City of Port Arthur, Texas
Robert A. "Bob"Bowers Civic Center
To: The Honorable Mayor and City Council
Through: Ronald Burton, Interim City Manager
From: Adam J Saunders,Civic Center Director
Date: October 21, 2019
RE: Proposed Resolution No. 21024
NATURE OF THE REQUEST:
As a result of Hurricane Harvey, the Civic Center parking lot, which includes the Library, has no
parking lot lights in operation. Temporary lights are currently in use. Pursuant to Resolution
No. 19-338, the City Council approved entering into a contract with Gulf Coast Electric Co., Inc.
of Beaumont, Texas for repair of the Civic Center and Library parking lot lights in the amount of
$63,120.00 and a contingency amount for unforeseen damage in the not to exceed amount of
$337,500.00. Per Resolution No. 19-338, the contingency amount shall not be expended without
written recommendation from the Engineer, City Manager, and prior approval of the City
Council. Amendment No. 1 in the amount of $243,120.00 is for various needed unforeseen
repairs to the parking lot lights that were discovered while repairing the parking lot lights, and an
additional thirty (30) days to complete said repairs. The City Manager also approves the
expenditure of the additional funds.
All work will be submitted for reimbursement from FEMA. For this reason, the City of Port
Arthur must follow a specific procurement process and procedure. In accordance with this
process and procedure, Gulf Coast Electric Co., Inc. has determined what items and units are not
repairable and need replacement and have submitted the documentation for amending the
contract. These items, in consultation with Epic Engineering, have been confirmed to need
replacement.
It is requested that the City Council authorize the City Manager to execute Amendment No. 1
submitted by Gulf Coast Electric Co., Inc. for various unforeseen repairs to the parking lot lights
in the amount of$243,120.00 to be paid out of the contingency funds, and an additional thirty
(30) days to complete said repairs.
ANALYSIS/CONSIDERATION:
The parking lot lights at the Civic Center, which includes the Library, need repair. Amendment
No. 1 contains the unforeseen list of items and units that need to be replaced in order to have all
parking lot lights operational.
BUDGETARY AND FISCAL EFFECT
This will be paid through the Hurricane Harvey account and reimbursement will be requested
through FEMA. Funds available in Hurricane Account 147-2300-901-51-00 Project 082617.
PR21024
RECOMMENDATION
A resolution authorizing the City Manager to execute Amendment No. 1 to the contract between
the City of Port Arthur and Gulf Coast Electric Co., Inc. of Beaumont, Texas for unforeseen
repairs found while repairing the Civic Center and Library parking lot lights in the amount of
$243,120.00 to be paid out of the contingency from Hurricane Account No. 147-2300-901-51-
00, Project 082617, and an additional thirty (30) days to complete said repairs.
STAFFING EFFECT
None
PR21024
P.R. No. 21024
10/18/19 AJS/gt
RESOLUTION NO.
A RESOLUTION AUTHORIZING THE CITY MANAGER TO EXECUTE
AMENDMENT NO. 1 TO THE CONTRACT BETWEEN THE CITY OF
PORT ARTHUR AND GULF COAST ELECTRIC CO., INC. OF
BEAUMONT, TEXAS FOR REPAIR OF THE CIVIC CENTER AND
LIBRARY PARKING LOT LIGHTS INCREASING THE CONTRACT
AMOUNT BY $243,120.00 AND AUTHORIZING THE EXPENDITURE
TO BE PAID OUT OF THE CONTINGENCY FUNDS PROVIDED IN THE
CONTRACT; FUNDS ARE AVAILABLE IN HURRICANE ACCOUNT
147-2300-901-51-00, PROJECT 082617.
WHEREAS, pursuant to Resolution No. 19-338, the City Council authorized the
execution of a contract with the Gulf Coast Electric Co., Inc. of Beaumont, Texas to repair of the
parking lot lights at the Civic Center and Library in the not to exceed amount of$400,620.00,
which included the bid amount of $63,120.00 and a contingency of $337,500.00 to cover
unforeseen damages that may be beneath the surface of the parking lot; and,
WHEREAS, Amendment No. 1 in the amount of $243,120.00 is requested for various
needed unforeseen repairs of the parking lot lights and an additional thirty (30) days is requested
to complete said repairs as listed in Exhibit"A"; and,
WHEREAS, pursuant to Resolution No. 19-338, the contingency amount shall not be
expended without written recommendation from the Engineer, City Manager and prior approval
of the City Council; and,
WHEREAS, Epic Engineering, LLC has submitted its recommendation for approval of
the unforeseen repairs attached hereto as Exhibit"B".
