HomeMy WebLinkAboutPR 14628: K-T CONSTRUCTION - DEMOLITION CONTRACT (GROUP B-t)City of Port Arthur
Community Services -
Demolition Division
Memo
To: Steve Fitzgibbons, Ciry Manager
From: Lawrence Baker, Director of Community Services
Date: March 18, 2008
Re: P. R: N0..14628' -AWARDING A CONTRACT. TO K-T CONSTRUCTION, LLC
FQR? THE: DEMOLITION OF FIVE: (5) DANGEROUS RESIDENTIAL
STRUCT-URES;(GRO.UP~B;t) LOCATED THROUGHOUT THE CITY [SSB:G]
COMMENT
RECOMMENDATION:. Staffi recommends that the City Council adopt P. R. No. 14628
autborizing.the.Ciry Manager to execute a contract with K-T Construction: LLC in the amount of
$14.700.00! fon the demolition and' removal of five (5) dangerous residential structures located
throughout the City.
BACKGROUND: Bids for demolition of fifty-one (~l) residential structures were opened on
March 12„ 2008: K T Construction LLC is the low bidder for Group B-t• their bid is
$14,700 00 to be completed within thirteen (13j working days from the date they receive a
Notice to Ptoceed. Bid award is based on the most responsive bid. Staxco Solunons, LLC
submitted an incomplete bid; and Lark Group, Inc. bid $2.4,900.00 (10 days). The bid tabulation
follows:
CONTRACTOR GROUP B-t
Staxco Solutions, LLC, Beaumont, T~ No Bid
*K-T Construction, LLC, Beaumont, TX $1'4,700.00
K. T. Maintenance; Port Arthur, Tai $24,900.00
'`Successful Bidder
The City followed the procedures of Section 2-28.3 ox the Code of Ordinances fox public works
projects expected to be less than X25,000.00.
BUDGET AND REVENUE IMPACT: Acceptance of this recommendation will not require a
budget amendment. Funding is available in=AccounfNo. 132=1021-514.59-00; Project No. SSBG03.
Structures deemed ineligible for the giant will be charged to other available funding sources.
(CONTINUED)
P R #14628 DEMO CONTRACT K T CONSTRUCTION/DEIGIO' 3-18-08 PAGE 2 OF 2.
STAFF LEVEL IMPACT: Acceptance of this recommendation kill have no effect on current
staffing level. ,
SUMMARY: Staff recommends that the Ciry Council adopt P. R. No. 14628, thereby authorizing
the execution of a demolition contract between the Ciry of Port Arthur and K-T Construction,
LLC in the amount of $14 700.00..
DTP
STRUCTURES TO BE DEMOLISHED:
GROUP-B=ek (5) TYPE OF. STRUCTURE S
311319`'"Street' Gara e A artment
342&Thomas_Boulevard~ Rear Residence
11916&.1145: efferson Drive 2 Residences/Gara e
1201 efferson..Drive Residence/Colla sed Gara e
271T5'h'Avenue_ Residence/Attached Gara e
P. R. No. 14628
03/18/08 DTP-
RESOLUTION>NO.
A RESOLUTION AWARDING A CONTRACT TO KK=T
CONSTRUCTION, LLC IN. THE AMOUNT OF
$14 700.00, AND AUTHORIZING THE EXECUTION OF
A CONTRACT FOR THE DEMOLITION.OF FIVE (5)
DANGEROUS RESIDENTIAL PROPERTIES (GROUP
B-t), TO BE CHARGED TO ACCOUNT NO. ]32-1021-
514.59=00; PROJECT NO. SSBG03;. STRUCTURES
INELIGIBLE.FOR THE GRANT WILL BE CHARGED
TO OTHER AVAILABLE FUNDING SOURCES.
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PORT ARTHUR:
THAT: the City Council ofthe City of Port Arthur hereby awards a contract for-the demolition of
five- (5) dangerous residential properties-in the City of Port Arthur,. to the best and lowest responsible bidder to-
wifrK-T"Construction,-LLC: and;:,.
