COMMENTS
RECOMMENDATION:
I recommend that the City Council approve Proposed Resolution No. 11937 executing a construction
contract with Allco, Inc., of Beaumont for $4,158,410.90 for water line rehabilitation.
BACKGROUND:
This water line rehabilitation project is part of the city-wide water system improvements plan. it includes
the replacement of approximately 93,500 fee of the City's water lines with the greatest break frequency. On
August 28, 2002, the City received four (4) sealed bids for this project. Allco, Inc., of Beaumont submitted
the lowest bid for the project. Arceneaux & Gates Consulting Engineers have reviewed the bids and
recommend that the City award to Alice, Inc. of Beaumont. The bid results are as follows:
Contractor
Mason Construction
Orange, Texas
Total Bid
$4,591,491.85
AIlco, Inc.
Beaumont, Texas
$4,158,410.90
Excavators & Constructors
Port Arthur, Texas
$5,210,548.50
Brystar Contracting
Beaumont, Texas
$5,428,425.00
"Remember, we are here to serve the citizens of Port./lrlhur"
Memo to Steve Fitzgibbons
Page 2 of 2
BUDGET/FISCAL EFFECT:
Funds for the Water Improvement Projects are budgeted in the City Water & Sewer CIP Fund No. 427-
1626-532.85-00. This project is budgeted at $4,500,000. The low bid of$4,158,410.90 is 7.5% below the
budgeted amount. The Engineer's Estimate was approximately $5.4 million. Various alternates for material
substitution were bid in order to determine the lowest and best possibility. Alternate F was selected due to
the considerable savings ($209,115.50). Alternate F substitutes PVC pipe in place of HDPE pipe in one
location along S.H. 87 toward Sabine. HDPE was specified in the base bid because in the long open area
along S. H. 87, it was expected that HDPE would be less expensive. However PVC pipe was bid less by all
contractors. PVC pipe is a good material selection in this application. Please note that Allco's bid was
lo,vest in each alternate as well as the base bid.
STAFF/EMPLOYEE EFFECT:
City staffwill monitor this contract.
SUMMARY:
I recommend that the City Council approve Proposed Resolution No. 11937 authorizing execution of a
construction contract with Allco, Inc.
/ld
"Remember we are here to serve the citizens of
RESOLUTION NO.
A RESOLUTION AWARDING A CONTRACT AND AUTHORIZING THE
EXECUTION OF SAID CONTRACT IN THE AMOUNT OF $4,158,410.90
FOR WATER LINE REHABILITATION BETWEEN THE CITY OF PORT
ARTHUR AND ALLCO, INC., OF BEAUMONT, TEXAS. ACCOUNT NO.
427-1626-532.85-00, PROJECT NO. 427005.
P.R. No. 11937
09-18-02 DS/Id
WHEREAS, the City of Port Arthur advertised and received bids from contractors for water main
improvements; now therefore,
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PORT ARTHUR:
THAT, the City Council of the City of Port Arthur hereby awards the contract for water main
improvements with Alternate "F" to the lowest bidder to-wit: Allco, Inc., of Beaumont, Texas; and,
THAT the City Manager of the City of Port Arthur is hereby authorized to execute on behalf of
the City of Port Arthur a contract between the City of Port Arthur and Allco, Inc., in the amount of
$4,158,410.90 a copy attached hereto as Exhibit "A"; and,
THAT a copy of engineer's recommendation for awarding the contract to the lowest responsible
bidder is attached hereto as Exhibit" B"; and,
THAT the said contract is an exact duplicate of a City Standard Form contract except for the
changes (if any) shown in the Certificate of Standard for Contract, a copy of which is attached hereto as
Exhibit "C", and said changes are hereby approved; and,
THAT a copy of the caption of this Resolution be spread upon the Minutes of the City Council.
READ, ADOPTED AND APPROVED THIS day of ,2002 at a
Regular Meeting of the City Council of the City of Port Arthur, Texas, by the following vote:
AYES: Mayor
Councilmembers
P.R. No. 11937
09-18-02 DS/Id
Page 2 of 2
NOES: "
ATTEST:
Evangeline Green
City Secretary
APPROVED:
Steve Fitzgibbons
City Manager
APPROVED AS TO FORM:
Mark Sokolow
City Attorney
APPROVED FOR ADMINISTRATION:
Shep el'i'~ ~ '
Director of Utility Operations
D~S TO AVAILABILITY OF FUNDS:
Rebecca Underhill
Director of Finance
Oscar Ortiz
Mayor
P. R. No. 11937
Page 1 of I
Exhibit A is available for review
in the City Secretary's Office.
