INTEROFFICE MEMORANDUM
Date: December 7, 2018
To: The Honorable Mayor and City Council
Through: Harvey Robinson, Interim City Manager
From: Donald G. Stanton, Assistant Director of Utilities
RE: PR 20424—Centrifuge Repair at the Water Treatment Plant
Introduction:
The intent of this Agenda Item is to seek City Council's Ratification for the Emergency Repair
for the repair of a centrifuge for sludge removal. Andritz Separation, of Pittsburg, Texas, was
chosen to do the repairs in the amount of$51,450.00. Budgeted funds are available in account
#410-1252-532.42-00. Emergency authorization from the City Manager was sought due to the
critical nature of sludge removal in the Water Purification process. This is considered to be a
fair and reasonable price for the required work.
Background:
The WTP has two large DS-706 Alfa Laval centrifuges to process sludge at this facility. These
units are estimated at $1,000,000 each. They have been in service since the WTP began
operation in 1998, and occasionally require repair. Currently, the bearings have gone out and
some ceramic tiles are missing from the scroll of one of the units. There are no Port Arthur
vendors that provide this specialized service.
Budget Impact:
These are expensive and complex units that operate in the harshest of environments. As such,
they demand a very stringent preventive maintenance program, and are recommended for re-
build every 5-6 years. The above mentioned repair, in the amount of $51,450.00, has funds
available in account no. 410-1252-532.42-00 (Equipment Maintenance).
"Remember,we are here to serve the Citizens of Port Arthur”
City of
ur1 rthu�
l
Recommendation:
It is recommended that City Council approve P. R. No. 20424, ratifying the emergency
authorization of the repair of the centrifuge at the Water Treatment Plant.
"Remember,we are here to serve the Citizens of Port Arthur"
P. R. No.20424
10/11/18 ds
Page 1 of 2
RESOLUTION NO.
A RESOLUTION RATIFYING THE EMERGENCY
REPAIR OF AN ALFA LAVAL CENTRIFUGE BY
ANDRITZ SEPARATION, OF PITTSBURG, TEXAS IN
THE AMOUNT OF $51,450.00, ACCOUNT NO. 410-1252-
532.42-00 (EQUIPMENT MAINTENANCE).
WHEREAS, a centrifuge at the City's Water Purification Plant had become inoperable
and was in need of emergency repairs; and,
WHEREAS, Andritz Separation of Pittsburg, Texas, who has a history of successful and
dependable service gave a quote for emergency repairs (Exhibit"A"); and,
WHEREAS, this was an emergency repair and the City Manager authorized the
expenditure (Exhibit "B") pursuant to Section 252.022(a)(2), of the Texas Local Government
Code, a procurement necessary to preserve or protect the public health or safety of the
municipality's residents. This procurement is also authorized pursuant to Section 252.022(a)(3),
of the Texas Local Government Code, because of unforeseen damage to public machinery,
equipment, or other property.
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE
CITY OF PORT ARTHUR:
THAT, the City Council of the City of Port Arthur hereby ratifies the emergency repairs
to the Alfa Laval Centrifuge by Andritz Separation of Pittsburg, Texas, in the total amount of
$51,450.00 (Exhibit"A"); and,
THAT, this project will be funded by the Utility Operations O&M budget account no.
410-1252-532.42-00 (Equipment Maintenance); and,
P. R. No. 20424
10/02/18 ds
Page 2 of 2
THAT a copy of the caption of this resolution be spread upon the minutes of the City
Council.
READ,ADOPTED AND APPROVED THIS day of , 2018
at a Regular Meeting of the City Council of the City of Port Arthur, Texas, by the following
vote:
AYES: Mayor ;
Councilmembers:
NOES:
Derrick Freeman
Mayor
ATTEST: APPROVED AS TO FORM:
Sherri Bellard Valecia Tizeno
City Secretary City Attorney
APPROVED FOR ADMINISTRATION:
1c.�t.+u![,/".
Harvey Robinson Clift, illiams, CPPB
Interim City Manager Purchasing Manager
Dr. Hani Tohme, P.E.
Director of Utilities
APPROVED AS TO AVAILABILITY OF
FUNDS:
LT4/ /'
Andrew asquez
Director of Finance
Account No.: 410-1252-532.42-00 (Equipment Maintenance)
Exhibit "A"
(Quote)
AN)RiTL
QUOTATION
Customer:1700.67 Supplier.: Andri#Separation Inc.
City of Port Arthur
PO Box 1089 Contact: Mr Zachary Hanson
Port Arthur TX 77641-1089 Phone: 817-375-4474
Fax: 903-856-3498
Contact: E-mail: zachary.hanson@andritz.com
Fax: +14099838291
Copy to: Date: 09/12/2018
Your inquiry: NOT YET
Our quote no: 20544461 Sales Responsible: WILLIAMS,WILLIAM D.
