Transit Department
Memorandum
To: Ronald Burton,City Manager
From: Ivan Mitchell,Transit Director
Cc: Joshua Melling,Maintenance Supervisor
Date: March 5,2020
Re: P.R.21313—Authorization to execute a change order with the Construction Managers of
Southeast Texas(CMOST)to construct PAT's new maintenance building and electric
charging infrastructure
Nature of Request: Proposed Resolution No. 21313 requests authorization for the City Manager to
execute change order No. 1 with Construction Managers of Southeast Texas (CMOST) to construct
PAT's new maintenance facility and electric bus charging infrastructure.
Background: Resolution No. 20-042 authorized the City Manager to execute a contract with the
Construction Managers of Southeast Texas(CMOST)to construct PAT's new maintenance facility and
electric bus charging infrastructure, and supply specified tools and shop equipment. In an effort to
consolidate project cost PAT and its engineer (Huitt-Zollars) elected to value engineer (VE)
CMOST's$3,495,000.00 base bid. The VE effort resulted in a$154,199.64 reduction and a new base
bid total of$3,340,800.36.
The$154,199.64 base bid reduction enables PAT to fund Alternates No. 1 and No. 2. Alternate No. 1
consists of constructing an in-ground pit in the new maintenance building. CMOST's bid price for
Alternate No. 1 is $254,794.13 which was value engineered to remove $28,450.43, resulting in a
revised total of$226,343.70. Alternate No. 2 is the purchase and installation of an in-ground at a bid
price of$194,671.57. CMOST was tasked with obtaining additional quotes from qualified vendors
who meet the Buy America and equipment specifications. CMOST obtained a vendor who met these
requirements at a reduction of $30,215.27; therefore the revised total for Alternate No. 2 is
$164,456.30.
The inclusion of Alternate No. 1 and No.2 allows PAT to construct a maintenance facility that is fully
equipped to maintain its fleet of fixed-route and paratransit vehicles. The VE reductions and adding
on Alternate No. 1 and No. 2 result in a new project total of$3,731,600.36 which is an additional
$236,600.36.
Recommendation: It is recommended that the City Council approve proposed P.R. 21313,authorizing
the City Manager to enter into a change order with CMOST to construct PAT's new maintenance
facility and electric bus charging infrastructure in the amount not to exceed$3,731,600.36.
Budgetary/Fiscal Effect: The Federal 5307 and 5339(b)funds for this project are 100%reimbursable
in account 401-1509-561.82-00 with a local match of$58,700 required for the Federal 5339(c)funds.
P.R. No. 21313
3/5/2020 IM
RESOLUTION NO.
A RESOLUTION AUTHORIZING THE CITY MANAGER TO ENTER INTO A
CHANGE ORDER WITH THE CONSTRUCTION MANAGERS OF SOUTHEAST
TEXAS OF PORT ARTHUR, TEXAS TO CONSTRUCT PORT ARTHUR TRANSIT'S
NEW MAINTENANCE BUILDING AND ELECTRIC CHARGING
INFRASTRUCTURE, IN AN AMOUNT NOT TO EXCEED $3,731,600.36; FUNDS
AVAILABLE IN ACCOUNT 401-1509-561.82-00.
WHEREAS, pursuant to Resolution No. 20-042, the City Council authorized the City
Manager to execute an agreement with the Construction Managers of Southeast Texas
(CMOST) to construct the new maintenance building and electric charging infrastructure for
Port Arthur Transit(PAT) in the amount not to exceed$3,495,800.36; and,
WHEREAS, PAT has been allotted federal funding to construct the maintenance
building and electric charging infrastructure; and,
WHEREAS, PAT and its engineer (Huitt-Zollars) chose to value engineer (VE) the
base bid which resulted in a$154,199.64 reduction attached hereto as Exhibit"A";; and,
WHEREAS, the base bid reduction has enabled PAT to include Alternate No. 1
(inspection pit) and No. 2 (in-ground lift) in the project scope at an additional cost of
$236,600.36; and,
WHEREAS, PAT is recommending that the City of Port Arthur by its City Manager
enter into a change order with CMOST, as delineated in Exhibit"B".