THATthe-City Manager of the City of PortArthur is Hereby authorized and directed to execute on
behalf of:the-City of P.orrArthur an agreement between the City of PortArthur and K-T Construction, LLC,
for the contract price of $14,700.00 (a copy of said contract is attached hereto as Exhibit "A"); and,
THAT since K-T Construction; LLC may be awarded more than one group; the company must
successfully and timely complete one group before a new group is started; and,
THAT said contract is a duplicate of the standard form Contract pxeviouslp approved by the City's
Legal Department except for the changes shown on the Certificate of Standazd Foan Contract, a copy of which is
attached hereto and is hereby incorporated by reference as Exhibit `B"; and-said changes axe hereby approved;
and,
THAT a copy of the caption of this Resolution be spread upon the Minutes ofahe City Council.
READ, ADOPTED, AND APPROVED this the 25a' day of March. A.D., 2008, at a Regular
Meeting' of the City Council of the City of Port Arthur, Texas by the following. vote:
P. R. No. 14628
03%18/08 DTP
AYES: MAYOR: ~Councilmembexs:
MAYOR
ATTEST:
CITY SECRETARY
APPROVED AS TO FORM:
~~ ~~~"'_
CITY ATTORNEY
APPROVED FOR'ADMINISTRATION:
CITY MANAGER
APPROVED AS TO AVAILABILITY OF FUNDS:
DIRECTOR OF FINANCE
5
l~
DIREC R OF COMMUNITY SERVICES
2
EXHIBIT "A"
DEMOLITION CONTRACT
CITY OF PORT ARTHUR
THE STATE OF TEXAS
COUNTY OF JEFFERSON
THIS AGREEMENT is made and entered into this 25`h day of March, 2008,,, by and
between the. City of Port Arthur, hereinafter called the "CITY", and K-T Construction,
LLC, hereinafter called' the: "CONTRACTOR", in consideration of the mutual
agreementscontained herein and'for a total sum of Fourteen thousand, seveu•hundred
dollars and:. no cents. ($14,700:001; we do hereby agree, to. all terms, conditions and
specifications-contained herein•.and attached hereto;- and we<do hereby declare. VALID
this~AGREEMENT and:CONTRACT:
WITNESSETH:
SECTION~I
TIIE CONTRACTOR SHALL:
A. Furnish, all labor, materials, tools, machinery, qualified supervision and. all other
items: and services necessary for. satisfactory completion of specifications and
agreements contained herein for demolition of structures and cleanup at the
property .described as Group B-t, described in the attached bid sheets.
B. Start the herein. specified work within 5.~ days from the date that the
CONTRACTOR receives a "Notice to Proceed" from the City of Port Arthur, and
further diligently pursue same until satisfactorily completed on or before thirteen
(13) working days, time being of the essence. It is further understood that if the
contract is not completed by the foregoing completion date, (or-the said date as
extended pursuant to provisions of this contract), the CONTRACTOR shall be
assessed liquidated. damages of twenty-five dollars ($25) per day for. each day the
contract is not completed.after said date. Al1.Contractors are required to have: a
Landfill Permit, which includes a minimum escrow. account of five hundred dollars
($500). If you opt not to set up an escrow account; you must pay as you .dispose
by cash or cashier's check.
C. Perform all work in accordance with the terms of this AGREEMENT and the
DEMOLITION SPECIFICATIONS attached heretoa.
EXHIBIT "A"'
D. Be responsible for obtaining: all: necessary, and general and.special permits and pay
any and all fees for said permits and any other fees, public or private; which may
be required by the United States, the State. of Texas, .Jefferson County, or the City
of Port Arthur, to satisfactorily complete the work as specified and agreed to
herein.