Ladies and Gentlemen,
We thank you for your inquiry and are pleased to quote as follows:
1. Scope of supply
PULLEY/GEAR FLANGE:
#Thrust bearing outer race has been spinning inside pulley and has grooved the shoulder. Bearing is
discolored and was near failure
#Skim cut thrust bearing shoulder inside pulley to clean
#Machine check pulley to ensure concentricity, parallelism and positive press. Correct as required
#Verify that conveyor stack up is correct after all components have been machined and correct if necessary
#Machine check pulley thrust cap and adjust fit length as required
#Machine check gear flange to ensure concentricity, parallelism and a positive press on main bearing. Correct
if required
#Remove all paint from pulley and gear flange before assembly
LIQUID HEAD I PILLOW BLOCK ASSY:
#Strip all paint from pillow block
#Liquid head bearing journals are in tolerance
#Machine check liquid head to ensure concentricity between stern and bowl alignment fit. Ensure
concentricity between inboard conveyor journal and main bearing journal. Repair these areas if required
# Inboard seal ring is in good condition. No repair required at this time
#Liquid head nabe is in tolerance. No repair currently required
#Pillow block is in tolerance
#Verify that pillow block covers are maintaining positive press on width of main bearing and correct as needed
#Tap-and clear.ail holes, grease passages arra bores. Install new bearings, seats and hardware at assembly
#Paint pillow block and covers dark blue after all work is completed.
TENSION BAR/LOCK NUT:
Page 1 of 6
Andritz Separation Inc Invoice to: Wire ins rumors:
110 Dickson Street Ardritz Separation Inc. Nordea Bank Finland PtC
Pittsburg,TX 75686 Mn:Accounts Receivable .New York Branch
Dept:0312,P.O.Box 120312 SWIFT:NDEAUS3N
(903)856--0445 Dallas.TX 75312-0312 Account:8879433001
Fax:+1(9031856 3498 Federal Tax ID Number.59-3773483 ABA:026010786
AN)RiTL
Our quote no: 20544461
#Conveyor bearing diameter is undersized by .003". Skim cut to clean. Overlay this area with stainless and
machine to correct diameter
# Ensure concentricity of bearing areas to conveyor alignment fit and correct as required
#Strip paint from locking nut and machine polish seal diameter
SOLIDS.HEAD/ PILLOW BLOCK ASSY:
#Strip all paint from pillow block
# Main bearing has spun inside pillow block. Bore of pillow block is slightly scored but still within specified
tolerance
# Bearing journal on head is on size
# Machine check head to ensure concentricity between stem and bowl alignment fit. Ensure concentricity
between inboard conveyor bore and main bearing journal. Repair these areas if required
# Pillow block covers are damaged from main bearing spinning in pillow block. Machine pillow block covers to
clean shoulder and maintain positive press on width of main bearing
#Tap and clean all holes, grease passages and bores. Install new bearings, seals and hardware at assembly
#Paint pillow block and covers dark blue after all work is completed
BOWL ASSEMBLY:
#Wear ring at discharge end of conical has a few tiles that are broken. Fill in damaged areas with Belzona
epoxy to prevent further erosion
#Wear saddles are in good condition
#Mechanically clean all residue and stuck on product with a wire wheel
#Conical section has grooving in ID from unknown cause. No repair necessary at this time for grooving issue
#Machine check bowl and conical section to ensure concentricity of alignment fits and that faces are parallel
CONVEYOR ASSEMBLY:
#Conveyor has approximately(10) broken tiles. Replace with new
# Feed accelerator housing is in good condition. No repairs required at this time
#Conveyor feed nozzles are in good condition
#Machine check conveyor bearing housing for run-out and correct as necessary
# Machine check conveyor for concentricity and parallelism on both main register fits and face. Correct if
required
#Tap and clean all holes and install balance arbors
#Verify that conveyor is straight and balance to ISO G-1.0 standards
#After balance install new bearings, seals, 0-rings and hardware
GEARBOX:
#Strip all paint from gearbox and components
# 1st stage pinion bearing diameter is undersize- Replace with new
#Machine polish 1st stage journals to smooth slight scarring
#Machine polish 1st stage gear bores
#2nd stage journals are severely scored. Undercut journals and sleeve with bronze
#Machine polish 2nd stage gear bores
#Machine check gear case for run-out and correct as needed
#Machine check 1st and 2nd stage covers for run-out and correct as required
#Machine check 1st and 2nd stage cage assemblies for run-out and correct if needed
Page 2 of 6
— - Anther Separation Inc. invoice to: Wire rnstnlctlons:
110 Dickson Street Andaz Separation,nc. Nordea Bank Fnland PLC
PA1a.5ury.TX 75686 Attn:Accounts Receivable New York Branch
Dept 0312.P.O.Box 120312 SWIFT•NDEAUS3N
Tel:+1(903)856-0445 DallasTX 75312-0312 Account:8879433001
Fax:r1(903)856-3498 Federal Tax 112 Number.59-3773483 ABA:026010786
R TL
Our quote no: 20544461
ASSEMBLY I TEST:
#After all repair work has been performed install conveyor assembly in bowl
#Install head and gearbox.Verify that gearbox pinion and case run-out are at or below.005"TIR
#Test ani trim balance to acceotable.tolerance
#Paint the pillow blocks dark blue and pulley and gearbox safety orange
#Preece to ship
Item Product ID No. SIW Quantity Unit Unit Price Amount
10 REPAIR 100031960 1 EA 34,500.00 34,500.00
7A MATERIALS FOR Rcr�rP5IR OF 129.999000 1 p IC' (I tl nn 16 050 rwS
LV FOR REPAIR 1 I(. 1 I ,7.l V.VV IW,JWW.VV
DS706
Items total 51,450.00
Total Amount USD 51,450.00
•S=Spare Parts,W=Wear Parts
Technical contact: Steve Howe/Phone: +13047572678/steve.howe@andritz.com
andritz.com
Terms and Conditions
2. Delivery Time:
after receipt of order and any clarifications.
3 . Terms of delivery:
Our terms of deliv.ry arp FXW ORIGIN, accordion to INCOTFRMS 7010.
4. Terms of Payment:
Within 30 days Due net
(1%default interest per month for delayed payment).
5. Validity of quotation:
This quotation is valid-to1-21-3112018-.
Other Terms:
6. TERMS APPLICABLE
In.u.....a.wow.>o..wr...d SM✓..ra1 Pnn.a.na/ppomen of Somme*melee.nWye.pints.color Nome n whom rt psi w.y..e to O.a.r..nor"i.>pa..to read,Pr.tleW.dosr..S.awed re uproar,
Imo m fl wpm.*rt....anger.on. ocoroportco of trto toms and Contillotto d 9.1e adS Ad.*lie b...,wall.re ties* .o two emm*.n 4Ponwhen denB.o.r.....No or no.oelme Areuea.neyaaae%to
..no rse..^)...mea a o.dso ora.lora..re Ar.w..we.o n4.oer.a poaa+.ev4aw.porta mob,l..a+adn d..e...MottoY.na'S..oe.l.Mose Ielm en]eorw".of Sole mortar Salsa mmd..w...a..e na.o
on,s4 el other oddball.Ob Ow.loon end tiltrs N Burr.rid Sallow tSp e.Md.v.o rged.South MM.Sod m..arnr.e Of Buyer without Snls no.lee,coo the e.Yra Seger owes*ammo to am.own...I,
Page 3 of 6
AndM1 z Separation Inc. Invoice-to: Wire Inetnlctione:
110 Dickson Street Andrilz Separation Inc. Nordea Bank Finland PLC
Pittsburg,TX 75686 Attn:Accounts Receivable ,New York Branch
Dept:0312.P.O.Box 120312 SWIFT:NDEAUS3N
Tel:41(903)858-0445 Dallas.TX 7 5312-031 2 Account:8879433001
Fax:•1(903)856-3498 Federal Tex ID Number.593773483 ABA:026010786
Exhibit "B"
(Approval Letter, Signed by City Manager)
City of v47404
---
ort rthu��
Teras
INTEROFFICE MEMORANDUM
UTILITY DEPARTMENT-ADMINISTRATION DIV.
Date: September 14, 2018
To: Harvey Robinson, Interim City Manager
From: Jeffrey, D. Wyble, Water Treatment Superintendent
RE: Emergency repair of dewatering centrifuge
Mr. Robinson,
We have two centrifuges that are critical to the water treatment process because they process the waste
material that is removed during treatment. Currently one unit is already being repaired and the other has
since gone down as well. It is imperative that we get this unit repaired because without the ability to
process waste, the treatment process gets backed up and it becomes harder and more costly to treat :he
City's drinking water. /Qe/aa/r cos7L ,s 157 yco
Thank You,
Jeffrey D. Wyble
Water Treatment Superintendent
City of Port Arthur
Emergency Pe is. ion is 1. - to proceed with the repair as written above.
Hary- Robinson
Interim City Manager
"Remember we are here to serve the Citizens of Port Arthur"