HomeMy WebLinkAboutPR 20913: LAKESHORE DRIVE ROADWAY PAVEMENT REPLACEMENT PROJECT PHASE I FROM 4186 TO 4300 LAKESHORE DRIVE city of , www.PortArthurTx.gov Date: August 20, 2019 To: Mayor and City Council Through: Ron Burton, Interim City Manager From: Alberto Elefano, PE—Director of Public Works RE: Lakeshore Drive Roadway Pavement Replacement Project Phase I from 4186 to 4300 Lakeshore Drive; Project No. EDC002 Repayment of Amount Due. Introduction: The intent of this Agenda Item is for City Council to authorize the City Manager to accept the Engineer's Certificate of Completion,the Contractor's Affidavit of Payment of Debts and Claims, Contractor's Certificate and Release, Engineer's Certificate of Substantial Completion and Substantial Completion of Inspection Punchlist, and the Contractor's Certificate of Guarantee and notification of repayment of amount of$1,122.70 due to the City for the Lakeshore Drive Roadway Pavement Replacement Project Phase I from 4186 to 4300 Lakeshore Drive; Project No. EDC002. Background: Excavation& Construction, LLC or Port Arthur, Texas was awarded the Lakeshore Drive Roadway Pavement Replacement Project Phase I at the cost of $560,000. The project being funded through the Port Arthur Economic Development Corporation (EDC) Street Maintenance and Repair Account. Change Order No. 1, (Resolution No. 19-349), has been submitted by Excavation & Construction, LLC of Port Arthur, Texas and approved by the City Council adjusting bid quantities which decreases the contract amount by $27,646.58 to the new contract amount of$528,195.66. Additionally, there was an overpayment in the amount of$1,122.70 that is due from Excavation& Construction, LLC of Port Arthur, Texas. Budget Impact: Funds are available in EDC Street Maintenance and Repair Account 307-1601-591.86-01. Recommendation: It is recommended that the City of Port Arthur City Council authorizes approval of PR 20912 that accepts the Engineer's Certificate of Completion, Contractor's Affidavit of Payment of Debts and Claims, Contractor's Certificate of Release, Contractor's Certificate of Guarantee executed by Excavation & Construction, LLC of Port Arthur, Texas, approves the City of Port Arthur's Certificate of Acceptance and notifies Excavation & Construction,LLC of Port Arthur,Texas of the amount due the City of Port Arthur in the amount of$1,122.70. The Certificate of Acceptance will not be executed until Excavation& Construction, LLC reimburses the City of Port Arthur for the overpayment in the amount of$1,122.70. "Remember,we are here to serve the Citizens of Port Arthur" P.O.Box 1089 X Port Arthur,Texas 77641-1089 X 409.983.8101 X FAX 409.982.6743 PR No. 20913 08120/12019 mje Page 1 of 4 RESOLUTION NO. A RESOLUTION AUTHORIZING ACCEPTANCE OF THE ENGINEER'S CERTIFICATE OF COMPLETION, CONTRACTOR'S AFFIDAVIT OF PAYMENTS OF DEBTS AND CLAIMS, CONTRACTOR'S CERTIFICATE AND RELEASE, CONTRACTOR'S CERTIFICATE OF GUARANTEE FOR THE LAKESHORE DRIVE ROADWAY PAVEMENT PROJECT PHASE I FROM 4186 TO 4300 LAKESHORE DRIVE; AUTHORIZING THE CITY MANAGER TO SIGN THE CERTIFICATE OF ACCEPTANCE ON BEHALF OF THE CITY OF PORT ARTHUR, TEXAS; AND NOTIFICATION OF PAYMENT DUE FROM EXCAVATION & CONSTRUCTION, LLC OF PORT ARTHUR, TEXAS, IN THE AMOUNT OF $1,122.70. WHEREAS, the City of Port Arthur is allocated a percentage of funds from the Economic Development Corporation (EDC) for street maintenance and repair; and, WHEREAS, Lakeshore Drive qualified for funding under the EDC's guidelines; and, WHEREAS, pursuant to Resolution No. 18-171, the City of Port Arthur's City Council awarded the contract to Excavation & Construction, LLC of Port Arthur, Texas with a projected budgetary impact