HomeMy WebLinkAboutPR 21649: CHANGE ORDER NO. 2 MCINNIS CONSTRUCTON, INC. Memorandum
City of Port Arthur, Texas
Robert A. `Bob"Bowers Civic Center
To: The Honorable Mayor and City Council
Through: Ron Burton,City Manager
From: Adam J Saunders,Civic Center Dir
RE: Proposed Resolution No.P.R. 21649
REQUEST:
The Department Club at 1924 Lakeshore Drive is in need of repair and maintenance. In March, 2019 the
Council passed Res 19-108 and in December, 2019 the Council passed Res 19-560. These two
Resolutions were for Architectural fees and Asbestos, lead and mold abatement. These activities are
Phase I of the repairs and maintenance. At the June 9, 2020 Council Meeting, City Council approved PR
21411 for Phase II of the repairs and maintenance.
Due to evacuation for Hurricane Laura, as well as some additional work due to discovered rotten wood,
there would need to be a change order for additional days to be added to the Contract Time. The day to
be added to Change Order#2 is a total of eight days. There is not change to the cost of the agreement.
ANALYSIS/CONSIDERATION:
There are a lot of needed repairs at the building. Phase I has been performed. Phase II is the next step in
the repairs and restoration of the Department Club. Change Order#2 to the Phase II repairs is needed due
to days evacuated for Hurricane Laura and work days added to repair discovered rotten wood.
RECOMMENDATION
A resolution authorizing the City Manager to enter into an agreement with McInnis Construction,Inc. of
Silsbee for Change Order#2 to Phase II repairs and maintenance of the Department Club in the amount of
eight days added to the Contract Time.
BUDGETARY AND FISCAL EFFECT
None
STAFFING EFFECT
None
PO 21649
P.R. No. 21649
07/08/2020 AJS
PAGE 1 of 3
RESOLUTION NO.
A RESOLUTION AUTHORIZING THE CITY MANAGER TO EXECUTE
CHANGE ORDER NO. 2 TO THE CONTRACT BETWEEN THE CITY
OF PORT ARTHUR AND MCINNIS CONSTRUCTION, INC. OF
SILSBEE, TEXAS FOR PHASE II REPAIRS TO THE DEPARTMENT
CLUB THAT INCREASES THE CONTRACT TERM BY EIGHT DAYS
TO A NEW COMPLETION DATE OF NOVEMBER 18, 2020 AT NO
ADDITIONAL COST.
WHEREAS, the City Council approved Resolution No. 20-191 at the June 9, 2020
Council Meeting, an agreement with McInnis Construction of Silsbee, Texas for Phase II repairs
to the Department Club in the amount of$224,000.00; and
WHEREAS, the City Council approved Change Order No. 1 pursuant to Resolution No.
20-227 at the July 21, 2020 Council Meeting, increasing the contract amount by $7,370.00; and
WHEREAS, it has been determined that additional days added to the contract term is
needed due to evacuation for Hurricane Laura and additional days to repair discovered rotten
wood; and
WHEREAS, McInnis Construction, Inc. of Silsbee, Texas has submitted Change Order
No. 2 for an additional eight days to a new completion date of November 18, 2020; and
WHEREAS, approval of Change Order No. 02 is deemed an appropriate action.
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE
CITY OF PORT ARTHUR:
Section 1. That the facts and opinions in the preamble are true and correct.
Section 2. That, the City Manager is hereby authorized to execute Change Order No.
2 with McInnis Construction, Inc of Silsbee, Texas for Phase II repairs at the Department Club, in
substantially the same form as attached hereto as Exhibit"A".
Pr21649
Section 3. That, a copy of the caption of this Resolution be spread upon the Minutes
of the City Council.
