HomeMy WebLinkAboutPR 20915: CHANGE ORDER NO. 1 FOR THE RECLAMATION AND ROAD RESURFACING PROJECT 1 Cit'of 4 ort rtl:u�— Mtus www.PortArthurTx.gov INTEROFFICE MEMORANDUM Date: July 24,2019 To: The Honorable Mayor and City Council Through: Rebecca Underhill, Interim City Manager From: Alberto Elefano, PE—Director of Public Works RE: PR 20915—Change Order No. 1 for the Reclamation and Road Resurfacing Project. Marshall Ave. (ST1P37); 6th Street(ST1P29); 42"d Street(ST1P24); 64th Street(ST1P27); 3rd Ave. (ST1P57) Introduction: The intent of this Agenda Item is for the acceptance of Change Order No. 1 for the Reclamation and Road Resurfacing Project for the following streets: Marshall Avenue(10th Street South to Gulfway Drive North); 6th Street(Williams Avenue West to Duff Drive East); 42nd Street(9th Avenue West to Wentworth Avenue East); 3rd Avenue (32"d Street South to 36th Street); and 64th Street(Garnett Avenue to West Port Arthur Road East) for the contract amount of$570,883.50. Background: LD Construction of Beaumont, Texas was awarded the Reclamation and Road Resurfacing Project for the following streets: Marshall Avenue (10th Street South to Gulfway Drive North); 6th Street (Williams Avenue West to Duff Drive East); 42nd Street (9th Avenue West to Wentworth Avenue East); 3rd Avenue (32nd Street South to 36th Street); and 64th Street(Garnett Avenue to West Port Arthur Road East) for the contract amount of $570,883.50. LD Construction of Beaumont, Texas adjusted bid quantities to reflect a decrease in reclamation,concrete and asphalt.Proposed Change Order No. 1,PR 20915,has been submitted for the removal of the bid items, decreasing the original contract amount of$570,883.50 by $131,624.17 to the new contract amount of$424,311.33. Budget Impact: Funds are available in the following accounts: Capital Projects — Streets Account No. 307-1601-591.86-00. The total budget impact will be $424,311.33. "Remember,we are here to serve the Citizens of Port Arthur" P.O.Box 1089 X Port Arthur,Texas 77641-1089 X 409.983.8101 X FAX 409.982.6743 Recommendation: It is recommended that the City of Port Arthur City Council approve PR 20915 authorizing the City Manager to execute Change Order No. 1 with LD Construction of Beaumont, Texas for the Reclamation and Road Resurfacing Project. PR No. 20915 07/22/2019 mje Page 1 of 3 RESOLUTION NO. A RESOLUTION AUTHORIZING THE CITY MANAGER TO EXECUTE CHANGE ORDER NO. 1 TO THE CONTRACT BETWEEN THE CITY OF PORT ARTHUR AND LD CONSTRUCTION OF BEAUMONT, TEXAS FOR THE RECLAMATION AND ROAD RESURFACING PROJECTS FOR MARSHALL AVENUE (10TH STREET SOUTH TO GULFWAY DRIVE NORTH); 6TH STREET (WILLIAMS AVE. WEST TO DUFF DRIVE EAST); 42ND