INTEROFFICE MEMORANDUM
Date: April 23,2020
To: The Honorable Mayor and City Council
Through: Ron Burton,City Manager
From: Alberto Elefano, P.E., Public Works Director
RE: P.R.21376: City Hall Gas Generator Change Order#2 from A&A Electric Co., LLC of Beaumont,
Texas to re-route and isolate Entergy's high voltage electrical system per Entergy's Standards.
Introduction:
The intent of this Agenda Item is to authorize the City Manager to execute Change Order No. 2 from A&A Electric
Co., LLC of Beaumont,Texas which increases the contract amount by$6,517.00 from the original contract amount
of$424,944.00 to the new contract amount of$431,461.00.
Background:
Pursuant to Resolution No. 19-503, A&A Electric, LLC of Beaumont, Texas was awarded the project for the
installation of a new Generac Generator SG0625 625KW to provide emergency back-up power to City Hall during
electrical outages. During the installation of new wiring inside the underground electrical vault, it was discovered
that Entergy of Texas has an extremely high voltage electrical grid inside as well. Entergy's system provides
electrical service not only to City Hall and the adjoining Annex Building, but also to the Development Services
Building,the US Post Office and the Transit Building. Entergy is requiring that the feeds for City Hall,the Annex
Building,and the Transit Building,which are of a lower voltage,be removed from their grid and isolated as its own
electrical leg. Change Order No.2 allows for the re-routing and isolation of these feeds according to the Standards
outlined by Entergy. Change Order No. 2 increases the contract amount by $6,517.00 from the original contract
amount of$424,944.00 to the new contract amount of$431,461.00.
Budget Impact:
Change Order No.2 impacts funds in the Capital Improvement Account No. 625-1801-531.92-06.
Recommendation:
It is recommended that the City of Port Arthur City Council approve PR 21376 with A&A Electric Co., LLC of
Beaumont, Texas authorizing the City Manager to execute Change Order No. 2 for the re-routing and isolation of
the electrical feeds according to Entergy Standards which increases the contract amount by $6,517.00 from the
original contract amount of$424,944.00 to the new contract amount of$431,461.00.
"Remember,we are here to serve the Citizens of Port Arthur"
444 4th Street X Port Arthur,Texas 77641-1089 X 409.983.8182 X FAX 409.983.8294
Cirvof 1
to/art rtlraJ
Ictar
www.PortArthurTx.gov
INTEROFFICE MEMORAND U M
Date: April 23,2020
To: Ron Burton, City Manager
From: Alberto Elefano, Director of Public Works
RE: Removal,re-routing, and isolation of City electrical legs from inside Entergy's high voltage
electrical grid.
Port Arthur City Council, under Resolution 19-503, authorized the purchase of a new natural gas
powered Generac Generator SG0625 625KW to replace the outdated existing generator that was failing. A&A
Electric of Beaumont, Texas has been contracted to replace the generator.
A&A Electric began work on April 6, 2020 inside the underground electrical vault located on the west
side of the City Hall and Annex Building courtyard. New wiring was pulled through the vault. It was
determined that Entergy, the local electrical utility company, had a high voltage electrical system inside the
vault that needed to be de-energized to complete the electrical connections. This high voltage electrical system
can only be maintained by qualified Entergy personnel. This system contains"legs"that provide power to City
Hall, the Annex Building, the Development Services Building, Transit and the US Post Office. Entergy has
requested that the City comply with its new electrical standards that require City owned electrical feed lines be
removed and isolated from its grid. So, in conjunction with Entergy, A&A Electric will remove, re-route and
isolate those electrical lines that feed City Hall, the Annex Building, the Development Services Building and
Transit on Saturday, April 25, 2020. These areas will be without electrical power for approximately 10 hours
starting at 8:00 am.
The existing generator that will be used for temporary emergency power until the new one is in place
will be connected at that time. A&A Electric has coordinated the participation of various entities and equipment
providers to insure a safe and timely completion before the beginning of Hurricane Season on June 1, 2020. It
is imperative that A&A Electric be allowed to proceed as planned since a delay can create a hazardous situation.
A&A Electric of Beaumont, Texas has submitted Change Order No. 2 to address the removal, re-
routing, and isolation of City owned electrical feed lines in the amount of$6,517.00. This Change Order
increases the original contract amount from$424,944.00 to the new contract amount of$431,461.00. The funds
are available in the Capital Improvements Account No. 625-1801-531.92-06.
APPROVED:
Ron Burton
City Manager
cc: Clifton Williams,Purchasing Manager
"Remember,we are here to serve the Citizens of Port Arthur"
P.O.Box 1089 X Port Arthur,Texas 77641-1089 X 409.983.8101 X FAX 409.982.6743
PR No. 21376
4/23/20 mje
Page 1 of 3
RESOLUTION NO.