E. Furnish certificates of insurance to the City's Purchasing Agent evidencing that
the CONTRACTOR has obtained Workman's Compensation, General Liability
and Automobile Liability Insurance, which is required by the CITY for
performance of.the_work.specified here. Minimum amounts of such insurance to
be obtained by the CONTRACTOR are as follows:
1.. Statutory Texas- Workman's Compensation. Insurance (with waiver of
subrogation in:favon of the City, its officers, employees. and-agents.
2... Commercialz General' Liability occurrence type insurance (products/
completed9 operations coverage °must be included; and the City and its
officers;.employees, and agents must be named as an additional insured):
a:> General Aggregate $500,000
b: Products-Comp/Ops Aggregate $500,000
c: Personal & Advertising Injury $500,000
dr Each Occurrence. $500,000
e:.Fire:Damage. $ :50,000
3. Commercial Automobile Liability (including owned, non-owned, and hired
vehicles coverage).
a. Bodily Injury (per person)
b. Bodily Injury_(per.accident)
c. Property.Damage
$300,000
$500,000
$100,000
4. Contractor Surety Bond
$ 5,000
F. Furnish to the Purchasing Agent, City of Port Arthur, prior to commencing work,
certificates of insurance meeting the above. listed- insurance requirements for any
sub-contractors, .haulers, or independent workmen used by the CONTRACTOR in
performance of the work specified herein.
G. Ensure that competent and•qualified supervision: is present on the~job site'at all
times while work. is in progress andahat alb demolition work is pursued in such a
manner as to maximize the safety of all workmen;'the general public .and
surrounding property.
z
EXHIBIT °A^
H. Comply with the Cidil Rights Act of ~ 1964 and Section:109 of the Housing and
Community Development Act of 1974, to wit: No person in the United States
shall, on the ground of race, color, national: origin;, or sex be excluded from
participation in, be denied the.benefts of, or.be subjected to discrimination under
any program or activity funded in whole or part with funds made available under
this title.
SECTION II.
THE CITY SHALL:
A. Inspeetthe.demolition work in progress to ensurexhat such work:is being.carried
out im accordance °with the terms of this AGREEIvIENT and'the DEMOLITION
SP.ECIEIC?,TIONS: attached hereto.
B" Compensateahe CONTRACTOR according. to the following method: Except as
hereinafter;provided, paymenYfor the Demolition Contract wilLbe made.in a lump
sum~:after. completion and-acceptance of the contract work. One progress payment
may. bee requested when at least fifty percent (50%) of the contract work is
completed:. Ten percent (10%) of the progress payment will be retained. This
retainagetwill.be held in escrow by the City for a maximum of thirty (30) days
after.• satisfactory completion and acceptance of the Contract to guarantee the
completion;.ofwoi•k. Thirty (30) days after said completion and acceptance, final
paymentshall: be:made in a lump sum or total agreed price less the;progress
payment, ifmade, by check issued by the City of Port Arthur and.made payable to
the CONTRACTOR for the satisfactory completion of the work, described herein.
Any payments are ubjectio satisfactory intermediate and final inspections by the
City. Further, an applicable .request for payment must be made by the
CONTRACTOR prior to each payment.
SECTION III
General Conditions:
A. If performance by the CONTRACTOR is prevented or delayed as a direct result of
acts of a public enemy, acts of the property owner, fire; epidemics, or acts of God,
such as floods, earthquakes, hurricanes, tornadoes and rain; an extension.of one (1)
working day of additional time will be allowed~to the.=CONTRACTOR for each
working day lost from such cause;.provided-the-CON,TRACTOR,.within three (3).
days after the beginning of such delay, gives written notice to the City.
3
EXHIBIT "A"
B. If for any reason; other than those specified. above, the CONTRACTOR at any
time fails for a period of five (5) consecutive working.. days to supply enough
skilled workers or otherwise. neglects to execute the work properly, the CITY,
after these five (5) working days may give written notice to the CONTRACTOR
terminating his contract. ,
C. The CONTRACTOR shall repair or replace, . if necessary, to the .City's
satisfaction, any damage to the work site,:the adjacent areas,,the access, areas to
the work site and to any elements within these_ areas that may have suffered
damage as a result of the CONTRACTOR'S or any of the subcontractor's.
operations, The CONTRACTOR shall leave these areas in a satisfactory and
workmanlike condition, at least equal to that existing. before the CONTRACTOR
hereunder started his work.