WHEREAS, the City Manager also recommends approval of the expenditure of the
contingency funds for the repair of the unforeseen damages to the Civic Center and Library
parking lot lights attached hereto as Exhibit"C".
s.pr21024
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE
CITY OF PORT ARTHUR:
THAT,the facts and opinions in the preamble are true and correct.
THAT, the City Council hereby accepts the written recommendation from Epic
Engineering, LLC attached hereto as Exhibit"B".
THAT, the City Council hereby authorizes the City Manager to execute Amendment No.
1 submitted by Gulf Coast Electric Co., Inc. of Beaumont, Texas, for repair of the parking lot
lights at the Civic Center and Library in the amount of $243,120.00 to be paid out of the
contingency and an additional thirty (30) days to complete said repairs, in substantially the same
form as attached hereto as Exhibit"A".
THAT, funding is available from Hurricane Account 147-2300-901-51-00, Project
082617.
THAT a copy of the caption of this Resolution be spread upon the Minutes of the City
Council.
READ, ADOPTED, AND APPROVED, this day of November, 2019, the
following Vote: AYES:
Mayor:
Councilmembers:
NOES:
Thurman "Bill" Bartie, Mayor
s.pr21024
ATTEST:
Sherri Bellard, City Secretary
APPROVED AS TO FORM:
ii l +
V i' iz; o, City Attorney
APPROVED FOR ADMINISTRATION:
Ronald Burton, Interim City Manager
APPROVED AS TO FUND AVAILABILITY:
KcA
Kandy Daniel, Interim Director of Finance Clifton Williams, CPPB
Purchasing Manager
s.pr21024
EXHIBIT "A"
s.pr21024
AMENDMENT NO. 1
DATE: 10/30/19
ORIGINAL AGREEMENT DATE: 09/03/19
GULF COAST ELECTRIC
PROJECT DESCRIPTION: Repair of Parking Lot lights at Civic Center and Library
ORIGINAL CONTRACT TERM: 30 days
NEW CONTRACT TERM including the AMENDMENT will be: 30 additional days
CHANGE TO CONTRACT AMOUNT: $243,120.00 (see attached additional repairs listed)
ORIGINAL CONTRACT AMOUNT: $63,120.00
CONTRACT AMOUNT due to this AMENDMENT will be: $306,240.00
Executed this day of November, 2019.
GULF COAST ELECTRIC
By:
Print Name:
Title:
Executed this day of November, 2019.
CITY OF PORT ARTHUR
By:
Ronald Burton
Interim City Manager
Residential
1''`4,
uf Coast Commercial
Industrial
Veal* COTte
a 'TEC'L 18185
2005 Pecos @.Fourthz • Beaumont, Texas 77701
September 30,2019
City of Port Arthur
P.O.Box 1089
Port Arthur,TX 77641-1089
Attn: Mr. Clifton Harrison
Re: City of Port Arthur- Parking Lot Lighting at Bob Bowers Civic Center and Port Arthur Public Library
Dear Mr. Harrison:
As per your request, we are submitting additional work required to repair damaged wire and conduit to complete the
project as per the bid documents at the above-referenced location.
Per the bid sheet,the price is as follows:
Bid Item#5 total: $56,160.00
Bid Item#6 total: $56,160.00
Bid Item#7 total: $79,200.00
Cutting and patching of concrete(estimate of 1200' between 6 poles) $33,600.00
Adder for LED Fixtures: $18,000.00
The price is based on regular working hours of Monday through Friday from 7:00 AM to 3:30 PM. If you have any
questions or comments, please contact the office.
Sincerely,
Gulf Coast Electric Company, Inc.
