INTEROFFICE MEMORANDUM
Date: December 7, 2018
To: The Honorable Mayor and City Council
Through: Harvey Robinson, Interim City Manager
From: Alberto Elefano,P.E., City Engineer
RE: P.R. 20590—W. 8th Street Roadway Pavement Rehabilitation Project, Change
Order No. 02
Introduction:
Acceptance of Change Order No. 02 for the W. 8th Street Roadway Pavement Rehabilitation
Project.
Background:
The City of Port Arthur awarded a contract for the West 8th Street Roadway Pavement
Rehabilitation Project to Oldcastle Materials Texas, Inc. of Beaumont, Texas. The change
order includes upgrading the existing driveway culverts in all residential driveways scheduled
to be removed and replaced up to the right-of-way. The Contractor discovered concrete under
the existing asphalt at five of the intersections that required adding, removing and adjusting
several bid items. Also during construction, a water leak was discovered that caused roadway
failure and storm sewer system damaged at Roosevelt and Grannis intersections which made it
necessary to replace the damaged storm sewer system and required full depth repairs at the
intersections. And for the last item in this change order, a resident required a temporary
handicap walkway. The total cost for this change order will increase the contract amount
$83,085.64 to a new total contract amount of$1,282,034.64
"Remember,we are here to serve the Citizens of Port Arthur”
P.O.Box 1089 * Port Arthur,Texas 77641-1089 * 409.983.8101 * FAX 409.982.6743
P.R. 20590
12/4/18 ACE
RESOLUTION NO.
A RESOLUTION AUTHORIZING THE CITY MANAGER TO EXECUTE
CHANGE ORDER NO. 02 TO THE CONTRACT BETWEEN THE CITY OF
PORT ARTHUR AND OLDCASTLE MATERIALS TEXAS, INC. OF
BEAUMONT, TEXAS FOR THE WEST 8TH STREET ROADWAY
PAVEMENT REHABILITATION PROJECT, INCREASING THE
CONTRACT AMOUNT BY $83,085.64 TO A NEW CONTRACT AMOUNT
OF $1,282,034.64, FUNDING IS AVAILABLE IN GLO ROUND 2.2
PROGRAM, PROJECT NO. I22W8, ACCOUNT NO. 145-1201-532.59-
00, $531,215.00 AND PROJECT NO. I22W8, CAPITAL
IMPROVEMENTS ACCOUNT 307-1601-591.86.00, $750,819.64
WHEREAS, per Resolution No. 18-267, the City Council awarded a contract for
the West 8th Street Roadway Pavement Rehabilitation Project to Oldcastle Materials
Texas, Inc. of Beaumont, Texas with a projected budgetary impact of $1,248,949.00;
and,
WHEREAS, per Resolution No. 18-331, Change Order No. 01 removed the
contingency bid item, decreasing the contract price by $50,000.00 to a new contract
amount of $1,198,949.00; and,
WHEREAS, proposed of Change Order No. 02 will increase the contract amount
by $83,085.64 to a new total of $1,282,034.64 for the purpose of upgrading the
existing driveway culverts in all residential driveways scheduled to be removed and
replaced up to the right-of-way; and,
WHEREAS, the Contractor discovered concrete under the existing asphalt at five
of the intersections that required adding, removing and adjusting several bid items;
and,
WHEREAS, during construction it was discovered that a water leak caused
roadway failure and storm sewer system damaged at Roosevelt Avenue and Grannis
Avenue intersections which made it necessary to replace the damaged storm sewer
system and required full depth repairs at the above mentioned intersections; and,
P.R. 20590
12/4/18 ACE
WHEREAS, a resident required a temporary handicap walkway which is also
included in this change order; now, therefore,
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PORT
ARTHUR:
THAT, the facts and opinions in the preamble are true and correct; and,
THAT, Change Order No. 02 is herein approved and the City Manager is
authorized to execute said Change Order No. 02 (attached as Exhibit "A") to the
contract between the City of Port Arthur and Oldcastle Materials Texas, Inc. of
Beaumont, Texas; and,
THAT, Change Order No. 02 will increase the contract amount by $83,085.64 to
a new total of $1,282,034.64; and,
THAT, a copy of the caption of this Resolution be spread upon the Minutes of
the City Council.
READ, ADOPTED AND APPROVED this the day of , A.D. 2018
at a meeting of the City of Port Arthur, Texas by the following vote:
Ayes: Mayor:
Councilmembers:
Noes:
Mayor
Derrick Freeman
P.R. 20590
12/4/18 ACE
ATTEST:
City Secretary
Sherri Bellard
APPROVED AS TO FORM: APPROVED FOR ADMINISTRATION:
1 dor ' -0
Valecia Tizeno a Harvey Robinson
City Attorney Interim City Manager
Hani Thome, P.E.