D. Ttie CONTRACTOR' agrees to indemnify and. hold harmless the City of Port
Artliur,_Texas~from any'and.all claims, and damages of any and every kind for
injury. toy or deaths of; any person, and.. damages: to .property arising out. of the
demolition.
E. Any amendmentsao this contract shall be written and must be executed by both
the: CITY- and" the. CONTRACTOR prior to the implementation of any such
change:
F. This CONTRACT and AGREEMENT embodies and represents all of the rights,
duties and. obligations: of the CITY and the CONTRACTOR and any oral or
written agreements-prior to the date first above.written, not included;or embodied
herein shall be declazed void. and not be binding.or of benefit to any of the parties
herein mentioned.
SECTION IV
Particular Requirements:
A. Other pazticulaz work requirements are contained in the DEMOLITION
SPECIFICATIONS, which are attached hereto and made a part hereof as Exhibit
~.A_ 1„
B. ALL DEMOLITION BIDS SHALL INCLUDE REMOVAL OF CONCRETE.
SLABS, PORCHES, STEPS, ETC., UNLESS OTHERWISE".NOTED.
4
EXHIBIT "A"
SECTION V '
If the CONTRACTOR materially defaults in (a) failing to have liability insurance; (b) not
completing the CONTRACT within the time required, or (c) uses demolition pr-ocedures
that are dangerous to the health and safety of residents and/or adjoining:: residents, the
Director of Community Services has the authority to issue a -cease and desist order until
this matter can be reviewed by the City Council.
SIGNED'A1VD''AGREED`TOahis ;day
K=T: CONSTRUCTIONI,LC
WITNESSEDr
A.D: 2008:.
SIGNED'AND'AGREED TO thi§~ day of ,_A:D: 2008:
CITY OF PORT~ARTHUR
BY CITY MANAGER
WITNESSED
s
EAIltU11 ~A-tH
DEMOLITION SPECIFICATIONS
CITY. OF PORT ARTHURr
I. -TITLE
The provisions embraced within thesesections.and subsections shall constitute; be known as;
and will be referred to herein and in any relevant AGREEMENT and CONTRACT as
"DEMOLITION SPECIFICATIONS".
II. SCOPE
The scope and purposes of theses specifications- is to establish certain regulations, general
requirements, and particulaz requirements necessary for the demolition, removal and cleanup of
the unsafe.and/or unsanitary structure(s) as required by the Inspections Department of the City of
Port Arthur.
IIL. CONTRACTOR BIDS-
Contracts for the--demolition~of structures will 6e~awarded in accordance with: the terms and
conditions-listed in the: Community Services Department's BID FORM FOR DEMOLITION.
The. completion: of the.demolition.package will be of vital importance to the City. The number of
calendaz days given on the proposal form will be used_to establish the completion date as used in
the Contract. In case the work is not completed within the time specified in the Contract, there
shall beaiquidated. damages of twenty-five dollazs ($25) per day for each day exceeding the
completion date.
IV. INSURANCE REQUIREMENTS
A.. The Contractor shall, upon submission of bid, famish the City with certificates of
insurance, indicating_ the.. existence of Statutory Workman's Compensation .Insurance,
' General and Auto Liability, Public Liability, and Property Damage Insurance. Such
insurance. must be issued by a company authorized to do business in the State of Texas.
Such a certificate must contain. a provision requiring not less than fifreen (15) days prior
notice in writing to the. City of any' change or termination of said insurance. All
insurance is to remain in force until the job of clearing the premises has been completed
and the work has been accepted by the City.
