine Ave from 60th St. to Dead End
–Sharon Dr. from Cambridge to Queens
–Waco Ave. from Gulfway to Thomas
Status of Remedial Street Projects
Remedial Projects for Bids
District 1
Marshall
Advertised for Bid, Bid Opening on the 28th of
Nov.
District 2
6th St
Advertised for Bid, Bid Opening on the 28th of
Nov.
District 3
42nd St
Advertised for Bid, Bid Opening on the 28th of
Nov.
3rd Ave
Advertised for Bid, Bid Opening on the 28th of
Nov.
District 4
64th St
Advertised for Bid, Bid Opening on the 28th of
Nov.
Status of Remedial Street Projects
District 1
12th St 6th on the list for City Crew
24th St 9th on the list for City Crew
9th St. 2nd on the list for City Crew
El Paso Avenue 11th on the list for City Crew
Status of Remedial Street Projects
District 2
8th St 1st on the list for City Crew
5th St 5th on the list for City Crew
Status of Remedial Street Projects
District 3
38th St
City Crew is currently working on this Project
and is ready for Asphalt
Forest Dr 4th on the list for City Crew
Evergreen Dr. 8th on the list for City Crew
38th Street
Reclaiming
38th Street
Applying Cement Lime
38th Street
Mixing Cement Lime
38th Street
Compact and Grade
Status of Remedial Street Projects
District 4
Cedar St 3rd on the list for City Crew
58th St 7th on the list for City Crew
Pine Ave. 10th on the list for City Crew
Sharon Dr 12th on the list for City Crew
Waco Ave 13th on the list for City Crew
Remedial Street Projects Summary
The City has 19 remedial streets to be completed by October 2019
Of the 19 streets, 5 are designated for contractors to accomplish in 28 days
of award of contract.
The 14 left on the list are to be completed by City Crew
The City has a new employee starting on Dec. 3 to operate the asphalt
machine
With the addition of the new employee, the Street Division will have a
dedicated crew for laying down asphalt and will perform the work in-house.
Street Division is equipped with the right equipment To Do the work in-
house
The Street Division Equipment Inventory
Asphalt Paver
Motor Grader
Padfoot Roller Compactor
Steelwheel Roller Compactor
Bomag Recycler
Asphalt Paver
Motor Grader
Padfoot Roller
Compactor
Steelwheel Roller
Compactor
Bomag Recycler
Rehabilitation Street Projects
The following streets are for
Rehabilitation:
–New Orleans Ave. from Thomas to 12th St
–New Orleans Ave. from 15th St to Gulfway
–Pearl St. from S. 15th Ave. to S. Gulfway
–St. Augustine from Procter to 4th St
–Bufford St. from S. Gulfway to s. 15th
Street
–Williams Ave. from Lakeshore to Procter
–T.B. Ellison Pkwy from Bridge to Lakefront
Dr.
–South St. from 8th St. to Delaware
–Redbird St. from Dead End to PAISD Aux.
–Ferndale Dr. from Highland Dr. to S. Park
–Northpark Dr. from W. Park to Evergreen
–Wilson Dr. from Evergreen to Woodrow
–Griffing Dr. from R/R Tr. To Las Palmas
–63rd St. from Diamond to Dead End
–Anne St. from Jade to Dead End
–Susie St. from Jade to Dead End
–Viterbo Rd. from Spur 93 to Dead End
Status of Street Rehabilitation Projects
District 1
New Orleans Avenue Completed (July 16, 2018)
New Orleans Avenue Completed (July 16, 2018)
Pearl Street Completed (August 17, 2018)
St. Augustine Completed (July 17, 2018)
Bufford Street Completed (July 24, 2018)
Repaired a 100 foot section of Backridge Rd. (Sabine Pass) (Completed Nov. 9, 2018)
Rehabilitation
Photo of
Pearl Street
Status of Street Rehabilitation Projects
District 2
Williams Avenue Reclassified / Reconstruction for Drainage Improvements
T.B. Ellison Pkwy Removed (*see note below) / Revised Limits
South St. Completed (August 23, 2018)
Redbird St. Completed (August 20, 2018)
* Repaired a 100 foot section of T.B. Ellison (Completed Nov. 12, 2018)
Rehabilitation photos of Redbird and South Street
South Street Redbird Street
Status of Street Rehabilitation Projects
District 3
Ferndale Drive Reclassified / Reconstruction for Drainage Improvements
Northpark Drive Reclassified / Reconstruction for Drainage Improvements
Wilson Drive Reclassified / Reconstruction for Drainage Improvements
Griffing Drive Reclassified as Pavement Maintenance
Status of Street Rehabilitation Projects
District 4
63rd Street West Completed (May 9, 2018)
Anne Street Completed (April 24, 2018)
Susie Street Completed (April 25, 2018)
Viterbo Road
To be Completed in March 2019 with the help of Jefferson
County Precinct 2, Inter-local Agreement is being drafted for
City Council Approval
Repaired a 60 foot section of 60th Street (Completed Nov. 9, 2018)
Rehabilitation Photos of 63rd , Susie and Anne
Susie
63rd Street
Anne
Rehabilitation Projects
The City has 17 Streets designated to be rehabilitated
The City completed 10 streets.
Four Streets were reclassified as Reconstruction because we wanted
to improve the drainage system as well as the street pavement.
One Street was reclassified as a Preventative Maintenance Street
(Normal Patching and Sealing Work)
In one street, we revised the limits to a *100 foot section
One Street will be completed jointly with Jefferson County Precinct 2
* Repaired a 100 foot section of T.B. Ellison (Completed Nov. 12, 2018)
Status update of the PERMA-PATCH material
The Street Division has applied the material on several places in the
City and will regularly check on the locations for documentation
purposes.
Perma-Patch in 6315 Hazel Ave.
Perma-Patch in 6315 Hazel Ave.
Conclusion
The City will have 2 reconstruction streets ready to be reconstructed by the
end of the year. The other 6 streets will follow shortly in Jan. 2019. These
projects are scheduled to be completed in June 2019
The City has 19 remedial streets. Five will be completed in 2019 by
contractors. The remaining 14 will be accomplished by City Crew by the end
of October 2019.
The City had 17 rehabilitation projects. 10 have been completed and five
have been reclassified. One project will be completed jointly with Jefferson
County Precinct 2. And for another, we revised the limits of the project.
The Total Cost to accomplish these projects will be $14.3 Million dollars by
the end of Oct. 2019