of $560,000.00 and a term of 74 calendar days; and, WHEREAS, pursuant to Resolution No. 19-349, the City Council approved Change Order No. 1 adjusting the bid quantities and decreasing the original contract amount from $560,000.00 to the new contract amount of $528,195.66; and, WHEREAS, Excavation & Construction of Port Arthur, Texas has completed the contracted project to the satisfaction of the project engineer and the City staff; and, WHEREAS, the City has received the Contractor's Certificate of Completion dated February 20, 2019 stating that the work to which the Certificate applies has been inspected, authorized, and declared to be complete in accordance with the contract PR No. 20913 08/20/2019 mje Page 2 of 4 documents and made a part hereof as Exhibit A; together with a Contractor's Affidavit of Payment of Debts and Claims, Exhibit B; Contractor's Certificate and Release, Exhibit C; Engineer's Certificate of Substantial Completion and Substantial Completion of Inspection Punchlist, Exhibit D; and the Contractor's Certificate of Guarantee, Exhibit E; executed by Excavation & Construction, LLC of Port Arthur, Texas and the Contractor's Certificate of Warranty, Exhibit F; and, WHEREAS, it was determined that the City of Port Arthur overpaid Excavation & Construction of Port Arthur, Texas the amount of $1,122.70 (See Exhibit G); and, WHEREAS, the City of Port Arthur has submitted an invoice to Excavation & Construction of Port Arthur, Texas for the amount due of $1,122.70 (See Exhibit H); now therefore, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PORT ARTHUR: THAT, the facts and opinions in the preamble are true and correct; and, THAT, the City of Port Arthur has submitted an invoice to Excavation & Construction, LLC of Port Arthur, Texas for the amount overpaid amount due of $1,122.70; and, THAT, upon the receipt of the payment from Excavation & Constructions, LLC to the City of Port Arthur in the amount of $1,122.70, the City Manager of the City of Port Arthur will be authorized to execute on behalf of the City of Port Arthur a Certificate of Acceptance, Exhibit I, for the completion of the Lakeshore Drive Roadway Pavement Replacement Project Phase I; and, PR No. 20913 08/20//2019 mje Page 3 of 4 THAT, a copy of the caption of this Resolution be spread upon the Minutes of the City Council. READ, ADOPTED AND APPROVED this the day of , A.D. 2019 at a meeting of the City of Port Arthur, Texas by the following vote: Ayes: Mayor: Councilmembers: Noes: Thurman "Bill" Bartie Mayor Attest: Sherri Bellard City Secretary APPROVED AS TO FORM: APPROVED FOR ADMINISTRATION: A 16 e ( c Vale If-no Ron Burton City -tto ey Interim City Manager PR No. 20913 08/20/2019 mje Page 4 of 4 APPROVED AS FOR AVAILABILITY OF FUNDS: Kandy Daniel Interim Director of Finance Alberto Elefano, P.E. Director of Public Works uIi Liktia.Clifton llCPPB Purchasing Manager EXHIBIT A PO Box 888 Phone:409-962-2677 Bridge City TX 77611 FAX:409-962-2771 EKC AVAlir■ D N CONST RUCT■ DN Contractors Certificate of Completion PROJECT: Lakeshore Drive Phase 1 LOCATION: Lakeshore Drive OWNER: City of Port Arthur Contractor certifies that the Work to which this Certificate applies has been inspected by authorized representatives of Owner and Contractor and that the Work is hereby declared to be complete in accordance with the Contract Documents as of February 29,2019. Signaturee Pitta Print R.:chez I14 rd Title D eAs: e 3S l''IAn e e r Date 6/4.2Y A2o/ 9 ELIZABETH LEMOINE •`;1�j'_� Notary Public.Stole of lexas My Commission E xpaes +;;,,;�,,,;•• September 24. 