STREET (9TH AVENUE WEST TO WENTWORTH AVENUE EAST); 3RD AVENUE (32ND STREET SOUTH TO 36TH STREET); AND 64TH STREET (GARNETT AVENUE WEST TO W. PORT ARTHUR ROAD EAST) DECREASING THE CONTRACT AMOUNT BY $131,624.17 TO A NEW CONTRACT AMOUNT OF $424,311.33. CAPITAL PROJECTS- STREETS ACCOUNT NO. 307-1601-591.86-00. WHEREAS, pursuant to Resolution No. 18-532, the City of Port Arthur City Council awarded a contract for the Reclamation and Road Resurfacing Project for Marshall Avenue (10th Street South to Gulfway Drive North); 6th Street (Williams Avenue West to Duff Drive East); 42nd Street (9th Avenue West to Wentworth Avenue East); 3rd Avenue (32nd Street South to 36th Street); and 64th Street (Garnett Avenue to West Port Arthur Road East) to LD Construction, of Beaumont, Texas; and, WHEREAS, during construction, LD Construction of Beaumont, Texas adjusted bid quantities to reflect a decrease in reclamation, concrete and asphalt on Marshall Avenue (10th Street South to Gulfway Drive North); 6th Street (Williams Avenue West to Duff Drive East); 42nd Street (9th Avenue West to Wentworth Avenue East); 3rd Avenue (32nd Street South to 36th Street); and 64th Street (Garnett Avenue to West Port Arthur Road East); and, PR No. 20915 07/22/2019 mje Page 2 of 3 WHEREAS, proposed Change Order No. 1 submitted for the removal of said bid items, decreasing the original contract amount of $570,883.50 by $131,624.17 to the new contract amount of $424,311.33, attached hereto as Exhibit A; and, WHEREAS, approval of Change Order No. 1 herein deemed an appropriate action; now, therefore, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PORT ARTHUR: THAT, the facts and opinions in the preamble are true and correct; and, THAT, Change Order No. 1 is herein approved and the City Manager is authorized to execute said Change Order No. 1 (attached as Exhibit A) to the contract between the City of Port Arthur and LD Construction of Beaumont, Texas; and THAT, Change Order No. 1 will decrease the contract amount by $131,624.17 to a new contract amount of $424,311.33 and, THAT, a copy of the caption of this Resolution No. be spread upon the Minutes of the City Council. READ, ADOPTED AND APPROVED this the day of , A.D. 2019 at a meeting of the City of Port Arthur, Texas by the following vote: Ayes: Mayor: Councilmembers: Noes: PR No. 20915 07/22/2019 mje Page 3 of 3 Thurman Bill Bartle Mayor Attest: City Secretary Sherri Bellard APPROVED AS TO FORM: APPROVED FOR ADMINISTRATION: / / — OAbACge � Va zen Rebecca Underhill Cityne Interim City Manager APPROVED AS FOR AVAILABILITY OF FUNDS: kc, ) ci) Kandy Daniel 8 Director of Finance Alberto Elefano, P.E. Director of Public Works li / Clifton