Loading...
HomeMy WebLinkAbout(3) STREET UPDATE NOVEMBER 20, 2018 PDFCity of Port Arthur Streets Update Presentation Nov. 20, 2018 Types of Street Projects Reconstruction Projects – Projects that address the entire street structure plus drainage improvements, utility replacement or realignment and sidewalks. Remedial Projects – Projects that can extend the life of the streets by 3 to 5 years by reclaiming and resurfacing the streets for a fraction of the cost of reconstruction. This method will provide better streets for the citizens while providing the City time to fund their reconstruction projects in the future. Rehabilitation Projects – Streets that show extensive pavement distress but not to the point that reconstruction is necessary. Reconstruction Street Projects The following Reconstruction Projects are in the Design Phase: – 15th Street from Stillwell to Vicksburg – 60th Street from West Port Arthur to Canal – Willow Avenue from Maple to 60th Street – Nashville Street from 7th to Proctor –Sunken Court from Wilson to Twin City –8th Ave from 32nd Street to Dead End –Carolina Avenue from Gulfway to Dead End -With an accelerated time line these projects are due for review and bid outs by December 2018 Status of Reconstruction Street Projects Street Projects Design Status District 1 15th Street 100% Nashville Ave 95% District 2 Carolina Ave. 95% District 3 8th Ave 100% Sunken Court Ph1 95% Sunken Court Ph2 95% District 4 Willow Avenue 95% 60th Street 95% Reconstruction Street Projects Summary The City will have two projects ready for the bid phase by the end of the year (15th Street and 8th Ave) The other 6 streets will follow shortly in Jan. 2019. These projects are scheduled to be completed in June 2019 Remedial Street Projects The following streets are to be remediated: –12th Street from 6th Ave. to Woodworth –24th Street from Gulf Ave. to Memorial –9th Street from Houston to Fort Worth –Marshall from 10th St to Gulfway –El Paso from Lakeshore to Howard –8th Street from Williams to Duff –5th Street from Stadium to Duff –6th Street from Brazos to Duff –38th Street from Rachel to Lansing –Forest Dr. from Griffing to Evergreen –42nd Street from 9th Ave to Wentworth –Evergreen Drive from North Park to Tyrrell –3rd Ave from 32nd St to 36th St –Cedar Street from 58th St. to North End –64th Street from Garnett to W. Port Arthur –58th Street from Ray Ave. to Cedar St. –Pine Ave from 60th St. to Dead End –Sharon Dr. from Cambridge to Queens –Waco Ave. from Gulfway to Thomas Status of Remedial Street Projects Remedial Projects for Bids District 1 Marshall Advertised for Bid, Bid Opening on the 28th of Nov. District 2 6th St Advertised for Bid, Bid Opening on the 28th of Nov. District 3 42nd St Advertised for Bid, Bid Opening on the 28th of Nov. 3rd Ave Advertised for Bid, Bid Opening on the 28th of Nov. District 4 64th St Advertised for Bid, Bid Opening on the 28th of Nov. Status of Remedial Street Projects District 1 12th St 6th on the list for City Crew 24th St 9th on the list for City Crew 9th St. 2nd on the list for City Crew El Paso Avenue 11th on the list for City Crew Status of Remedial Street Projects District 2 8th St 1st on the list for City Crew 5th St 5th on the list for City Crew Status of Remedial Street Projects District 3 38th St City Crew is currently working on this Project and is ready for Asphalt Forest Dr 4th on the list for City Crew Evergreen Dr. 8th on the list for City Crew 38th Street Reclaiming 38th Street Applying Cement Lime 38th Street Mixing Cement Lime 38th Street Compact and Grade Status of Remedial Street Projects District 4 Cedar St 3rd on the list for City Crew 58th St 7th on the list for City Crew Pine Ave. 10th on the list for City Crew Sharon Dr 12th on the list for City Crew Waco Ave 13th on the list for City Crew Remedial Street Projects Summary The City has 19 remedial streets to be completed by October 2019 Of the 19 streets, 5 are designated for contractors to accomplish in 28 days of award of contract. The 14 left on the list are to be completed by City Crew The City has a new employee starting on Dec. 3 to operate the asphalt machine With the addition of the new employee, the Street Division will