2019 EXHIBIT B PO Box 888 Phone:409-962-2677 Bridge City TX 77611 FAX:409-962-2771 EXC AV AT■ C: N CONSir IF* U =mini DINN Contractor's Affidavit of Payment of Debts and Claims PROJECT: is/ticJherrr Pr!ve- i eQd Repo;r.S LOCATION: La$iesAotC Ar•:vc , Por Y- ,4r )Il+ or i e%4s OWNER: e,`¢J. 0-1) Port 4-rt ut' State of Texas County of Jefferson The undersigned hereby certifies that,except as listed below, payment has been made in full and all obligations have otherwise been satisfied for all materials and equipment furnished,for all work, labor,and services performed,and for all known indebtedness and claims against the Contractor for damages arising in any manner in connection with the performance of the Contract referenced above for which the Owner or Owner's property might in any way be held responsible or encumbered. EXCEPTIONS: Signature ('-e- IQ i/3-Z Print /gcAeze horr,n9 'on Date 2 427/, 9 ELIZABETH LEMOINE ;SAA Notary PubIrc,StoTe or texas •y . My Commission Exp'piles September 24, 2019 Sworn to and subscribed before me, a Notary public,this() '1 day of R-1011-14o 1, of 019 Notarp_ublic My commission expires: `�y EXHIBIT C CONTRACTOR'S CERTIFICATE AND RELEASE FROM: EXCAVATION AND CONSTRUCTION, LLC (Name of Contractor) TO: CITY OF PORT ARTHUR (Owner) FOR THE CONTRACT ENTERED INTO THE 09 DAY OF JULY 20 18 BETWEEN THE CITY OF PORT ARTHUR (Owner) AND EXCAVATION AND CONS I RUCTION, LLC (Name of Contractor) OF 6601 PROCTOR STREET EXTENSION, PORT ARTHUR, TEXAS (City and State) FOR THE: LAKESHORE DRIVE ROADWAY PAVEMENT REPLACEMENT PHASE I KNOW ALL MEN BY THESE PRESENTS: 1. The undersigned hereby certifies that there is due from, and payable by, the Owner to the Contractor under the contract and duly approved change orders and modifications the balance of: Forty-eight thousand Thirty-eight Dollars &Sixty-five Cents($48,032.65) 2. The undersigned further certifies that, in addition to the amount set forth in Paragraph 1, there are outstanding and unsettled the following items which he claims are just and due and owing by the Owner to the Contractor: NONE 3. The undersigned further certifies that all work required under this contract, including all Change Orders, has been performed in accordance with the terms thereof, and that there are no unpaid claims for materials, supplies, or equipment and no claims of laborers or mechanics for unpaid wages arising out of the performance of this contract, and that the wage rates paid by the Contractor were in conformity with the contract provisions relating to said wage rates. 4. Except for the amounts stated under Paragraphs 1 and 2 hereof, the undersigned has received from the Owner all sums of money payable to the undersigned under, or pursuant to, the above mentioned contract or any modification or change thereof. 5. That, in consideration of the payment of the amount stated in Paragraph 1 here of, the undersigned does hereby release the Owner and Operator from any and all claims arising under, or by virtue of this contract, except the amount listed in Paragraph 2 hereof due from the Owner; provided, however, that if for any reason, the Owner does not pay in full the amount stated in Paragraph 1 hereof, said deduction shall not affect the validity of this release, but the amount so deducted shall be automatically included under Paragraph 2 as an amount which the Contractor has not released, but will release upon payment thereof. The Contractor further certifies that, upon the payment of the amount listed in Paragraph 2 hereof, and of any amount which may be deducted from Paragraph 1 hereof, he will release the Owner and Operator from any and all claims of any nature whatsoever arising out of said contract or modification thereof, and will execute sucn further releases or assurances as the Owner and Operator may request. 