Williams, CPPB Purchasing Manager EXHIBIT A CITY OF PORT ARTHUR Public Works Engineering DATE: JUNE 20,2019 PROJECT: RECLAMATION AND ROADWAY PROJECTS OWNER: CITY OF PORT ARTHUR CONTRACTOR: LD CONSTRUCTION CHANGE ORDER NO.:01(FINAL) THE FOLLOWING CHANGES IN THE PLANS AND/OR SPECIFICATIONS ARE HEREBY MADE: Add/Delete Construction Items and/or quantities to the Contract: Item ItemOriginal Original Final Final No. Code Description Unit Unit Price Unit Price Quantity , Amount Quantity Amount 1 MARSHALL AVENUE(10TH ST.-GULFWAY DR.) 500 6001 MOBILIZATION LS 1 5 12,000.00 S 12,000.00 1 S 12,000.00 S 12,000.00 251 003 RECLAMATION,4"-5' SY 8624 S 4.00 $ 34,496.00 5566 S 4.00 S 22,264.00 112 6001 ROAD GRADER WORK(ORD COMP) LF 2606 5 3.00 S 7,818.00 2277 $ 3.00 S 6,831.00 310 6001 PRIME COAT(MULTI OPTION) GAL 1725 S 6.00 5 10,350.00 450 S 6.00 S 2,700.00 341 6042 2 INCH HOT MIX ASPHALT CONCRETE(TYPED) SY 8624 S 10,50 $ 90,552.00 5188 S 10.50 S 54,474.00 465 001 MANHOLE COVER ADJUSTMENT EA 0 S - $ - 0 $ - $ - 465 002 WATER VALVE COVER ADJUSTMENT EA 0 S - S - 0 5 - S - 506 001 INLET PROTECTION(BMPS) EA 19 $ 100.00 S 1,900.00 16 5 100.00 S 1,600.00 502 6001 BARRICADES,SIGNS AND TRAFFIC HANDLING EA 1 $ 2,500,00 S 2,500.00_ 1 S 2,500.00 S 2,500.00 ORIGINAL CONTRACT AMOUNT $ 159,616.00 FINAL CONTRACT AMOUNT S 102,369.00 2 6TH STREET(WILLIAMS AVE..DUFF DR.) 500 6001 MOBILIZATION LS 1 S 4,000.00 S 4,000.00 1 $ 4,000.00 $ 4,000.00 251 003 RECLAMATION,4'-5' SY 2271 S 5.00 S 11,355.00 $13333 S 5.00 S 25,666.65 112 6001 ROAD GRADER WORK(ORD COMP) LF 730 S 4.00 S 2,920.00 2190 S 4.00 S 8,760.00 310 6001 PRIME COAT(MULTI OPTION) GAL 455 S 7.00 S 3,185.00 250 S 7.00 S 1,750.00 341 6042 2 INCH HOT MIX ASPHALT CONCRETE(TYPED) SY 2271 S 12.00 S 27,252.00 1711 S 12.00 S 20,532.00 465 001 MANHOLE COVER ADJUSTMENT EA 0 5 - S - 0 S - S - 465 002 WATER VALVE COVER ADJUSTMENT LA 0 5 - 5 - 0 S - 5 - 506 001 INLET PROTECTION(BMPS) FA 4 $ 100.00 S 400.00 2 S 100.00 $ 200.00 502 6001 BARRICADES,SIGNS AND TRAFFIC HANDLING EA I S 2,500.00 S 2,500.00 1 S 2,500.00 5 2,500.00 ORIGINAL CONTRACT AMOUNT $ 51,612.00 FINAL CONTRACT AMOUNT S 63,408.65 3 42ND STREET(9TH AVE.-WENTWORTH AVE) 500 6001 MOBILIZATION LS 1 S 5,000.00 S 5,000.00 I S 5,000.00 S 5,000.00 251 003 RECLAMATION,4"-5" SY 2975 $ 5.00 S 14,875.00 1840.67 $ 5.00 S 9,203.35 112 6001 ROAD GRADER WORK(ORD COMP) LF 930 S 4.00 S 3,720.00 753 $ 4.00 S 3,012.00 t 310 6001 PRIME COAT(MULTI OPTION) GAL 595 $ 7.00 $ 4,165.00 350 5 7.00 S 2,450.00 341 6042 2 INCH HOT MIX ASPHALT CONCRETE(TYPE D) SY 2975 S 12.00 S 35,700.00 2309.97 S 12.00 S 27,719.64 465 001 MANHOLE COVER ADJUSTMENT EA 2 S 150.00 S 300.00 2 $ 150.00 S 300.00 465 002 WATER VALVE COVER ADJUSTMENT EA 0 $ - S - 0 $ - S - 506 001 INLET PROTECTION(BMPS) EA 3 S 100.00 5 300.00 5 $ 100.00 $ 500.00 502 6001 BARRICADES,SIGNS AND TRAFFIC HANDLING EA I S 2,500.00 S 2,500.00 1 $ 2,500.00 S 2,500.00 /ORIGINAL CONTRACT AMOUNT S 51,612.00 FINAL CONTRACT AMOUNT S 50,684.99 4 3RD AVENUE(32ND ST.