Director of Public Works
APPROVED AS FOR AVAILABILITY OF
FUND :
IW.M.1\/
Andrew Vasquez, CPA
Director of Finance
(114-�il 02.6.--
Clifton Williams CPPB
Purchasing Manager
p.w
ARCENEAUX WILSON&COLE
engineering i surveying'planning
November 26. 2018
Mr. Alberto Elefano, PE
City Engineer
City of Port Arthur
444 Fourth Street
Port Arthur, Texas 77640
RE: PROPOSAL FOR CHANGE ORDER NO. 2
Roadway Pavement Rehabilitation along West 8th Street from Foley
Avenue to Joe Louis A venue
JOB NO: CPA-840
Dear Mr. Elefano:
Attached is Change Order No. 2 for Roadway Pavement Rehabilitation along West 8th Street
from Foley Avenue to Joe Louis Avenue. This change order includes upgrading the existing
driveway culverts on all residential driveways scheduled to be removed and replaced up to the
right-of-way. In addition. the Contractor discovered concrete under the existing asphalt at five of
the intersections that will require adding, removing and adjusting several bid items for the contract.
The City requested the Contractor to investigate a possible leak and roadway failure at the
Roosevelt Avenue and Grannis Avenue intersections that developed into replacing the damaged
storm sewer system and required a full depth concrete repair that will be added through this
change order. Once the construction on West 8th Street began we were approached by a resident
near Joe Louis Avenue that required a temporary handicap walkway. We received approval from
the City to accommodate the resident by adding an item in this contract to order and install the
temporary access route. The total cost for this change order will increase the contract amount
$83,085.64 to a new total contract amount of $1,282,034.64. Please note the City has the option
to use seeding as opposed to the block sodding which would decrease the contract amount below
the original contract price awarded in July.
409.724.7888
2901 Turtle Creek Dr.,Suite 320
Port Arthur,TX 77642 Engineering Surveying
awceng.com =-1n'94 12194049
A.111, emit
wAr
We recommend that the City of Port Arthur authorize this change to the contract. I have attached
Change Order No. 2 which modifies the contract to reflect this revision for your consideration and
action. Should you have any questions or require additional information, please contact our office.
Sincerely,
Arceneaux Wilson & Cole LLC
TEXAS REGISTERED ENGINEERING FIRM F-16194
Keestan Cole, PE
Vice President
Amm
t`1.
V ARCENEAUX WILSON&COLE
CHANGE ORDER NO. 2
DATE: November 26, 2018 JOB NO. CPA-840
AGREEMENT DATE: July 10, 2018
NAME OF PROJECT: ROADWAY PAVEMENT REHABILITATION ALONG WEST 8T"
STREET FROM FOLEY AVENUE TO JOE LOUIS AVENUE
OWNER: CITY OF PORT ARTHUR
CONTRACTOR: OLD CASTLE MATERIALS TEXAS, INC., DBA GULF COAST AN
OLDCASTLE COMPANY
The following changes are hereby made to the CONTRACT DOCUMENTS:
I. Edit the following Items to the Contract and Scope of Work:
a. Add the following Bid Items:
i. Bid Item No. 0104-6001 Remove Conc (Pay) $ 10.020.00
340 SY x$30.00/SY
ii. Bid Item No. 0105-0003 Removing Base and Asphalt Pay (3.5") $ 14,847.00
2,121 SY x$7.00/SY
iii. Bid Item No. 0361-0001 Full Depth Concrete Repair $ 19,643.00
(CL P) (8")
1 LS x$19,643.00/LS
iv. Bid Item No. 0464-6002 RC Pipe (CL III) (15") $ 67,200.00
640 LF x$105.00/LF
v. Bid Item No. 0465-0001 Remove and Replace $ 5,250.00
Storm Manhole (Conflict Structure)
1 EA x $5,250.00/EA
vi. Bid Item No. 0491-0001 Treated Plywood (Temporary Walkway) $ 324.64
8 EA x$40.58/EA