A RESOLUTION AUTHORIZING THE CITY MANAGER TO
EXECUTE CHANGE ORDER NO. 2 TO THE CONTRACT BETWEEN
THE CITY OF PORT ARTHUR AND A&A ELECTRIC CO., LLC OF
BEAUMONT, TEXAS FOR RE-ROUTING AND ISOLATION OF
HIGH VOLTAGE ELECTRICAL SERVICE INSIDE THE
UNDERGROUND VAULT PER ENTERGY OF TEXAS STANDARDS
THAT INCREASES THE CONTRACT AMOUNT BY $6,517.33
FROM THE ORIGINAL CONTRACT AMOUNT OF $424,944.00
TO THE NEW CONTRACT AMOUNT OF $431,461.33. FUNDING
IS AVAILABLE IN THE CAPITAL IMPROVEMENTS ACCOUNT
NO. 625-1801-531.92-06.
WHEREAS, pursuant to Resolution No. 19-503, the City of Port Arthur's City
Council authorized the City Manager to purchase a Generac SG0625 625KW Natural Gas
Generator through the BuyBoard Cooperative Purchasing Program from Waukesha-
Pearce Industries, Inc.; and,
WHEREAS, pursuant to Resolution No. 20-099 the City of Port Arthur's City
Council approved Change Order #1 in the amount of $52,888.00 for the elevation of the
new replacement gas generator and the re-location and re-installation of the old diesel
generator to provide temporary power to City Hall during the upgrade process; and,
WHEREAS, Entergy of Texas has established a high voltage electrical system
inside the underground electrical vault, located on the west side of City Hall, and is
requiring that the City remove and isolate feeds to City Hall, the Annex Building, the
Development Services Building, and the Transit Building;
WHEREAS, A&A Electric Co., LLC of Beaumont, Texas has submitted Change
Order #2 in the amount of $6,517.00 for removal, re-routing and isolation of electrical
PR No. 21376
4/23/2020 mje
Page 2 of 3
legs from Entergy's high voltage grid that fall under the City's responsibility, See Exhibit
A; and,
WHEREAS, Change Order #2 will increase the contract amount by $6,517.00
from the original contract amount of $424,944.00 to the new contract amount of
$431,461.00; and,
WHEREAS, Change Order No. 2 is herein deemed an appropriate action; now,
therefore,
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PORT ARTHUR:
THAT, the facts and opinions in the preamble are true and correct; and,
THAT, Change Order No. 2 is herein approved and the City Manager is authorized
to execute said Change Order No. 1 to the contract between the City of Port Arthur and
A&A Electric Co., LLC of Beaumont, Texas; and
THAT, Change Order No. 2, submitted by A&A Electric Co., LLC of Beaumont,
Texas will increase the contract amount by $6,517.00 from the original contract amount
of $424,944.00 to the new contract amount of $431,461.00; and,
THAT, a copy of the caption of this Resolution be spread upon the Minutes of the
City Council.
READ, ADOPTED AND APPROVED this the day of , A.D.
2020 at a meeting of the City of Port Arthur, Texas by the following
vote: Ayes: Mayor:
Council members:
PR No. 21376
4/23/20 mje
Page 3 of 3
Noes:
Thurman "Bill" Bartle
Mayor
ATTEST:
Sherri Bellard
City Secretary
APPROVED AS TO FORM: APPROVED FOR ADMINISTRATION:
7ld
Valecia Tizer'(o Ron Burton
City Attorney City Manager
APPROVED AS FOR AVAILABILITY OF
FUNDS:
7..lipa_A__,\_n
Kandy Dani I
Acting Director of Finance
Alberto Elefano, P.E.
Director of Public Works
Clifton Williams, CPPB
Purchasing Manager
EXHIBIT A
A & A ELECTRIC CO. OF BEAUMONT, INC.
6250 WALDEN ROAD
P.O. BOX 22986
BEAUMONT, TEXAS 77720
Phone: 409-842-4437
CHANGE ORDER # 2
Proposal Submitted to: Date: April 23 , 2020
City of Port Arthur Generator Work
ATTN: Ms. Jennifer Edwards
ORIGINAL CONTRACT PRICE: $372,056.00
CHANGE ORDER#1: $ 52,888.00
CHANGE ORDER#2: $ 6,517.00
NEW CONTRACT AMOUNT: $431,461.00
SCOPE: We hereby submit specifications and estimates for. Implementing changes to Entergy High Voltage
Vault as directed by Entergy Representative.
1-Labor and material charges to relocate and modify feeders in Entergy High $ 6,517.00
Voltage Vault, as directed by Entergy Reprsentative.
� I
TOTAL CHANGE ORDER#2 $6,517.00
ORIGINAL CONTRACT TIME: 28 Calendar Days
CURRENT DATE OF COMPLETION: May 13 ,2020
CONTRACT TIME due to CHANGE ORDER: 5 Days
NEW DATE OF COMPLETION: May 18 ,2020
Lee Acevedo,Jr. a
A&A Electric Company of Beaumont Date of Acceptance
Accepted by:
City of Port Arthur Date of Acceptance