WHEREAS, a change order agreement between the City of Port Arthur and CMOST is
attached hereto as Exhibit"B".
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE
CITY OF PORT ARTHUR:
THAT, the facts and opinions in the preamble are true and correct.
THAT, the City Manager is hereby authorized to enter into a change order with the
Construction Managers of Southeast Texas (CMOST) of Port Arthur, Texas, to construct Port
Arthur Transit's maintenance building and electric charging infrastructure, in an amount not to
exceed $3,731,600.00, in substantially the same form as attached hereto as Exhibit"B".
P.R. No. 21313
3/5/2020 IM
THAT, a copy of the caption of this Resolution be spread upon the Minutes of the City
Council.
READ,ADOPTED AND APPROVED this day of A.D. 2020 at a
Regular Meeting of the City of Port Arthur, Texas by the following vote: AYES:
Mayor:
Councilmembers:
NOES:
Thurman"Bill" Bartie, Mayor
ATTEST:
Sherri Bellard, City Secretary
APPROVED AS TO FORM:
Val Tizeno, City Attorney
APPROVED FOR ADMINISTRATION: APPROVED AS TO AVAILABILITY
OF FUNDS:
401-1509-561.82-10
Ronald Burton Kandy Daniel
City Manager Interim Director of Finance
Clifton Williams, CPPB Ivan Mitchell
Purchasing Manger "I"ransit Director
P.R. No. 21313
3/5/2020 IM
Exhibit "A"
0 Construction Managers
of Southeast Texas, LLC
225 HIGHWAY 365—PORT ARTHUR,TEXAS 77640—PHONE(409) 736—9010—FAX(409)7369020
March 03, 2020
Port Arthur Transit
344 Procter St.
Port Arthur, TX 77640
Re: Transit Maintenance Facility
Change Proposal No.01:
Mr. Mitchell:
Please find below the cost associated with the accepted value engineering(VE) options for the Construction
Managers of Southeast Texas, LLC base bid. We have also included the VE cost for the addition of Alternates
No.01 and No.02 to the project scope. If you have any questions, please let me know.
1. Value Engineering Contract Deductions from Base Bid ($154,199.64)
2. Added cost for Alternate No.01 including VE deductions $226,343.70
3. Added cost for Alternate No.02 including VE deductions $164,456.30
Revised TOTAL: S236,600.36
Sincerely,
Construction Managers
of Southeast Texas, LLC
7
cf‘., d4b,
Jose Cardenas
Project Manager
CC: Bruce Reyes—CMOST
Ig'
Construction Manac��rs
of SDut€ Past Texas, LLC
ti
3/3/2020
City of Port Arthur Transit Maintenance Facility- Base Bid P20-014
Item # Description Value Approved
Mechanical
Remove Controls. Efs can still operate the same using time
clocks. Economizer,fresh air mix, modulation hot gas
reheat, modulating heat, barometric exhaust all would be
1 controlled by RTU. T,Stat will control scheduling. $ (30,000.00) $ (30,000.00)
Exterior Improvements
2 Delete Termite/Soil Treatment $ (6,200.00) $ (6,200.00)
Finishes
Change Ceiling tile from Armstrong MESA to Armstrong
3 1728 $ (1,200.00) $ (1,200.00)
Electrical
4 Use I-Line panelboard in lieu of the switchboard @ "MSB" $ (2,500.00) $ (2,500.00)
Reduce fuel tank on generator from a 72 hour tank to a 48
5 hour tank. $ (4,000.00) $ (4,000.00)
Delete removal of light poles from CMOST scope, to be
6 perfromed by the City. $ (1,000.00) $ (1,000.00)
Equipment
