HomeMy WebLinkAboutPROPOSED STREETS/DRAINAGE BOND PROJECTSCITY OF PORT ARTHUR Public Works Department MEMORANDUM pp TO: Stephen Fitzgibbons, City Manager q /J ~it~~' FROM: John A. Comeaux, P.E., Director of Public Works /~.~, DATE: 29 April 2008 '~V _ RE: Streets Bond Projects The projects we are recommending for the streets bonds will consist of projects outside the ist of reconstruction or resurfacing by both ill cons scope of the normal streets program and w The recommended projects are as follows: City crews and contractors. Procter Street from 9"' Avenue to Stadium Road $287,500 (milling, concrete repair, HMAC) Stadium Road from Lewis Drive to the south dead end $138,000 (milling,-concrete repair, HMAC) S. i~t Avenue from the north dead end to the Texas Bayou bridge 475,200 $ (HMAC for industrial traffic). $546,350 Jade Avenue from ST 73 to FM .365 (milling and HMAC) Lewis Drive from Stadium Road to 9th Avenue $ 312,100 (milling, concrete repair, HMAC) hnson Boulevard from US 69 to SH 347 J i $210,000 o mmv J (concrete repairs) $145,000 Gilham Circle (milling, concrete repair, HMAC) Thomas Boulevard from Woodworth Boulevard to 9"' Avenue $255,500 (milling, concrete repair, HMAC) 90`" Street from US 69 to SETX Airport property -City share 55,000 $ (reconstruct as concrete roadway) $ 55,000 Old Yacht Club Road -last 1,000 feet (HMAC for industrial traffic) $200,000 Anchor Drive Extension -City share of infrastructure (construct new concrete roadway) Tallow Woods Sect. 3subdivision -City share of infrastructure 200,000 $ (construct new streets and drainage) Purchase of Newpurchase of Nevv E~uioment $ 60,000 Pothole Patcher $ 60,000 Used Concrete Truck These equipment items will allow for better, more timely repairs and increased capability and cost savings for concrete work. 1 of 2 Z:\engineer\documents\memos\Streets Bond.doc Alternate Projects: $123,300 Austin Avenue from Gulfway Drive to 8`" Street (concrete repair and HMAC overlay) $ 67,100 39`" Street from Memorial Boulevard to 5~' Avenue (concrete repair and HMAC overlay) Please call me if you require further information. cc: Ross E. Blackketter, P. E., City Engineer/Asst. Director of Public Works Paul Brown JAC/reb 2of2 Z:\engineer\documents\memos\Streets Bond.doc ~` CITY OF PORT ARTHUR Public Works Department MEMORANDUM ,,SS i~ .G TO: Stephen Ftzgibbons, City Manager FROM: John A. Comeaux, P.E., Director of Public Works DATE: 23 April 2008 RE: Drainage Bond Projects The projects we are recommending for the drainage bonds are as follows: Procter Street Storm Sewer from Duff Drive to Pecos Avenue $400,000 This project will consist of the construction a storm sewer trunk line as shown in the Tumer, Collie & Braden Master Drainage Plan. The installation of this line will greatly reduce the flooding problem that exists in the Lakeview area. Because of the size of the required pipes, this work will be contracted out. Vista Village Outfall Ditch $250,000 Complete the concrete .lining of the remaining .1,000 feet of the Vista Village outfall ditch. Concrete lining the ditch will reduce the maintenance requirements allowing City assets to be utilized in other areas. This will be done by a contractor. Mauve Outfall Ditch $340,000 Widen the existing outfall ditch from Mauve Avenue to State Highway 73 to improve the drainage in the- Palomar area. This project can be completed by City crews or contractor. 2nd Avenue Storm Sewer from 11"' Street to i2d' Street $ 91,000 Replacing the existing pipes and catch basins with larger drains and inlets to City standards to relieve local flooding conditions. This project will be accomplished by City crews. Lee Avenue Storm Sewer from Delaware Drive to lOd' Street $100,000 Replacing the existing pipes and catch basins with larger drains and inlets to City standards to relieve local flooding conditions. This project will be accomplished by City crews. 5"' Street Storm Sewer from Trinity Avenue to 13"' Avenue ROW $200,000 This project will consist of the construction a storm sewer trunk line as shown in the Tumer, Collie 8c Braden Master Drainage Plan. The installation of this line will greatly reduce the flooding problem that exists in the Lakeview area, and will be by City Crews. Z:\engineer\documents\memos\Drainage Bond.doc loft Rev. Raymond Scott Ave. Storm Sewer from W 19"' Street to Thomas Blvd. $350,000 This project will consist of the construction a storm sewer trunk line to convey stormwater from W. 19"' Street into the existing system south of Gulfway Drive. The installation of this line will greatly reduce the flooding problem that exists in the Westside. This project can be constructed by City crews or by contractor. Purchase of New Track Gradall $250,000 Purchase of this equipment item will allow the construction of the above mentioned projects by City crews. The current machine used for storm sewer construction is a 1993 XL4100 Gradall which is not capable of handling the load of the new construction projects. Please call me if you require further information. cc: Ross E. Blackketter, P. E., qty Engineer/Asst. Director of Public Works Paul Brown JAC/reb Z:\engineer\documents\memos\Drainage Bond.doc 2 of 2