1 of 2 IN WITNESS WHEREOF, the undersigned has signed and sealed this instrument this cab 'Lk day of J Sn e , 20 19 . EXCAVATION AND CONSTRUCTION (Contractor) BY: (Ricky Harrington) , being first duly sworn on oath, deposes and says, first, 91,5:n e-b that he is the /lei n a,9 e-r of Excavation and Construction, LLC (Tide) (Name of Contractor) ev,i'ie 55 Second, that he has read the foregoing certificate by him subscribed as /712,-,q, e r of Excavation and Construction, LLC i8e (Name of Contractor) Affiant further states that the matters and things stated herein are true. L 't4,110 /d2 (Ricky Harrington) Subscribed and sworn to before me this Q.Le day of J U n , 20 19 . My commission expires CI- a Li' aOl R (Date) 8,- mi 411 �ubli (Notary c) Seal: EU2ABEIH tEMOINE I ` ��` Notary Pubilc,Store 01 Texos My commission Expnt's Septembe' 24. 2019 2 of 2 EXHIBIT D rr r:Itr www.PortArthurTx.gov CERTIFICATE OF COMPLETION Date: June 24, 2019 Project: Lakeshore Drive Roadway Pavement Replacement Project Phase I from 4186 to 4300 Lakeshore Drive. Project—Close Out; Project No. EDC002 To: All Concerned Gentlemen: I HEREBY CERTIFY THAT this project was completed on February 29, 2019 and that the work was under periodic inspection during construction by Public Works Engineering, City Inspector. That to the best of my knowledge, the project was constructed substantially in accordance with the plans and specifications, and that record documents were received and are on file in the City of Port Arthur Public Works Engineering Division. Submitted by: Alberto Elefano, P.E. Public Works Director "Remember,we are here to serve the Citizens of Port Arthur" P.O.Box 1089 X Port Arthur,Texas 77641-1089 X 409.983.8101 X FAX 409.982.6743 EXHIBIT E CONTRACTOR'S CERTIFICATE OF GUARANTEE FROM: EXCAVATION AND CONSTRUCTION, LLC (Name of Contractor) TO: CITY OF PORT ARTHUR (Owner) FOR THE CONTRACT ENTERED INTO THE 09 DAY OF JULY, 20 18, BETWEEN THE CITY OF PORT ARTHUR (Owner) AND EXCAVATION AND CONSTRUCTION, LLC (Name of Contractor) OF 6601 PROCTOR STREET EXTENSION, PORT ARTHUR, TEXAS (City and State) FOR THE: LAKESHORE DRIVE ROADWAY PAVEMENT REPLACEMENT PHASE I LOCATED IN THE CITY OF PORT ARTHUR, TEXAS KNOW ALL MEN BY THESE PRESENTS: 1. The undersigned does hereby guarantee all of the work done under the above referenced contract to be free from improper workmanship and free from faulty materials, and that all work was performed in accordance to the guidance and instructions received from the City of Port Arthur according to the terms of the aforesaid contract. 2. This guarantee shall cover a period of one (1) year from the date of acceptance of all work under this Contract, as evidenced by the action taken by the City Council of the City of Port Arthur accepting this work. 3. This Certificate is given in connection of the final payment under the contract between the Owner and EXCAVATION AND CONSTRUCTION, LLC and with the knowledge that it will be relied upon in making such payment and that such payment would not be made except upon the truth of the matter concerned in this affidavit. IN WITNESS WHEREOF, the undersigned has signed and sealed this instrument this a Cf day of Julf, f, , 20 19 . EXCAVATION AND CONSTRUC110N, LLC (Contractor) BY4111.1 (Eric Gilchriest) 1 of 2 I C G t 1C-hrit%i , being first duly sworn on oath, deposes and says, first, that he is the Manan eY of EXCAVATION AND CONSTRUCTION, LLC (Title) (Name of Contractor) Second, that he has read the foregoing certificate by him subscribed as ',-11lan0( Q�' (Title) of EXCAVATION AND CONSTRUCTION, LLC (Name of Contractor) Affiant further states that the matters and thin stated herein are true. (Eric Gilchriest) Subscribed and sworn to before me this c.