HomeMy WebLinkAboutPR 21687: CHANGE ORDER NUMBER 4 WITH JACKBUILT CONTRACTOR, LLC www.PortArthurTx.gov INTEROFFICE MEMORANDUM Date: November 24, 2020 To: The Honorable Mayor and City Council Through: Ron Burton, City Manager From: Chandra Alpough, Director of Parks and Recreation RE: P.R. 21687—Change Order Number 4 and Approval for Final Payment- Contract with Jack Built Contractor, LLC for Interior Repairs at the Recreation Center Introduction: The intent of this Agenda Item is to request the City Council's approval of P.R. No. 21687 authorizing Change Order Number 4 decreasing the contract amount by $1,300.00 for a new contract amount of$62,662.89 and for approval of the final payment in the amount of$307.78 to the contract between the City of Port Arthur and JackBuilt Contractors, LLC of Orange, Texas for interior repairs at the Recreation Center. Background: On July 7, 2020, pursuant to Resolution No. 20-223, the City Council awarded a contract to JackBuilt Contractors,LLC of Orange, Texas for interior repairs at the Recreation Center in the amount of$62,255.11. On September 15, 2020, pursuant to Resolution No. 20-291, the City Council awarded Change Order Numbers 1,2 and 3 increasing the contract amount by$1,608.18 for a new contract amount of$63,962.89. In the original bid,the equipment in the exercise room was supposed to be moved by JackBuilt Contractors, LLC. The Parks and Recreation staff moved the equipment. JackBuilt Contractors, LLC submitted Change Order Number 4 in the amount of$1,300.00 giving credit for the labor due to departmental staff moving the equipment. The City is satisfied with the work completed by JackBuilt Contractors, LLC and requests the approval for the final payment in the amount of$307.78. Budget Impact: Funding in the amount of $62,662.89 is available for this purpose. ($30,516.54 in the Hurricane Harvey Fund Account Number 147-2300-901.95-00 Project Number PR-001 and $32,146.35 in the Capital Improvement Project Account Number 307-1601-591.95-00 Project Number PR-001). "Remember,we are here to serve the Citizens of Port Arthur" P.O.Box 1089 X Port Arthur,Texas 77641-1089 X 409.983.8182 X FAX 409.983.8294 Recommendation: It is recommended that the City Council approve P.R. No. 21687 authorizing Change Order Number 4 decreasing the contract amount by $1,300.00 for a new contract amount of $62,662.89 and for approval of the final payment in the amount of $307.78 to the contract between the City of Port Arthur and JackBuilt Contractors, LLC of Orange, Texas for interior repairs at the Recreation Center. "Remember,we are here to serve the Citizens of Port Arthur" P.O.Box 1089 X Port Arthur,Texas 77641-1089 X 409.983.8182 X FAX 409.983.8294 w P.R.# 21687 11/24/2020 ca RESOLUTION NO. A RESOLUTION AUTHORIZING THE CITY MANAGER TO EXECUTE CHANGE ORDER NUMBER 4, DECREASING THE CONTRACT AMOUNT BY $1,300.00, FOR A NEW CONTRACT AMOUNT OF $62,662.89 AND FOR APPROVAL OF THE FINAL PAYMENT IN THE AMOUNT OF $307.78 TO THE CONTRACT BETWEEN THE CITY OF PORT ARTHUR AND JACKBUILT CONTRACTORS, LLC OF ORANGE, TEXAS FOR INTERIOR REPAIRS AT THE RECREATION CENTER; ($30,516.54 AVAILABLE IN ACCOUNT NUMBER 147-2300-901.95-00 PROJECT NUMBER PR-001 AND $32,146.35 AVAILABLE IN ACCOUNT NUMBER 307-1601-591.95-00 PROJECT NUMBER PR-001) WHEREAS, on July 7, 2020, pursuant to Resolution No. 20-223, the City Council awarded a contract for interior repairs at the Recreation Center to JackBuilt Contractors, LLC of Orange, Texas in the amount