B. The Contractor/Successful Bidder must obtain and famish to the City proof of insurance
in the following minimum amounts:
1. Statutory Texas Workman's Compensation Insurance;
2. Commercial General Liability
a. General Aggregate $500,000
b. Products-Comp/Ops Aggregate $500,000
c. Personal & Advertising Injury $500,000
d. Each Occurrence $500,000
1
EXHIBIT "A-1"
e. Fire Damage $ 50,000
3. Automobile Liability
a. Bodily Irijury (per person) $300,000
b. Bodily Injury (per accident) $500,000
c. Property Damage $100,000
4. Contractor Surety Bond $ 5,000
V. PERtVIITS
The Contractor/Successful Bidder must obtain= from the City of Port Arthur and., all other
governmental entities;.at his own expense, all necessazy generaPand special permits and pay any
and all fees_forsaid.permits and any other fees, public or private.
All Contractorsare requiredao have~a Landfdl Permit, which: includes a minimumescrow.:
account of fiverhundred.:dollars•($500).. If=you opt noY to set up an escrow account, you.
must,pay;cash or::by cashier's checkers you:.dispose.
VL,. . GENERAL..CONDITIONS`AND REQUIREMENTS
The: following,.list:of conditions and requirements are to be understood as being a general guide
in the demolition-ofstructures. It-must be noted; however, that there are special requirements
listed below. ineSeetion VII of these specifications, which are in addition to these general
requirements for demolition, and that it is the responsibility of the Contractor/Successful Bidder
to. comply,with all particular requirements.
A. It is understood and agreed that. the; Contractor/Successful Bidder will function and
operate as.an independent contractor. Any liability incurred by the Contractor/Successful
Bidder will accme only to that party as an independent contractor and not to the City of
Port Arthur.
B. No work under a City DEMOLITION CONTRACT shall be subcontracted, by the
Contractor/Successful Bidder without prior, written approval of the Community
Services Department. No subcontractor will be approved unless that subcontractor meets
the same insurance requirements specified for and required of the Contractor.
C. The demolition work specifiedherein shall be performed in a safe, satisfactory condition;
starting with the roof and:working.down, with the safety and;.welfaze of all people. and
property being of the highest priority.
D. All materials, debris, and rubble from the demolition of the structure(s) specified-herein
will become the property of the ContractorlSuccessful.Bidder: Salvage can only begin-
, immediately prior to the beginning of demolition.
E. The Contractor/Successful Bidder will be held responsible for repair of broken or
damaged water, gas, or any other type of lines, which occur during the course of the
demolition work. The Contractor shall repair or replace, if necessary, to the City's
2
EXHIBIT-"A-1"~
satisfaction, any damage to the work site;. the. adjacent azeas, the access areas to the work
site and to any elements within.these.azeas-thatmay have suffered: damage as-a;result of
the Contractor's or any.,of the:subcontraetor?s•operations: The-Contractor shall: leave
these azeas in a satisfactory condition.
F. The Contractor/Successful Bidder shall haul off all debris.and unsalvageable_materials;
and no debris or rubble which may pose a threat to public safety will be left on the site
overnight. No such debris or material will be placed. on a sidewalk or public right.of--way
so thatit poses a danger to any person.
G. All demolition work must. be can•ied out to the satisfaction of the City's Inspections
Official.
H. The City (without prejudice•to any other right or remedyitmay have) has the rightto.
terminate the contract in the event of any default by the. Contractor after giving the
Contractor. seven (7) days written notice. Such notice of ierrnination shall be subsequent
to default by the Contractor•and; after receiving written notice from the City certifying
cause: fon such action. In addition to other events of default or grounds for ternlination
identified:inahe:contract; it-shall be considered default by.the Contractor whenever he/she
shall`. _
Declaze bankruptcy, become insolvent, or.assign his/her assets for the benefit of
his/hercreditors.
2: Violate or disregazd provisions of the Contract or instruction from the Owner.
3. Fail to prosecute the work according to the agreed Schedule of Completion,
including amendments and/or modifications thereof.
