INTEROFFICE MEMORANDUM
Date: February 11, 2020
To: The Honorable Mayor and City Council
Through: Ron Burton, City Manager
From: Donald Stanton, Interim Director of Utilities
RE: Proposed Resolution No. 21280—TWDB Funding application for 57 water
mains
Introduction:
The Water Line Improvement project is proposed to be funded under the Texas Water
Development Board Drinking Water State Revolving Fund(DWSRF). Arceneaux Wilson&
Cole, LLC (AWC) is preparing the Project Information Form (PIF) for this project to get
project approval for a loan application commitment for the fall of 2020. This loan application
commitment does not obligate the City to the funding but allows the City to be considered for
funding up to the amount requested in the PIF.
Background:
The Water Line Improvement project will aid in the low pressure and leakage problems that
the City's water distribution system currently experiences. By replacing deteriorated water
lines with adequately sized pipes and with new PVC pipe materials. The total footage of new
water line is approximately 120,000 feet throughout several areas of Port Arthur. The
improvements were based on maintenance records of water leaks repaired and older pipe
materials needing upgrades. The project has a total estimated construction cost of
approximately$16,000,000.00 and will require a design extension of one of the current main
transmission lines along Atlanta. AWC has already completed the construction plans for this
project, other than the added Atlanta line, and therefore is primarily seeking funds for the
construction phase.
Budget Impact:
Total estimated construction cost is $16,000,000.00.
Recommendation:
It is recommended that City Council authorize the City Manager to submit an application to
the Texas Water Development Drinking Water State Revolving Fund Program, as discussed
and/or outline above.
"Remember,we are here to serve the Citizens of Port Arthur"
P.O.Box 1089 X Port Arthur,Texas 77641-1089 X 409.983.8101 X FAX 409.982.6743
P.R. No.21280
02/11/2020 bw
Page 1 of 2
RESOLUTION NO.
A RESOLUTION AUTHORIZING THE CITY MANAGER
TO SUBMIT AN APPLICATION TO THE TEXAS WATER
DEVELOPMENT BOARD DRINKING WATER STATE
REVOLVING FUND PROGRAM. REQUESTED FUNDS
ARE NECESSARY FOR IMPROVEMENTS TO THE 57
WATER MAINS IDENTIFIED BY REPAIR RECORDS.
WHEREAS, the Texas Water Development Board provides lower interest loans through
the Drinking Water State Revolving Fund Program (DWSRF) for the planning, design and
construction of water mains; and,
WHEREAS,the DWSRF rates may be one percent(1%) lower than market rates; and,
WHEREAS,the City is currently performing an overhaul on the 57 water mains; and,
WHEREAS, an entity seeking DWSRF funding in the fiscal year 2020 must submit an
application/information form for priority ranking by April 30, 2020; and,
WHEREAS, it is in the City's best interest to fund this project through the DWSRF.
NOW THEREFORE,BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF PORT ARTHUR:
THAT,the facts and opinions in the preamble are true and correct; and,
THAT, the City Manager is hereby authorized to submit the attached Exhibit A
information form to the Texas Water Development Board DWSRF for the purpose of ranking the
57 water mains for funding; and,
THAT a copy of the caption of this resolution be spread upon the minutes of the City
Council.
READ,ADOPTED,AND APPROVED THIS day of , 2020 at
a Regular Meeting of the City Council of the City of Port Arthur, Texas, by the following vote:
AYES: Mayor
P. R. No. 21280
02/11/2020 bw
Page 2 of 2
Councilmembers:
NOES:
Thurman"Bill"Bartie
Mayor
ATTEST: APPROVED AS TO FORM:
i . on 6e40(-i o
P"
Sherri Bellard Va :�� iz
City Secretary Cit • ttorn
APPROVED FOR ADMINISTRATION:
Ronald Burton
City Manager
•
Donald Stanton
Interim Director of Utilities
(1414,1`
Kandy Dani Clifton illiams, CPPB
Interim Director of Finance Purchasing Manager
Exhibit A
N
!I:11
d c0d� G~ Vlt
5 ° '54 5N F' O
ie Pri >o
—
! 1 gg.82 as. ril aa5„ g
1 W z os O,aI�' n
ili 8� a W o W W f I
Q a fi LL=2 Z i
§ ; W ?�
V ~
3 •as
Y .
\ r
II t
Z
0, 5
00 k
r ,
. ..
, ....
_ :,,_ ,
. ••• . . .
:.
.. ,
...
.,,.. ,.c. ,
•
•
T� rT 0 . 1
• . __
-L^ 4, f \— <c_. r [77 •,.4.1 .. 'i--.