P``44d A A-AA,
Kevin J. Picard
Vice President
KJP/dh
Cc: Files
IGWT
409 833-2828 • Fax 409 833-4308 • wwwgulfcoastelectric.com
,,,7f;- - Damage Results/Civic Center Parking Lot Lights
Pole No.of Fixture Location of
Location Heads Location of Conduit Results of Conduit Wire Results of Wire
1A 1 1A-3A Good 1A-3A BAD
2A 2 TAM Panel-2A TBD TAM Panel TBD
2A-6A Good 2A-6A BAD
3A 1 1A-3A Good 1A-3A BAD
3A-4A Good 34-4A BAD
4A 2 3A-4A Good 3A-4A BAD
4A-5A Good 4A-5A BAD
4A-74 Good 4A-7A BAD
5A 2 1A-SA Good 4A-SA BAD
6A 2 2A-6A Good 2A-6A BAD
7A 2 4A-7A Good 4A-7A BAD
7A-8A ? 7A-8A BAD
TBD TBD
8A 2 8A-9A GOOD 8A-9A BAD
7A-8A ? 7A-8A BAD
9A 2 8A-9A GOOD 8A-9A BAD
10A 2 10A-17A GOOD 10A-17A BAD
11A 2 11A-18A ? 11A-18A BAD
11A-12A ? 11A-12A BAD
12A 1 11A-12A TBD 11A-12A TBD
TBD TBD
13A 2 13A-14A GOOD 13A-14A BAD
TBD TBD
14A 2 13A-14A GOOD 13A-14A BAD
15A 1 15A-20A ? 15A-20A BAD
16A 2 16A-21A GOOD 16A-21A BAD
TBD TBD
17A 2 104-174 GOOD 10A-17A BAD
17A-22A GOOD 17A-22A BAD
18A 2 11A-18A GOOD 11A-18A - BAD
18A-23A GOOD 18-23A BAD
19A 2 19A-24A GOOD 19A-24A BAD
TBD TBD
20A 1 TBD _ TBD
P/ Damage Results Civic Center ParkingLot Lights
Pole No.of Fixture Location of
Location Heads Location of Conduit Results of Conduit Wire Results of Wire
15A-20A ? 15A-20A BAD
21A 2 16A-21A GOOD 16A-21A BAD
22A 2 17A-22A GOOD 17A-22A BAD
22A-25A GOOD 22A-25A BAD
23A 2 18A-23A GOOD 18A-23A BAD
23A-26A GOOD 23A-26A BAD
24A 2 19A-24A GOOD 19A-24A BAD
25A 2 22A-25A GOOD 22A-25A BAD
25A-36A GOOD 25A-36A BAD
26A 2 23A-26A GOOD 23A-26A BAD
26A-27 BAD/BROKEN AT BASE 26A-? BAD
27A 2 27A-28A GOOD 27A-28A BAD
26A-27A BAD 26A-27A BAD
28A 2 28-29 GOOD 28A-29A BAD
27-28 GOOD 27A-28A BAD
29A 2 28A-29A GOOD 28A-29A BAD
30A 2 30A-31A GOOD 30A-31A BAD
TBD TBD
31A 2 30A-31A GOOD 30A-31A BAD
31A-32A GOOD 31A-32A BAD
32A 2 31A-32A GOOD 31A-32A BAD
32A-34A GOOD 32A-34A BAD
33A 2 TBD TBD
33A-35A GOOD 33A-35A BAD
34A 2 32A-34A GOOD 32A-34A BAD
35A 2 33A-35A TBD 33A-35A TBD
TBD TBD
36A 2 25A-36A GOOD 25A-36A BAD
36A-37A GOOD 36A-37A BAD
37A 2 36A-37A GOOD 36A-37A BAD
EMPTY EMPTY
Bl 2 HR? TBD HR? TBD
B1-B2 GOOD B1-B2 BAD
B2 2 B1-B2 GOOD Bl-B2 BAD
B2-B3 GOOD B2-B3 BAD
U
%a
;;-----,— Damage Results/Civic Center Parking Lot Lights
Pole No.of Fixture Location of
Location Heads Location of Conduit Results of Conduit Wire Results of Wire
B2-A19 GOOD B2-A19 BAD
B3 2 B2-63 GOOD B2-B3 BAD
B3-84 BAD B3-B4 BAD
84 2 B3-B4 BAD B3-B4 BAD
B4-B5 GOOD B4-B5Q BAD
B5 2 B4-B5 GOOD B4-65 BAD
a
.#47--ft 4:1 .7,'"-'-'401
lif ,, ,, .
Pale'A.JPEG Pole 2A JPEG Pole 28 JPEG Pole 3A JPEG Pole 4A.JPE
061
11.11F1 .
� , �,rtilk
,,, t "r"
*36,;AIL) k 4 .., -t`-`4 ' .-.-0' 11.4
4110.71 4144111N '6` - till . r -
- -- Pole 8A.,=_, Pole 9A JPEG
, i'.. t.:, . Y
,,,, '-'d I
,. ... _ __.
..... •
... ,
Pole 21A.JPEG Pole 22AJPEG Pole 23A JPEG Po'e 2 e 0 JPEG Pole 25A JPEG
`!tes ti ??. 1111_.
.
/ Y .` \�`
f
Pole 26A.JPEG Pole 27AJPEG Pole 28A JPEG Pole 29A JPEG Pole 30A.JPE
'::, /orgit, „ 4—"‘ ir ;,
-1--,,,„‘..,
ti ``�..
Pole 31A.JPEG Pole 32A.JPEG Pole 34A.JPEG Pole 35A JPEG
Y gi \*,
Imo= -�- , r
t.