have a dedicated crew for laying down asphalt and will perform the work in-house. Street Division is equipped with the right equipment To Do the work in- house The Street Division Equipment Inventory Asphalt Paver Motor Grader Padfoot Roller Compactor Steelwheel Roller Compactor Bomag Recycler Asphalt Paver Motor Grader Padfoot Roller Compactor Steelwheel Roller Compactor Bomag Recycler Rehabilitation Street Projects The following streets are for Rehabilitation: –New Orleans Ave. from Thomas to 12th St –New Orleans Ave. from 15th St to Gulfway –Pearl St. from S. 15th Ave. to S. Gulfway –St. Augustine from Procter to 4th St –Bufford St. from S. Gulfway to s. 15th Street –Williams Ave. from Lakeshore to Procter –T.B. Ellison Pkwy from Bridge to Lakefront Dr. –South St. from 8th St. to Delaware –Redbird St. from Dead End to PAISD Aux. –Ferndale Dr. from Highland Dr. to S. Park –Northpark Dr. from W. Park to Evergreen –Wilson Dr. from Evergreen to Woodrow –Griffing Dr. from R/R Tr. To Las Palmas –63rd St. from Diamond to Dead End –Anne St. from Jade to Dead End –Susie St. from Jade to Dead End –Viterbo Rd. from Spur 93 to Dead End Status of Street Rehabilitation Projects District 1 New Orleans Avenue Completed (July 16, 2018) New Orleans Avenue Completed (July 16, 2018) Pearl Street Completed (August 17, 2018) St. Augustine Completed (July 17, 2018) Bufford Street Completed (July 24, 2018) Repaired a 100 foot section of Backridge Rd. (Sabine Pass) (Completed Nov. 9, 2018) Rehabilitation Photo of Pearl Street Status of Street Rehabilitation Projects District 2 Williams Avenue Reclassified / Reconstruction for Drainage Improvements T.B. Ellison Pkwy Removed (*see note below) / Revised Limits South St. Completed (August 23, 2018) Redbird St. Completed (August 20, 2018) * Repaired a 100 foot section of T.B. Ellison (Completed Nov. 12, 2018) Rehabilitation photos of Redbird and South Street South Street Redbird Street Status of Street Rehabilitation Projects District 3 Ferndale Drive Reclassified / Reconstruction for Drainage Improvements Northpark Drive Reclassified / Reconstruction for Drainage Improvements Wilson Drive Reclassified / Reconstruction for Drainage Improvements Griffing Drive Reclassified as Pavement Maintenance Status of Street Rehabilitation Projects District 4 63rd Street West Completed (May 9, 2018) Anne Street Completed (April 24, 2018) Susie Street Completed (April 25, 2018) Viterbo Road To be Completed in March 2019 with the help of Jefferson County Precinct 2, Inter-local Agreement is being drafted for City Council Approval Repaired a 60 foot section of 60th Street (Completed Nov. 9, 2018) Rehabilitation Photos of 63rd , Susie and Anne Susie 63rd Street Anne Rehabilitation Projects The City has 17 Streets designated to be rehabilitated The City completed 10 streets. Four Streets were reclassified as Reconstruction because we wanted to improve the drainage system as well as the street pavement. One Street was reclassified as a Preventative Maintenance Street (Normal Patching and Sealing Work) In one street, we revised the limits to a *100 foot section One Street will be completed jointly with Jefferson County Precinct 2 * Repaired a 100 foot section of T.B. Ellison (Completed Nov. 12, 2018) Status update of the PERMA-PATCH material The Street Division has applied the material on several places in the City and will regularly check on the locations for documentation purposes. Perma-Patch in 6315 Hazel Ave. Perma-Patch in 6315 Hazel Ave. Conclusion The City will have 2 reconstruction streets ready to be reconstructed by the end of the year. The other 6 streets will follow shortly in Jan. 2019. These projects are scheduled to be completed in June 2019 The City has 19 remedial streets. Five will be completed in 2019 by contractors. The remaining 14 will be accomplished by City Crew by the end of October 2019. The City had 17 rehabilitation projects. 10 have been completed and five have been reclassified. One project will be completed jointly with Jefferson County Precinct 2. And for another, we revised the limits of the project. The Total Cost to accomplish these projects will be $14.3 Million dollars by the end of Oct. 2019 Questions?