4. Fail to provide a qualified superintendent, competent workmen or subcontractors,
orproper materials, or failure to make prompt payment therefor.
L If the Contract is terminated..-as provided above or as provided in the Contract, the. City
will engage another contractor to complete the work. Payment for the.completion of such
work will come .from funds: obligated by the City under its contract with the original
Contractor.
METHOD OR PAYMENT-
Payment shall be made as provided in Section II of the.contract.
K. PAYMENT WITHHELD
Any part or the whole of any payment may be withheld by the-City to the extent deemed
necessary and reasonable should evidence of the..foldowing be discovered:
Defective work not corrected.
2. Claims filed against the Contractor.
EXHIBIT "A-1"
Reasonable evidence indicating the probability of filing, claims- against the.
Contractor.
4. Failure of the Contractor to make proper payments to subcontractors or for
materials or for labor.
5. The contract cannot be completed for the then unpaid balance.
6. Unsatisfactory progress of the work by the Contractor.
When the above grounds are removed, the amount withheld because_ofthem shall be paid to the
Contractor subject to and within tfie other tenns•of this contract:.
L. CONTRACT PAYMENT~RETAINAGE
Contract payment retainageshall be asprovided in the Contract:
VIL. AARTICUL"AR~~WORK:REQUIREMENTS~
The.following.particular.work..requirements and conditions apply specifically to the.building(s)
or structure(s) which azeaocated-atand described as:
GROUPB=tt - 5 TYPE OE STRUCTURES
31]3~19`s'S"treet* Gara eA artment
3428 Tfiomas-.Boulevard Rear Residence
1141'&:1145° efferson Drive 2 Residences/Gara e
120T efferson Drive Residence/Colla sed Gara e
2717'5.'' Avenue Residence/Attached Gara e
A. Before any building or structure is demolished, its utilities shall be safely disconnected.
The Contractor-shall serve notice to all suppliers of~utilities to the building:: to be
demolished and have them disconnect the services•andremove-all meters and equipment
belonging to them. Forty-eight (48) hours' written notice must be given the City for
termination of their utilities. All piping and wiring. shall be properly terminated. Any
costs incurred in the termination of utilities and services shall be borne by the Contractor.
B. Demolition and clean-up includes, but is not limited,to, the removal of all hunber, doors,
windows, wire, sheet metal, appliances, furniture, loose rock, brick, mortaz, concrete, and
the cleaning and removal of all rubbish, trash or other debris that would inhibit or prevent
the mechanical mowing of said lot and premises.
C. Fill, grade and level with clean. fill dirt all depressions in the: earth which exist beneath
demolished building(s) or structure(s) and ald ruts or other depressions created during. the
demolition work when the average:depth of such depressions exceeds,three: (3) inches.
D. Any trees and shrubs designated by the- Community Services Department will be cut
down and removed from the premises.
EXHIBIT "A-1"
E. The grass at the demolition sitershall be mowed to a height.not exceeding two (2) inches.
F. All sewer lines exposed through demolition work must be cut off within two (2) inches of
the surface to the ground or concrete slab and must be plugged with concrete in such a
manner as to prevent ground water. incursion. into the City's sanitary sewer system.
G. REMOVAL OF STEPS- AND CONCRETE PORCHES UNLESS OTHERWISE
NOTED.
H. HAZARDOUS MATERIALS
Materials defined by the. Environmental Protection Agency to be hazardous to the
environment or persons, shall be disposed of in accordance. with all-local,:.state and
federal government regulations and governing' laws. This shall be the responsibility of
the~Contractor: The~Contractor shall furnish written proof ofsuch disposal.
I. BOND RE.QUIRENIENTS-
If. the; amount bid~on. the: contract exceeds $25,000,, the Contractor will be required to
furnish~aPerformance,Bond and a Labor and Material Payment Bond in the amount of
$1.00% of the_Contract:on forms furnished by the City.