ARCENEAUX & GATES
Consulting Engineers, Inc.
Engineers · Surveyors · Planners
I;~hibit "g~
P. R. NO. 11937
Page 1 of 4
September 4, 2002
'Mr. Dan Shepherd
Director of Water Utilities
CITY OF PORT ARTHUR
PO Box 1089
Port Arthur, Texas 77641-1089
RE:
RECOMMENDATION OF AWARD OF CONTRACT
City Of Port Arthur Water Line Rehabilitation
Job No. 01-CPA-230 [Construction Phase No. 01-CPA-231]
Dear Mr. Shepherd:
On August 28, 2002 the City of Port Arthur received four (4) sealed bids for the construction
project named above. Representatives of our firm and the City conducted the mandatory
Pre-Bid meeting for this project. All firms that submitted bids were confirmed present at the
Pre-Bid meeting. The bids were opened in our presence on August 28, 2002, and the results
read aloud in the public bid opening. AIIco, Inc. of Beaumont, Texas, submitted the lowest
Total Amount Bid. The Total Amount Bid, without Alternates was $4,367,526.40. There were
a total of eight Alternates provided on the bid. Each of the eight alternates involved
substitution of material only in order to obtain the greatest savings for the City of Port Arthur.
The bids were analyzed for all possible combinations of alternates and it was found that
AIIco, Inc. submitted the lowest, responsive Bid for all possible combinations (Total Amount
Bid plus any combination of Alternates and/or Substitutions). A copy of the certified Bid
Tabulation is enclosed for your information.
We have reviewed the bids along with the alternates and determined that acceptance of
Alternate "F" will provide the best value to the City. Alternate "F" substitutes C900 Polyvinyl
Chloride (PVC) pipe for High-Density Polyethylene pipe (HDPE), including the associated
valves and fittings, and will result in a $209,115.50 deduction in the Total Amount Bid by the
Iow Bidder. The following is a summary of the Total Amount Bid including Alternate "F":
AIIco, Inc.:
$4,158,410.90
Mason Construction:
$4,591,491.85
Excavators & Constructors: $5,210,548.50
Brystar Contracting:
$5,428,425.00
One Turtle Creek Square 3501 Turtle Creek Ddve, Suite 102 Port Arthur, Texas 77642 (409) 724~7888 FAX (409) 724-1447
~hibit ~13~
P, R. No. 11937
Page 2 of 4
Mr. Dan Shepherd
City of Port Arthur
September 4, 2002
Page Two
We conducted a brief verification of the qualification statement prepared by the Iow bidder
and find no discrepancies in the information submitted. We therefore recommend that the
City award this contract to AIIco, Inc., the lowest responsive bidder on the basis of the Total
Amount Bid including Alternate "F" in the amount of $4,158,410.90. Should you have any
questions or require additional information, please contact our office.
Very truly yours,
ARCENEAUX & GATES CONSULTING ENGINEERS, INC.
Presidenf/CEO
Enclosure: Bid Tabulation
I;;~hibit ~[l~
P. R. No. 11937
Page 3 of 4
B~D TABULATION
For The
Water Line Rehabilitation
City of Port Arthur
Job No. 01-CPA-230
BIDE OPENED: August 28, 2002 at 3:10 P.M.
I~xhibit "B,"
P. R. No. 11937
Page 4 of 4
Total Water Line Items $ 4,312,739,40 $ 5,563,725.00 $ 4,771,682.00 $ 5,478,486.50
Total Supplemental Items $ 54,787.00 $ 71,870.00 $ 56,759.85 $ 55,662.00
Total Amount Bid $ 4,367,526.40 $ 5,635,695.00 $ 4,828,441.85 $ 5,534,t48.50
Total Amount Bid With Alternate "F" $ 4,t58,410.90 $ 5,428,425.00 $ 4,591,49t.86 $ 5,210,548.50
~it "C"
P. I~. No. 11937
Page 1 of 3
(City of Port Arthur)
(Law Department)
(Required Form)
(7/8~88)
(10/5/89)
(3/15/90)
(9-8-94)
(p.2 Revised 9/18/90
I certify that the contract (hereinafter called "said contract") affixed to the attached Proposed City Council Resolution No
11937 is an exact dupLLcate of an applicable standard form contract (the title of which is shown below) previously approved
by the Law department and adopted as a standard form by City Council Resolution, except for the blanks that have been
filled in with all necessary information and except for the changes described be[ow.