e:
•
r
L i _, -
J__
•
c
A'./;(:\'z',--:_iit, .. __,
1
---L
k- y
S
Estimated Costs Texas Water Development Board
Drinking Water State Revolving Fund
Seeking planning funding N PIF # 1319405
Seeking acquisition funding N
Seeking design funding Y Entity Name: Port Arthur
Seeking construction funding Y Project Name: Water Line Improvements
Cost Category (a) Planning (b)Acquisition (c) Design (d) (e) Total
Construction (a)+(b)+(c)+(d)
Treatment $0 $0 $0 $0 $0
Transmission $0 $0 $0 $16,000,525 $16,000,525
and
Distribution
Source $0 $0 $0 $0 $0
Storage $0 $0 $0 $0 $0
Purchase of $0 $0 $0 $0 $0
System
Restructuring $0 $0 $0 $0 $0
Land $0 $0 $0 $0 $0
Acquisition
Source Water $0 $0 $0 $0 $0
Protection
Engineering $0 $0 $50,000 $192,006 $242,006
General, Legal, $0 $0 $0 $0 $0
Financial
Contigency $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0
(Describe
Cost)
Subtotal (Add $0 $0 $50,000 $16,192,531 $16,242,531
all rows above)
Financing from $0 $0 $0 $0 $0
Local Funds
Financing from $0 $0 $0 $0 $0
Other Funds
Subtotal, SRF- $0 $0 $50,000 $16,192,531 $16,242,531
Funded
Amount
Green component costs as a percentage of"Subtotal, SRF-Funded Amount" 0%
Anticipated Commitment(s) MULTIYEAR
.pavxAl okARCENEAUX WILSON&COLE
engineering i surveying I planning
City of Port Arthur
Water Line Improvements
Drinking Water State Revolving Fund (DWSRF) SFY 20
Project Information Form (PIF)
February 11, 2020
The Water Line Improvement project is proposed to be funded under the Texas
Water Development Board Drinking Water State Revolving Fund (DWSRF).
Arceneaux Wilson & Cole, LLC (AWC) is preparing the Project Information Form
(PIF) for this project to get project approval for a loan application commitment
for the fall of 2020. This loan application commitment does not obligate the City
to the funding but allows the City to be considered for funding up to the amount
requested in the PIF.
The Water Line Improvement project will aid in the low pressure and leakage
problems that the City's water distribution system currently experiences. By
replacing deteriorated water lines with adequately sized pipes and with new PVC
pipe materials. The total footage of new water line is approximately 120,000 feet
throughout several areas of Port Arthur. The improvements were based on
maintenance records of water leaks repaired and older pipe materials needing
upgrades. The project has a total estimated construction cost of approximately
$16,000,000 and will require a design extension of one of the current main
transmission lines along Atlanta. AWC has already completed the construction
plans for this project, other than the added Atlanta line, and therefore is primarily
seeking funds for the construction phase.
409.724.7886
290`Turtle Creek Dr.,Suite 320
Port Arthur,TX 77642 Engineering Surveying
awceng.com F-16194 10194049
City of Port Arthur
Water Line Improvement Project
Item Description Unit Unit Price Quantity Total Cost
1 Mobilization/Demobilization L.S. $150,000.00 1 $150,000.00
2 20-Inch C905 PVC Water Line L.F. $175.00 4,500 $787,500.00
3 16-Inch C905 PVC Water Line L.F. $135.00 5,675 $766,125.00
4 12-Inch C905 PVC Water Line L.F. $90.00 9,700 $873,000.00
5 8-Inch C900 PVC Water Line L.F. $45.00 9,700 $436,500.00
6 6-Inch C900 PVC Water Line L.F. $40.00 89,250 $3,570,000.00
7 20-Inch PVC Bore Construction L.F. $225.00 625 $140,625.00
8 16-Inch PVC Bore Construction L.F. $160.00 200 $32,000.00
9 12-Inch PVC Bore Construction L.F. $120.00 50 S6,000.00
10 8-Inch PVC Bore Construction L.F. $115.00 125 $14,375.00
11 6-Inch PVC Bore Construction L.F. $110.00 3,200 $352,000.00
12 16-Inch Directional Drilling L.F. $250.00 1,050 $262,500.00
13 12-Inch Directional Drilling L.F. $180.00 600 S108,000.00
14 8-Inch Directional Drilling L.F. $150.00 275 $41,250.00
15 6-Inch Directional Drilling L.F. $140.00 3,200 $448,000.00
16 20-Inch Gate Valve& Box EA. $14,000.00 40 $560,000.00
17 16-Inch Gate Valve& Box EA. $6,000.00 30 $180,000.00
18 12-Inch Gate Valve& Box EA. $2,400.00 60 $144,000.00
19 10-Inch Gate Valve& Box EA. $1,600.00 10 $16,000.00
20 8-Inch Gate Valve& Box EA. $1,400.00 80 $112,000.00
21 6-Inch Gate Valve& Box EA. $1,100.00 475 S522,500.00
22 4-Inch Gate Valve& Box EA. $900.00 30 $27,000.00
23 2-Inch Gate Valve& Box EA. $800.00 5 $4,000.00
24 1-Inch HDPE Service Line EA. $1,500.00 1,300 $1,950,000.00
25 Fire Hydrant Assembly EA. $4,000.00 275 $1,100,000.00
26 2-Inch Air Release Valve EA. $4,100.00 50 $205,000.00
27 Remove/Replace Fencing L.F. $50.00 1,000 $50,000.00
28 Remove/Replace Sidewalk S.Y. $80.00 1,200 $96,000.00
29 Remove/Replace Concrete S.Y. $100.00 250 $25,000.00
Section
30 Remove/Replace Asphalt and S.Y. $85.00 4,000 $340,000.00
Base Section
31 Trench Safety All Depths L.F. $5.00 118,825 $594,125.00
$13,913,500.00
CONTINGENCY 15% $2,087,025.00
TOTAL CONSTRUCTION ESTIMATE $16,000,525.00