16
..2.,:„:„.„ .. ....
.„.„. :.. . .� .r..: .,� molie
i% tomA. -4
Pole 36A coot JPEG Pc e 35A.JP_ underground wire underground wre.JPEG
font IPF(;
I
{5
. , t" - i , i{ r
0.v.
1
Pole 1A_JPEG Pole 2A.JPEG Pole 2B.JPEG
`Pr° -',,:****s\
s
illigtt
et _
• \
#; .
*1111111r. . _1...... ,,.
Pole 5AJPEG Pole 6A_JPEG Pole 7A-JPEG
i ',,-
416 A- 4
imehismainuel,
Pole 21A.JPEG Pole 22AJPEG Pole 23AJPEG Pol
OP
Pole 26A.JPEG Pole 27A_JPEG Pole 28A.JPEG Pol
moo.
3
11_kfal. .)!
Poie 31A_JPEG Pole 32A_JPEG Pole 33A.JPEG Pc
4
itfr
Walk 4
.. Ailiweeek ,,,,.
.:}`
Pole 36A cont.JPEG Pole 36A_JPEG Pole 37A_JPEG unc
-441*
, r
-?
lit 0
Pole 3AJPEG Pole 4AJPEG
It
<of/
ii till ..
r-`- ;*
4 ,.
Pole 8AJPEG Pole 9A.JPEG
le 24A_JPEG Pole 25AJPEG
I ` it
I
I
ti
e 29A.JPEG Pole 3OA.JPEG
., It
11
IS 7 ' ell
^ie 34A JPEG Pole 35A_JPEG
w ter- -
Jerground wire underground wire_JPEG
rnnt IPF(
EXHIBIT "B"
s.pr21024
5C, EPIC
ENGINEERING, LLC.
POWER•INSTRUMENTATION.CONTROLS Lon A. Hubbard, P.E.
Firm #F-14251.
October 17, 2019
Ardurra Group, LLC
2032 Buffalo Terrace
Houston. Texas 77019
Reference: Evaluation of"Civic Center Parking Lot Lights - Justification of Total
Damages_Gulf Coast Electric.xlsx"
Ladies and Gentlemen:
Assignment:
EPIC Engineering was engaged to evaluate documentation and evidence provided by
Gulf Coast Electric in the form of a spreadsheet "Civic Center Parking Lot Lights -
Justification of Total Damages_Gulf Coast Electric.xlsx". The spreadsheet was an
indication of conduit and cabling systems that were in good condition and conduits and
cabling systems that were in a non-usable condition.
Evaluation:
On October 17, 2019 Chris Hamilton with EPIC Engineering had a conversation with
Kevin Picard of Gulf Coast Electric to confirm the procedure that was followed to
determine faulty conduit systems. To determine faulty conduits, the conductors were
removed, and a pull line and rage was passed through the conduit. Conduits in the
spreadsheet that are marked other than "GOOD" would not allow passing of pull line
and rag. Such conduits are damaged and damaged sections shall be repaired.
In the process of removing the conductors from the conduits, conductors a likely
damaged. It was also noted that there was excessive discoloration and deterioration in
the conductor's insulation. This is a result of excessive exposure to flood water and silt
within the conduit system. All conductor shall be replaced.
603 Dayton St. Orange,Texas 77630 409-670-9393 409-267-1149
ii( EPIC
ENGINEERING, LLC.
POWER INSTRUMENTATION•CONTROLS Lon A. Hubbard, P.E.
Firm#F-14251
Conclusion:
EPIC Engineering concurs with the damage assessment provided in the "Civic Center
Parking Lot Lights - Justification of Total Damages_Gulf Coast Electric.xlsx"
Respectfully,
EPIC Engineering
L A iiiiet,1_
Lon A. Hubbard, P.E.
Principal Engineer
000000p4
ho
*�° -...0... °9 Ido
0 LON HUBBARD 0
oQ.$ 64303 °°.o
0
October 17, 2019
603 Dayton St. Orange,Texas 77630 409-670-9393 409-267-1149
EXHIBIT "C"
s.pr21024
interoffice
MEMORANDUM
To: Mayor and City Council
From: Ron Burton, Interim City Manager l,�.,4
Date: October 31, 2019 +
Subject: P.R. No. 21024
I have reviewed Amendment No. 1 to the contract between the City and Gulf Coast
Electric Co., Inc. for the repair of the Civic Center and Library parking lot lights. The
amendment in the amount of$243,120.00 and the additional thirty (30) days is for various
needed unforeseen damages that were discovered while making said repairs. I approve
the expenditure of the contingency funds for the repairs of the unforeseen damages
discovered as delineated above.