The title of the applicable standard form contract is:
[ ] Federally Funded Construction Contract, Revised 1/5/88, 7/89, 8/89; 4/28/94
[X] Non-Federally Funded Construction Contract, Revised 1/5/88, 7/89, 8/89; 4/28/94
[ ] Federal - Professional Services - Engineering Contract, Revised 1/5/88, 5/89 (§10) 7/89/(§8); 10/89; 2/91 (§8)
[ ] Non-Federal - Professional Services - Engineering Contract, Revised 1/5/88, 5/89(§10), 7/89(§8), 10/89;
2/91(§8)
[ ] CDBG - Professional Services - Engineering Contract, Revised 1/5/88, 5/89 (§10), 7/89(§8), 10/89; 2/91 (§8)
[ ] Federal - Professional Services -
Non-Engineering (Consultant) Contract, Revised 1/5/88, 5/89 (§10), 7/89 (§8); 10/89; 2/91 (§8)
[ ] Non-Federal - Professional Services -
Non-EngineerLng (Consultant) Contract, Revised 1/5/88, 5/89 (§10), 7/89 (§8); 10/89; 2/91 (§8)
[ ] CDBG - Professional servLces -
Non-Engineering (Consultant) Contract, Revised 1/5/88, 5/89 (§10), 7/89 (§8); 10/89; 2/91 (§8)
[ ] Other Standard Form Contract, described as follows:
The changes are as follows: (Put an "X' in the appropriate [ ])
[X] None.
[ ] The following described provisions at the indLcated page, section, etc. of the standard form have been deleted
from said contract:
Page 1 of 3
(p.2 Revised 9/18/90)
(Certificate of Standard Form Contract, page 2)
DElEtIONS
Exhibit "C"
P. R. No. 11937
Page 2 of 3
Page Number
Where
Deleted Provision
Is
Found On Standard Form
None.
Section or Paragraph No.
and Caption
Which
Contains Provision
Deleted From Form
Subsection or
Subparagraph No.
and Caption
Which Contains Provision
Deleted From Form
Description of
Provision DeJeted
[ ] The foLLowing described provisions at the indicated page, section, etc. of the standard form have been altered,
modified, replaced or otherwise changed:
ALTERATIONS, MO~IFI~ATIOtV$, REP/ACEMEItfT$, ETC.
Sub § or Sub ¶ No.
Page No. § or ¶ No. E Caption E Caption Description
Where of of of
Provision Found Standard Form which Standard Form Provision
on Contains Provision which in
Standard Form Contains Provision Standard Form
Page § Et caption
sub § ~ caption, etc.
of said contract
which contains
altered, etc.
provision; Et
Description of
Alteration etc.
No Changes
Page 2 of 3
p.3 Revised 9/18/90)
(Certificate of Standard Form Contract, page 3)
Exhibit "C"
P. R. No. 11937
Page 3 of 3
[ ] The following provisions have been added to Said Contract:
No Additions
Page, Section and Caption
Subsection and Caption, etc. of Said Contract Which
Contains the Added Provision and OescriptJan Thereof
I further certify that said attached proposed City Council Resolution contains the following provision:
"That said contract is an exact duplicate of a City Standard Form Contract except for the changes described in the
Certificate of Standard Form Contract, a copy of which is attached hereto as Exhibit "A" and is hereby incorporated by
reference, and said changes are hereby approved."
I understand that this certificate will be reLied on by the Law Department in reviewing and approving (or rejecting)
as to form and by the City Council in reviewing and adopting (or rejecting) said Resolution and Contract.
Signed this ~'~/~ day of ~'~. , 2002.
~'~epartment Head~"~- J
Page 3 of 3