�u day of n Pi 1 , 20 19 , My commission expires (Date) \Q..0(Notary ,'c) Seal: 1/Illy ;: j ELIZABETH LEMOINE ✓+°_.�l�,'q? Notary Public,Stole of Texas My Commission Expires ;;;.•• ° September 24, 20)9 2 of 2 EXHIBIT F PO Box 888 Phone:409-962-2677 Bridge City TX 7761111FAX:409-962-2771 1111 EXC A11=111-11-1 O N COI4I ILI I=ir 101 Contractors Certificate of Warranty PROJECT: Lo Masitore- Ong rc f!"DQ d R efleL PS LOCATION: LcrKSt,,Sprve. Perp 4,1-Aur Te44S OWNER: C,(iy CV f' I) rt 4ryr Excavation &Construction, LLC,does hereby warrant that all labor and materials furnished and work performed are in accordance with the contract documents and authorized modifications thereto and will be free from defects due to defective materials and workmanship for a period of one year from Date of Final Completion. This warranty commences on 3)/ f/ ? and expires on 3J/Jac Should any defect develop during the warranty period due to improper materials or workmanship,the defect shall be corrected at no expense to the Owner. If,for any reason, Excavation &Construction, LLC fails to repair the defect,the Owner may,at his option,correct defects and charge Excavation &Construction, LLC for such correction. Nothing in the above shall be deemed to apply to work which has been abused or neglected. Signature 64`'rte/ /" Ce--- - Print /Q:c-A s.r d r, n G f on Title fu5toe35 /t?On 4sc�' Date a2/6,27/1 9 EXHIBIT G Exacavation &Construction Proj#EDC002 Lakeshore Phase 1 Pymt# Pymt Date CK# Amt Expensed Retainage Ck Amount Total contract amount 528,195.63 Pymt#1 8/2/2018 364566 117,640.97 5,882.05 111,758.92 Pymt#2 9/5/2018 365543 82,192.28 4,109.61 78,082.67 Pymt#3 10/3/2018 366290 87,894.90 4,394.74 83,500.16 Pymt#4 11/8/2018 368173 51,742.44 2,587.12 49,155.32 Pymt#4 1/9/2019 369413 217,706.59 10,885.33 206,821.26 Amount Invoiced and Paid 557,177.18 27,858.85 529,318.33 529,318.33 (1,122.70) Refund Due Less duplicate payment 51,742.44 2,587.12 49,155.32 505,434.74 25,271.73 480,163.01 Final Invoice 22,760.89 1,138.04 21,622.85 Total per contract 528,195.63 26,409.77 501,785.86 Final Invoice due 22,760.89 1,138.04 21,622.85 duplicate payment (51,742.44) (2,587.12) (49,155.32) Overpaid (28,981.55) (1,449.08) (27,532.47) Retainage Due Excavation 26,409.77 Net Refund due to the City (1,122.70) EXHIBIT H INVOICE #ENG-100 CITY OF PORT ARTHUR PUBLIC WORKS DEPARTMENT - ENGINEERING 444 4TH STREET PORT ARTHUR, TX 77640 DATE AUGUST 20, 2019 BILL TO FOR EXCAVATION & CONSTRUCTION LLC LAKESHORE DRIVE PROJECT 6601 PROCTOR ST. PHASE I PORT ARTHUR, TX 77640 PHONE 409 962 2677 Details AMOUNT Overpayment on Project $1,122.70 TOTAL $1,122.70 Make all checks payable to CITY OF PORT ARTHUR If you have any questions concerning this invoice, please contact: Alberto Elefano; Director of Public Works 409 9838189 THANK YOU EXHIBIT I CITY OF PORT ARTHUR, TEXAS DEPARTMENT OF PUBLIC WORKS CERTIFICATE OF ACCEPTANCE FOR... LAKESHORE DRIVE ROADWAY PAVEMENT REPLACEMENT PROJECT PHASE I FROM 4186 TO 4300 LAKESHORE DRIVE. To: Excavation & Construction, LLC of Port Arthur, Texas This document is to certify that the City of Port Arthur, Texas accepts the completion of the Lakeshore Drive Roadway Pavement Replacement Project Phase I on the basis of the recommendation of the City of Port Arthur's Public Works' Engineering Department and receipt of the Engineer's Certificate of Completion, Contractor's Affidavit of Payment of Debts and Claims, Contractor's Certificate of Release, Contractor's Certificate of Guarantee executed by Excavation&Construction, LLC of Port Arthur, Texas. Ronald Burton Interim City Manager Sherri Bellard City Secretary