6 Delete Tire Racks, to be by owner $ (1,000.00) $ (1,000.00)
7 Delete Shelving Units, Units to be by owner $ (38,000.00) $ (38,000.00)
8 Delete Parts Washer, to be by owner $ (991.66) $ (991.66)
9 Delete Jack Stands,to be by owner $ (3,503.12) $ (3,503.12)
10 Delete Flammable Materials Cabinet,to be by owner $ (1,756.00) $ (1,756.00)
11 Delete Office Stool,to be by owner $ (883.15) $ (883.15)
12 Delete Electronic Workstation Stool,to be by owner $ (1,535.79) $ (1,535.79)
13 Delete Electronic Workstation,to be by owner $ (4,144.92) $ (4,144.92)
14 Delete Vises,to be by owner $ (3,500.00) $ (3,500.00)
15 Delete Column lifts,to be by owner $ (46,000.00) $ (46,000.00)
26 Delete five storage cabinets,to be by owner $ (6,985.00) $ (6,985.00)
27 Use Stertil Koni Air Compressor in lieu of specified $ (1,000.00) $ (1,000.00)
TOTAL PROPOSED VE ITEM VALUE $ (154,199.64) $ (154,199.64)
Original Base Bid $ 3,495,000.00
Revised Base Bid $ 3,340,800.36
Construction Managers
of Southeast Texas, LLC
3/3/2020
City of Port Arthur Transit Maintenance Facility -Alternate#1 P20-014
Item # Description Value Approved
Equipment
1 Delete Shelving Units and Vises,to be by owner $ (6,068.43) $ (6,068.43)
Change Portable work platform in th epit to a catwalk by
2 Stertil Koni S (19,932.00) $ (19,932.00)
Electrical
3 Delete half of the battery packs @ light fixtures in the pit. $ (2,450.00) $ (2,450.00)
TOTAL PROPOSED VE ITEM VALUE $ (28,450.43) $ (28,450.43)
Original Alternate#1 Cost $ 254,794.13
Revised Alternate#1 Cost $ 226,343.70
City of Port Arthur Transit Maintenance Facility -Alternate#2 P20-014
Item # Description Value Approved
Equipment
1 Use In-Ground Lift by Stertil Koni $ (30,215.27) $ (30,215.27)
TOTAL PROPOSED VE ITEM VALUE $ (30,215.27) $ (30,215.27)
Original Alternate#2 Cost S 194,671.57
Revised Alternate#2 Cost $ 164,456.30
City of Port Arthur Transit Maintenance Facility-SUMMARY P20-014
Item # Description Value
1 Revised Base Bid Cost t including VE Deductions $ 3,340,800.36
2 Revised Alternate#1 Cost including VE Deductions $ 226,343.70
3 Revised Alternate#2 Cost Including VE Deductions $ 164,456.30
TOTAL Revised Project Cost $ 3,731,600.36
Additional Funds Required $ 236,600.36
P.R. No.21313
3/5/2020 I M
Exhibit "B"
PAT MAINTENANCE BUILDING CONSTRUCTION CHANGE ORDER NO. 1
ORIGINAL AGREEMENT DATE: February 28, 2020
PROJECT DESCRIPTION: Port Arthur Transit Maintenance Building Construction
CHANGE IN SCOPE: Please see the attached document detailing the scope change.
CHANGE TO CONTRACT AMOUNT:
ORIGINAL CONTRACT PRICE: $3,495,000.00
CURRENT CONTRACT PRICE (adjusted by previous CHANGE ORDER):$3,495,000.00
The Contract Amount due to this CHANGE ORDER will increase by: $236,600.36
The new CONTRACT AMOUNT including the CHANGE ORDER will be: $3,731,600.36
ORIGINAL CONTRACT DAYS: Nine-month contract from notice to proceed
NEW CONTRACT DAYS: Nine-month contract from notice to proceed
SIGNED AND AGREED TO on the day of , 2020.
CONSTRUCTION MANAGERS OF SOUTHEAST TEXAS
Print Name:
Title:
SIGNED AND AGREED TO on the day of , 2020.
CITY OF PORT ARTHUR
BY:
RONALD BURTON,
CITY MANAGER