HomeMy WebLinkAboutPR 20710: CHANGE ORDER NO. 1 - NORTH PEDESTRIAN BRIDGE REPAIR PROJECT .,:.-r .....4 . City of ort rthut� Te.ru s www.POrtArthurTx.gov INTEROFFICE MEMORANDUM Date: February 19, 2019 To: The Honorable Mayor and City Council Through: Harvey Robinson, Interim City Manager From: Chandra Alpough, Director of Parks and Recreation OQL, RE: P.R. 20710- Change Order No. 1 —North Pedestrian Bridge Repair Project Introduction: The intent of this Agenda Item is to request the City Council's approval for the City Manager to execute Change Order No. 1 to the contract between the City of Port Arthur and SKR Construction of Port Arthur, Texas for the North Pedestrian Bridge Repair Project at the Babe Zaharias Golf Course increasing the contract amount by $1,881.00 and increasing the contract time by 4 days for a new contract amount of $28,988.00 and new ending date of March 15, 2019. Background: On January 8, 2019, per Resolution No. 19-004, the City Council awarded a contract for the north pedestrian bridge repair at the Babe Zaharias Golf Course to SKR Construction of Port Arthur,Texas in the amount of$27,107.00. After starting the project,rotten wood boards were found on the binds of the bridge. SKR Construction is requesting a change order in the amount of$1,881.00 to remove the rotten boards and install new ones and requesting 4 additional days to the complete the project due to this unforeseen situation. Budget Impact: Funds are available in the following account: 103-2001-601.87-00, Golf Course Fund Account Recommendation: It is recommended that the City Council approve P. R. No. 20710 authorizing the City Manager to execute a Change Order No. 1 to the contract between the City of Port Arthur and SKR Construction of Port Arthur, Texas for the North Pedestrian Bridge Repair Project at the Babe Zaharias Golf Course increasing the contract amount by $1,881.00 and increasing the contract time by 4 days for a new contract amount of $28,988.00 and new ending date of March 15, 2019. "Remember,we are here to serve the Citizens of Port Arthur" P.O.Box 1089 X Port Arthur,Texas 77641-1089 X 409.983.8182 X FAX 409.983.8294 P.R.# 20710 02/19/19 ca RESOLUTION NO. A RESOLUTION AUTHORIZING THE CITY MANAGER TO EXECUTE CHANGE ORDER NO. 1 TO THE CONTRACT BETWEEN THE CITY OF PORT ARTHUR AND SKR CONSTRUCTION OF PORT ARTHUR, TEXAS FOR THE NORTH PEDESTRIAN BRIDGE REPAIR PROJECT AT THE BABE ZAHARIAS GOLF COURSE INCREASING THE CONTRACT AMOUNT BY $1,881.00 AND INCREASING THE CONTRACT TIME BY 4 DAYS FOR A NEW CONTRACT AMOUNT OF $28,988.00 AND NEW ENDING DATE OF MARCH 15, 2019 FUNDING AVAILABLE IN GOLF COURSE FUND ACCOUNT NO. 103-2001-601.87-00 WHEREAS, on January 8, 2019, per Resolution No. 19-004, the City Council awarded a contract for the north pedestrian bridge repair at the Babe Zaharias Golf Course to SKR Construction of Port Arthur, Texas in the amount of$27,107.00; and, • WHEREAS, rotten wood was discovered on the binds of the bridge and needs to be removed; and, WHEREAS, SKR Construction has requested to remove the rotten wood boards and install new boards in the amount of$1,881.00 and increase the time by 4 days (attached hereto as Exhibit "A") for a new contract amount of $28,988.00 and new contract ending date of March 15, 2019; now therefore, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PORT ARTHUR TEXAS: Section 1. THAT the facts and opinions in the preamble are true and correct. Section 2. THAT the City Manager of the City of Port Arthur is hereby authorized and directed to execute, on behalf of the City of Port Arthur, Change Order No. 1 to the contract with SKR Construction of Port Arthur, Texas, increasing the contract amount by $1,881.00 to remove rotten wood boards and install new boards for a new contract amount of$28,988.00 and increasing the contract time by 4 days for a new contract ending date of March 15, 2019. P.R.# 20710 02/19/19 ca Section 3. THAT a copy of the caption of this resolution be spread upon the minutes of the City Council. READ, ADOPTED AND APPROVED THIS day of , A.D., 2019, at a Regular Meeting of the City Council of the City of Port Arthur, by the following vote: AYES:(Mayor) Councilmembers: NOES: Derrick "Ford" Freeman Mayor ATTEST: Sherri Bellard City Secretary APPROVED AS TO FORM: Val Tizen sq. City Attorney APPROVED FOR ADMINISTRATION: Harvey Robinson Interim City Manager P.R.# 20710 02/19/19 ca I1 1 / UU Chandra Alpough Director of Parks and Recreation APPROVED AS TO AVAILAB ITY OF FUNDS: Lt\ Andrew 'asquez, CPA Director of Finance *A, (4.4.404„.... Clifton illiams, CPPB Purchasing Manager EXHIBIT "A" A ,_„„„, SKR Construction Inc. 6625 Jade Ave Port Arthur TX 77640 409-982-0063 (409) 982-0470 fax Attn: Chandra D. Alpough February 18, 2019 City of Port Arthur TX Parks and recreations This letter is to let you know that in The Babe Zaharias Golf club; we have found out that there is some rotten wood on the binds of the bridge, about 'A" of the bind has rotten wood on it, we are going to need four more days of time to be able to remove the rottened wood and install new boards on it . And the price is going to be increase by $ 1,881.00 (one Thousand eight hundred and eighty one Dollars) Per contract demolish work unit price $5.75 198sf x $ 5.75 = $ 1138.50 Per contract Surface deck unit price $ 3.75 198 sf x $ 3.75 + $ 742.50 The demolish and installation of the wood $1,138.50+$742.50=$ 1,1881.00. Sincerely t8 - l7 Jose Sanchez Date SKR Construction Inc. CHANGE ORDER NO. 01 DATE: February 20, 2019, P.R. 20710 ORGINAL AGREEMENT DATE: January 8, 2019 ORIGINAL ENDING DATE: March 11, 2019 SKR CONSTRUCTION, INC. PROJECT DESCRIPTION: North Pedestrian Bridge Repair Project at Babe Zaharias Golf Course CHANGE TO CONTRACT TERM: ORIGINAL CONTRACT TERM: 30 Days CURRENT CONTRACT TERM (adjusted by previous CHANGE ORDER): N/A The Contract Term due to this CHANGE ORDER will be (increased/decreased by: 4 Days The new CONTRACT TERM including the CHANGE ORDER will be: 34 Days The new CONTRACT DATE: March 15,2019 CHANGE TO CONTRACT AMOUNT: ORIGINAL CONTRACT amount: $27,107.00 CURRENT CONTRACT PRICE (adjusted by previous CHANGE ORDER): N/A The Contract Amount due to this CHANGE ORDER will be (increased/decreased) by: $1,881.00 The new CONTRACT AMOUNT including the CHANGE ORDER will be: $28,988.00 SKR Construction Signature Jose Sanchez Printed Name CITY OF PORT ARTHUR Harvey Robinson Interim City Manager