-36TH ST.) 500 6001 MOBILIZATION LS I 5 7,000.00 S 7,000.00 I 5 7,000.00 5 7,000.00 251 003 RECLAMATION,4"-5' SY 4305 $ 5.00 $ 21,525.00 3087.33 $ 5.00 5 15,436.65 112 6001 ROAD GRADER WORK(ORD COMP) LF 1289 $ 4.00 $ 5,156.00 1263 S 4.00 $ 5,052.00 310 6001 PRIME COAT(MULTI OPTION) GAL 861 5 7.00 S 6,027.00 350 S 7.00 5 2,450.00 341 6042 2 INCH HOT MIX ASPHALT CONCRETE(TYPE D) SY 4305 $ 12.00 $ 51,660.00 2881.08 S 12.00 S 34 572.96 465 001 MANHOLE COVER ADJUSTMENT EA 2 S 150.00 S 300.00 2 $ 150.00 5 300.00 465 002 WATER VALVE COVER ADJUSTMENT EA 0 S - 5 - 0 $ - S 506 001 INLET PROTECTION(BMPS) EA 3 $ 100.00 S 300.00 2 5 100.00 S 200.00 502 6001 BARRICADES,SIGNS AND TRAFFIC HANDLING EA 1 S 2,500.00 5 2,500.00 1 S 2,500.00 $ 2,500.00ORIGINAL CONTRACT AMOUNT S 94,468.00 FINAL CONTRACT AMOUNT S 67,511.61 5 64TH STREET(GARNETT AVE.-WEST PORT ARTHUR RD.) 500 6001 MOBILIZATION LS I S 15,000.00 $ 15,000.00 1 S 15,000.00 S 15,000.00 251 003 RECLAMATION,4'-5" SY 10971 S 4.00 5 43,884.00 7557.77 5 4.00 S 30,231.08 112 6001 ROAD GRADER WORK(ORD COMP) LF 3401 S 3.00 S 10,203.00 3401 S 3.00 $ 10,203.00 310 6001 PRIME COAT(MULTI OPTION) GAL 2195 5 6.00 5 13,170.00 1100 S 6.00 S 6,600.00 341 6042 2 INCH HOT MIX ASPHALT CONCRETE(TYPED) SY 10971 5 10.50 S 115,195.50 7436 $ 10.50 $ 78,078,00 465 001 MANHOLE COVER ADJUSTMENT EA I S 150.00 S 150.00 0 S 150.00 $ 465 002 WATER VALVE COVER ADJUSTMENT EA 4 $ 150.00 $ 600.00 0 $ 150.00 S - 506 001 INLET PROTECTION(BMPS) EA 4 $ 100.00 $ 400.00 2 S 100.00 S 200.00 502 6001 BARRICADES,SIGNS AND TRAFFIC HANDLING EA I S 25.00 $ 25.00 1 $ 25.00 S 25.00 ORIGINAL CONTRACT AMOUNT S 198,627.50 FINAL CONTRACT AMOUNT S 140,337.08 ORIGINAL TOTAL AMOUNT I 5 555,935,50 1 FINAL TOTAL AMOUNT I S 424,311.33 I AMOUNT OF CHANGE ORDER DEDUCTED: $ (131,624.17) ORIGINAL CONTRACT AMOUNT: 5 555,935.50 NET FROM PREVIOUS CHANCE ORDERS: S 555,935.50 TOTAL AMOUNT OF THIS CHANGE ORDER: S (131,624.17) PERCENT OF THIS CHANGE ORDER: -23.68 TOTAL PERCENT CHANGE ORDER TO DATE: -23.68 FINAL TOTAL AMOUNT: S 424,311.33 NO CALENDAR DAYS HAVE BEEN ADDED IN THE CONTRACT BVl'HIS FINAL CHANGE ORD 1 ACCEPTED BY: PREPARED BY: VlldrifOg4 �( Keith/ Gunn,LD Construction ' 'arael Miranda,P ject Man: APPROVED BY:Az(/' ) ' APPROVED BY: (((JJJIIIIDeWayynneJDavi{,,P.E. "Ass✓t✓✓✓ City Engineer Clifton Williams,CPPB,Purchasing Manager Alberto Elereno,P.E.,Public Works Director