HomeMy WebLinkAbout(3 & 4) Street 1st and 2ndCity of Port Arthur
Streets Program Update
1
Round 1
District 1 (Completed) Streets
Nashville Street
Bluebonnet
Woodworth
W. 7th Ransom Howard
W. 8th Street
Lakeshore Phase 1
12th Street
24th Street
9th Street
Marshall
El Paso 3rd Ave.
5th Ave.
2
Round 1
District 2 (Completed) Streets
15th Street
Carolina Ave
8th Street
5th Street
6th Street
Procter Street Extension
3
Round 1
District 3 (Completed) Streets
38th Street
Forest Dr.
42nd Street
Evergreen Dr.
3rd Ave.
Memorial Blvd (Feeder)
9th Ave.
4
Round 1
District 4 (Completed) Streets
Viterbo Road
Willow Ave (Pending Close-out)
60th Street (Pending Close-out)
Cedar Street
64th Street
58th Street
Pine Ave
Sharon Drive
Waco Ave
Lakeside Plaza
Beaumont Ave.
5
District 2 and 3 (On-Going) Streets
Lakeshore Drive (Phase 3 and 4) Contracted May 21, 2021 (Completion)
Forest Drive (Contracted) January 19, 2021 (Complete)
8th Ave (Final Stages) Contracted August 31, 2020 (Complete)
Sunken Court (Phase 1 and 2) Contracted October 2, 2020 (Complete)
6
2nd Round Streets
District 2 (Procter Ext. Feeder to Atlantic) Complete
District 2 (16th Street) Complete
District 4 (Lakeside) Complete
District 4 (Cashmere) Ongoing
District 1 and 4 (Atlanta) Ongoing
7
Next for 2nd Round
District 3 Brazos, 76th and 77th
District 1 and 4 (Shreveport)
District 3 and 1 Design Engineers will be procured for 9th Ave. Project.
We have 32 more 2nd Round of Streets that have been identified for completion for fiscal year 20-21. By this time next year I anticipate to have a bulk of the streets complete.
8
City of Port Arthur
Drainage Update
9
Drainage Projects (HMGP and CDBG Funded)
The Hazard Mitigation Grant Program and Community Development Block Grant Projects are:
El Vista Drainage Improvements
Port Acres Drainage Improvements
Lake Arthur Detention
Babe Zaharias Golf Course
10
El Vista Drainage
30% Design is complete
60% Design is due 9/1/2020
90% Design is due 10/1/2020
100% Design is due 10/20/2020
Phase II of obligation is Construction and is due before Jan. 2021
Construction Completion is due before Dec. 2021
11
Port Acres Drainage
30% Design is Complete
60% Design is due 9/15/2020
90% Design is due 11/1/2020
100% Design is due 11/14/2020
Phase II obligation is Construction and is due before Feb. 2021.
Construction Completion is due before April 2022
12
Lake Arthur Detention
30% is complete
60% is due 10/1/2020
90% is due 11/15/2020
100% is due 12/2/2020
Phase II obligation is Construction and is due before 3/2021
Construction Completion is due before May 2022
13
Babe Zaharias Golf Course
30% is complete
60% is due 10/1/2020
90% is due 11/15/2020
100 is due 12/2/2020
Phase II obligation is Construction and is due before 3/2021
Construction Completion is due before May 2022
14
Questions
15