CHANGE ORDER NO. 2
AIM CHANGE
COW
November 26, 2018
A M Job No. CPA-840
AlirAr ARCENEAUX WILSON&COLE
vii. Bid Item No. 0713-6005 Crack Cleaning and Sealing (JCP) $ 12,100.00
2,000 LF x$6.05/LF
b. Increase the following Bid Items:
i. Bid Item No. 0104-6015 Remove Conc (Sidewalk) $ 448.00
14 SY x $32.00/SY
ii. Bid Item No. 0104-6017 Remove Conc (Driveway) $ 1,080.00
30 SY x $36.00/SY
iii. Bid Item No. 0104-6022 Remove Conc (Curb and Gutter) $ 572.00
110 LF x$5.20/LF
iv. Bid Item No. 0496-6007 Remove Str(Pipe) $ 17,500.00
625 LF x$28.00/LF
v. Bid Item No. 0529-0001 Concrete Curb and Gutter $ 720.00
30 LF x $24.00/LF
vi. Bid Item No. 0530-6004 Driveways (Concrete) $ 1,460.00
20 SY x$73.00/SY
vii. Bid Item No. 0531-6001 Concrete Sidewalk $ 352.00
4 SY x $88.00/SY
c. Decrease the following Bid Items:
i. Bid Item No. 0105-0002 Removing Base and Asphalt Pay (9.5") $ (14,847.00)
2,121 SY x $7.00/SY
ii. Bid Item No. 0247-0001 Fl Bs (Cmp in Plc) (Ty A Gr 3) (8") $ (31.996.00)
1,684 SY x $19.00/SY
iii. Bid Item No. 0260-6001 Lime (Hydrated Lime) (Slurry) $ (9.800.00)
49 TONS x$200.00/TON
of 4
CHANGE ORDER NO. 2
Alla CHANGE
November 26, 2018
allillit
'`'. Job No. CPA-840
�. ARCENEAUX WILSON&COLE
,ngn-cr.nc.I surveying i p nni
iv. Bid Item No. 0260-6073 Lime Treatment (Subgrade) (8") $ (11.788.00)
1.684 SY x$7.00/SY
SUBTOTAL $ 83,085.64
a
3of4
��= CHANGE ORDER NO. 2
'`'. MAK November 26, 2018
�. Job No. CPA-840
ARCENEAUX WILSON&COLE
engineering I surveying 1 plonning
CHANGE TO CONTRACT PRICE:
ORIGINAL CONTRACT PRICE: S1,248.949.00
CURRENT CONTRACT PRICE adjusted by previous CHANGE ORDER(S): $1,198,949.00
The CONTRACT PRICE due to this CHANGE ORDER will be [increased] [decreased]
by: $83,085.64 Dollars
The new CONTRACT PRICE, including this CHANGE ORDER, will be $ 1,282,034.64
CHANGE TO CONTRACT TIME:
ORIGINAL CONTRACT TIME: 142 Calendar Days
CURRENT CONTRACT TIME adjusted by previous CHANGE ORDER: 142 Calendar Days
CURRENT DATE OF COMPLETION: December 21, 2018
CONTRACT TIME due to this CHANGE ORDER will be increased by 0 Calendar Days
The New DATE OF COMPLETION: December 21, 2018
No other Terms and Conditions of the Contract are changed as a result of this Change Order.
Contractor's acceptance of Change Order relieves OWNER of any liability for additional costs
incurred by Contractor in his performance of the work covered by the Change Order.
RECOMMENDED BY ENGINEER: ACCEPTED BY:
ARCENEAUX WILSON & COLE LLC [CONTRACTOR,OFFICER OR OWNER'
OLD CASTLE MATERIALS TEXAS, INC.,
DBA GULF COAST AN OLD CASTLE
COMPANY
ACCEPTED BY:
CITY of PORT ARTHUR
4 u 1 4
Texas General Land Office fice
Q - • h�
Disaster Recovery
1- .. m
cilf ST9@IISHED
‘
Construction Contract Change Order Request Form
Engineer: Owner (Contractor Locality): Contractor:
Arceneaux Wilson &Cole City of Port Arthur Oldcastle Materials Texas, Inc.,
2901 Turtle Creek Dr., Suite 320 dba Gulf Coast an Old Castle
Port Arthur, TX 77642 444 4th Street Company
Port Arthur, TX 77642 Agreement Date: 07-10-18
Phone No.: 409-724-7888
Phone No.:409-983-8100 Phone No.: 409-860-4459
Date: November 21, 2018 Contract For(Project Description): GLO Contract No.:
Project Code No.: P21431-4 Roadway Pavement 12-403-008-7654
Rehabilitation along West 8th
Street from Foley Avenue to Joe
Bid Package No.: 225302- Louis Avenue Change Order No.: 2
1_Bid 7
You are hereby requested to comply with the following changes from the contract plans and specifications:
Item Description of Changes: Quantities, Units, Unit Prices, 1 Decrease in Increase in
No. Change in Completion Scheduled, Etc. Contract Price Contract Price
1a. Add Bid Item No. 0104-6001 Remove Conc (Pay) $ 10,020.00
340 SY @ $30.00/SY
lb. Add Bid Item No. 0105-0003 Removing Base and
Asphalt Pay (3.5") 2,121 SY @ $7.00/SY $ 14,847.00
1c. Add Bid Item No. 0361-0001 Full Depth Concrete
Repair (CL P) (8") 1 LS @ $19,643.00/LS $ 19,643.00
1d. Add Bid Item No. 0464-6002 RC Pipe (CL III) (15")
640 LF @ $105.00/LF $ 67,200.00
le. Add Bid Item No. 0465-0001 Remove and Replace
Storm Manhole (Conflict Structure) $ 5,250.00
1 EA @ $5,250.00/EA
1f. Add Bid Item No. 0491-0001 Treated Plywood $ 324.64
(Temporary Walkway) 8 EA @ $40.58/EA
Add Bid Item No. 0713-60 05 Crack Cleaning and
1g. Sealing (JCP) 2,000 LF @ $6.05/LF $ 12,100.00
Construction Contract Change Order Request Form Page 1 of 3
August 2018
Item Description of Changes: Quantities, Units, Unit Prices, Decrease in Increase in
No. Change in Completion Scheduled, Etc. Contract Price Contract Price
2a Increase Bid Item No. 0104-6015 Remove Conc $ 448.00
(Sidewalk) 14 SY @ $32.00/SY
2b Increase Bid Item No. 0104-6017 Remove Conc
(Driveway) 30 SY @ $36.00/SY $ 1,080.00
2c Increase Bid Item No. 0104-6022 Remove Conc $ 572.00
(Curb and Gutter) 110 LF @ $5.20/LF
2d Increase Bid Item No. 0496-6007 Remove Str(Pipe) $ 17,500.00
625 LF @ $28.00/LF
2e Increase Bid Item No. 0529-0001 Concrete Curb and $ 720.00
Gutter 30 LF @ $24.00/LF
2f Increase Bid Item No. 0530-6004 Driveways
(Concrete) 20 SY @ $73.00/SY $ 1,460.00
Increase Bid Item No. 0531-6001 Concrete Sidewalk
2g. 4 SY @ $88.00/SY $ 352.00
3a. Decrease Bid Item No. 0105-0002 Removing Base
and Asphalt Pay (9.5") (-) 2,121 SY @ $7.00/SY $ - (14,847.00)
3b. Decrease Bid Item No. 0247-0001 Fl Bs (Cmp in Plc) $ - (31,996.00)
(Ty A Gr 3) (8") (-)1,684 SY @ $19.00/SY
3c. Decrease Bid Item No. 0260-6001 Lime (Hydrated $- (9,800.00)
Lime) (Slurry) (-) 49 TONS @ $200.00/TON
3d. Decrease Bid Item No. 0260-6073 Lime Treatment $_ (11,788.00)
(Subgrade) (8") (-) 1,684 SY @ $7.00/SY
SUBTOAL $ 83,085.64
Construction Contract Change Order Request Form Page 2 of 3
August 2018
Change in Contract Price Change in Contract Time (Calendar Days)
Original Contract Price: $ 1,248.949.00 Original Contract Time: 142 days
Previous Change Order(s): Net Change from Previous
No. 1 to No. 2 $ - (50.000.00) Change Orders: 0 days
Contract Price Prior to Contract Time Prior to
this Change Order: $ 1,198,949.00 this Change Order: 142 days
Net Increase/Decrease of Net Increase/Decrease of
this Change Order: $ 83,085.64 this Change Order:
Contract Price With all Contract Time With all
Approved Change Orders: $ 1,282,034.64 Change Orders: 142 days
Cumulative Percent Change in Contract Price (+/-): Grantee Contract End Date:
2.65% (mm/dd/yy) 12 /31 /2018
Construction Contract Start Date: Construction Contract End Date:
(mm/dd/yy) 08 /01 /2018 (mm/dd/yy) 12 /21 /2018
Reimbursements of costs included in this change order are subject to review by the GLO-DR program.
* This document may be executed prior to submission for GLO-DR program review, but all parties
involved will be held responsible if the change order or the amendment warranted as a result of
this change order is not in compliance with CDBG or HUD requirements.
RECOMMENDED: APPROVED: ACCEPTED:
By: By: By:
ENGINEER OWNER CONTRACTOR
Date: Date: Date:
Construction Contract Change Order Request Form Page 1 of 3