5
P.R. # 14628
Exhibit"B"
(City of Port Arthur) ~ ~
(Iaw Department)
(Required Eorm) - .~
(07108188) -
(10/05189) ,
(03/15190) -
(p. 2 Rerdsed 09/18190)
CERTIFICATE OF STANDARD FORM.CONTRACT FOR LAW
DEPARTMENT REVIEW AND CITY COUNCIL AGENDA
I certify that the contract (hereinafter called "said contract") affixed to the attached proposed City Council
Resolution No. 14628 is an exact duplicate of an applicable standard form contract (the tide of which is
shown below) previously approved by the-Law Department and adopted as a. standard form by City Council
Resolution, except for the blanks [hat have:been filled in with all necessary information and except for the changes
described below.
The-title of the applicable standazd;form contract is:
[ ] . Federally Funded.Construc[ion Contract, Revised 01/05/88,` 07/89, 08189
[ ] Non-Federally Funded:Construction Contract, Revised.01/05/88; 07/89r 08/89
[ ] Federal -Professional Services -Engineering Contract, Revised 01/05/88; 05/89, 07/89, 04/91
[ ]~ Non-Fe`decal.,--ProfessionaL.Services -Engineering: Contrac[,.Revised.01/05/88, 05/89(§10),
07!89(§8).
[..] a CDBG_ Professional Services -Engineering Contract, Revised.01/05/88; 05/89,§ 07/89§
[. ] Federal. -Professional Services -Non-Engineering (Consultant) contract, Revised 01/05/88,
05189(§10); 07/89(§8)
[+]' Non-Federal.- Professional Services -Non-Engineering (Consultant) Contract Revised 01/05/88,
OS/89 (§10), 07/89(§8)
[ ], CDBG -Professional. Services -Non-Engineering.(Consultant) Contract, Revised 01/05/88,
05/89(§10), 07/89(§8)
[X] Other Standard Form Contract, described as follows:
CDBG Demolition Contract-
The changes aze as follows: (Put an."X" in the.appropriate [ ]).
[X] None.
[ ] The following described provisions a[ the indicated page, section, etc. of the standard form have been
deleted from said contract:
DELETIONS
Page Number
Where Deleted
Provision is
Found On
Provision
Standard Form
Section or
Paragraph No.
and Caption
Which Contains
Provision Deleted
From Form
Section or
Subpazagraph No.
and Caption
Which Contains
Provision Deleted
From Form
Description of
Deleted
1
P.R. H14628
Exhibit "B"
[ ] The following described provisions at. the indicated page, section, etc. of the
standard form have been altered, modified, replaced or otherwise changed:
ALTERATIONS; MODIFICATIONS, REPLACEMENTS, ETC.
Sub § or Page, § & caption;
Page No.
§ or § No. Sub § No. sub § & caption,
of said contract
etc
Where & Caption of
Standazd & Caption.
of Standazd. .
which contains
Description
Provision
Fotmd On .
Fdrm which:
form which altered, etc. rovision; &
of Provision Descri tion of Alteration:
P
Standard Contains Contains in Standazd
Fotm Provision-
Provision
Form etc.
[+] Ttie:fdllowing:provisions:havebeenadded.toSaidContract:
ADDITIONS
Page, Section and Caption Subsection and
Caption; etc. of said Contract Which
Contains the Added Provision and.
Descrintion Thereof
I further certify that said attached proposed City Council Resolution contains the following provision: "That said
contract is an exact duplicate of a City Standazd.Form Contracrexcept for the.changes described in the Certificate of
Standard Form Contract, a copy of which isattached hereto as Exhibit "B" and is.hereby incorporated by reference,
and said changes are hereby approved."
I understand that this certificate will be relied on by the Law Department in reviewing.and approving (or rejecting) as
to form and by the City Council in reviewing and adopting (or rejecting) said Resolution and Contract:
Signed this 18" day of March, 2008.
Lawrence~aker
Director of Community Services