READ, ADOPTED, AND APPROVED, this day of November, 2020, A.D., at a
Regular Meeting of the City Council of the City of Port Arthur, Texas by the following vote:
AYES:
Mayor:
Councilmembers:
NOES:
Thurman"Bill"Bartie, Mayor
ATTEST:
Sherri Bellard, City Secretary
APPROVED AS TO FORM:
Valecia T'zeno, City Attorney
APPROVED FOR ADMINISTRATION:
Ronald Burton, City Manager
Pr21649
APPROVED AS TO FUND AVAILABILITY:
Kandy Dame Clifton ' illiams, CPPB
Interim Director of Finance Purchasing Manager
Adam Saunders
Director of Civic Center
Pr21649
EXHIBIT "A"
CHANGE ORDER
PROJECT: Federated Women's Club CHANGE ORDER NO: 2
CONTRACTOR: McInnis Construction DATE: 10.07.2020
675 South 4th St. ARCHITECT'S PROJECT NO.: 18039
Silsbee, Texas 77656 CONTRACT DATE: 03.31.20
CONTRACT FOR: Renovation
This Contract is changed as follows:
Addition of Contract days for the following
Mandatory Evacuation for Hurricane Laura 2 days $00.00
Additional wood rot replacement, not in scope of work 6 days $00.00
TOTAL: $00.00
**See attached breakdown
Not valid until signed by the Owner, Architect, and Contractor.
The original Contract Sum was $224,000.00
Net change by previously authorized Change Orders $7,370.00
The Contract Sum prior to this Change Order was $231,370.00
The Contract sum will be increased by this Change Order in the amount of $00.00
The new Contract Sum including this Change Order will be $231,370.00
The Contract Time will be increased by Eight(8)days.
The date of Substantial Completion as of the date of this Change Order therefore is November 18, 2020.
NOTE: The summary does not reflect changes in the Contract Sum or Contract Time which have been authorized by
Construction Change Directive.
The LaBiche Architectural Group McInnis Construction, Inc. City of Port Arthur
7999 Gladys Avenue, Suite 101 675 South 4th Street 3401 Culture Ctr. Dr.
Beaumont, e s 7 06 Silsbee, Texas 77656 Port Arthur, Texas 77642
By: By: By:
Date: _D-,a-i- Date: \,� i n ,-)7X) Date:
/% Z° 4 _ti -. ` LV
(---.L,
yti
({.?.,,,,,,, 11592 _='P
Ammormiciammik
�rwMrw1111l
Change Order `: MCINNIS CONSTRUCTION, INC.
PROJECT: CHANGE ORDER NUMBER:
Port Arthur Federated Womans Club OWNER
1924 Lakeshore Dr DATE: 10/6/2020 ARCHITECT
Port Arthur TX
ARCHITECT'S PROJECT NO: CONTRACTOR
CI
Labiche Architectural Group
TO CONTRACTOR: Project#18039 FIELD ❑
McInnis Construction INC
675 S 4th St CONTRACT DATE: OTHER 0
Silsbee Tx
CONTRACT FOR: City of Port Arthur
The Contract is changed as follows:
Addtion of Contract days for the following
Mandatory Evacuation for Hurricane Laura 2 days
Additional wood rot replacement,not in scope of work 6 days
No cost increase
The original Contract Sum was $ $224,500.00
The net change by previously authorized Change Orders $ $7,370.00
The Contract Sum prior to this Change Order was S $231,870.00
The Contract Sum will be unchanged by this Change Order in
the amount of $ $0.00
The new Contract Sum including this Change Order will be $ $231,870.00
The Contract Time will be increased by 8 ( )days
The date of Substantial Completion as of the date of this Change Order therefore is 11/18/2020
NOT VALID UNTIL SIGNED BY THE ARCHITECT,CONTRACTOR AND OWNER.
McInnis Construction
ARCHITECT(Firm name) CONTRACTOR(Firm name) OWNER(Firm name)
675 S 4th St Silsbee TX
ADDRESS ADDRESS ADDRESS
BY(Signature) BY(Signature) BY(Signature)
Kyle Kelley
Typed name Typed name Typed name
DATE DATE DATE