of$62,355.11; and, WHEREAS, on September 15, 2020, pursuant to Resolution No. 20-291, the City Council executed Change Order Numbers 1, 2 and 3 increasing the contract amount by $1,608.18 for a new contract amount of$63,962.89; and, WHEREAS, the equipment in the exercise room was supposed to be moved out of the room by JackBuilt Contractors, LLC but was moved by departmental staff; and, WHEREAS, JackBuilt Contractors, LLC has submitted Change Order Number 4 decreasing the contract amount by $1,300.00 for credit for labor due to departmental staff moving the equipment that was originally supposed to be moved by JackBuilt Contractors, LLC (attached hereto as Exhibit"A") for a new contract amount of$62,662.89; and, WHEREAS, JackBuilt Contractors, LLC has completed the project to the City's satisfaction and has requested approval for final payment in the amount of $307.78 (attached hereto as Exhibit"B"); now, therefore, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PORT ARTHUR TEXAS: P.R.#21687 11/24/2020 ca Section 1. THAT the facts and opinions in the preamble are true and correct. Section 2. THAT the City Manager of the City of Port Arthur is hereby authorized and directed to execute, on behalf of the City of Port Arthur, Change Order Number 4 decreasing the contract amount by $1,300.00 for credit for labor to move equipment that was moved by departmental staff that was originally supposed to be moved by JackBuilt Contractors, LLC (attached hereto as Exhibit "A") for a new contract amount of$62,662.89 and for approval for final payment in the amount of$307.78 (attached hereto as Exhibit"B"). Section 3. THAT a copy of the caption of this resolution be spread upon the minutes of the City Council. READ, ADOPTED AND APPROVED THIS day of , A.D., 2020, at a Regular Meeting of the City Council of the City of Port Arthur, by the following vote: AYES:(Mayor) Councilmembers: NOES: Thurman"Bill" Bartie Mayor ATTEST: Sherri Bellard City Secretary P.R.#21687 11/24/2020 ca APPROVED AS TO FORM: iartib,ultiLyq al Tizeno'Esq. City Attorney APPROVED FOR ADMINISTRATION: Ron Burton City Manager Chandra Alpough Director of Parks and Recreation APPROVED AS TO AVAILABILITY OF FUNDS: Kandy Daniel Interim Director of Finance e-414-1 Clifton Williams, CPPB Purchasing Manager EXHIBIT "A" CHANGE ORDER NO. 4 ORIGINAL AGREEMENT DATE: July 7, 2020 PROJECT DESCRIPTION: Interior Repairs at the Recreation Center CHANGE IN SCOPE: Credit for Moving Equipment CHANGE TO CONTRACT AMOUNT: ORIGINAL CONTRACT PRICE: $62,355.11 CURRENT CONTRACT PRICE(adjusted by previous CHANGE ORDER):$63,962.89 The Contract Amount due to this CHANGE ORDER will decrease by: $1,300.00 The new CONTRACT AMOUNT including the CHANGE ORDER will be: $62,662.89 ORIGINAL CONTRACT DAYS: 30 NEW CONTRACT DAYS: 30 SIGNED AND AGREED TO on the_day of , 2020. JACKBUILT CONTRACTORS, LLC Print Name: Title: SIGNED AND AGREED TO on the_day of _, 2020. CITY OF PORT ARTHUR BY: RON BURTON CITY MANAGER EXHIBIT "B" C Y .0 X C/. L W N - /^ > .' t . .71 TD 21 z '7 7 7 _ E. 7 - _ _ F7 E a 0 z - . TO 5 2 • m = S. y- � s. f - - - rF , _J ± ^ _ _ , ^ - � " —1 c -I o 0 r " ". J. 2 ^. J f y . 7 , 7 T O 01 O c Cm- = -} 2 7 •' r G ',9 - " - N 7J O o D r ry z — — ^ O ,, f7 C a - z ' i J 3 r a Z m 7 r. = �" LA =• O O - - F • C Ci - „ 7 2 }. f > 0 '� C) °' n ., - r m c0 z z - - •r' X' n 77 30 > 44 ", rf " 71 w -u z 2 D > c 0 D. a C z - T m - 70 m • S _n 0 f f w - cTi D rri - 0 3 ® -1 Eh H4 V` -I' — fa,f/:b)dY TY x — _ 'O A •O W - Z a a a 2 S ^ E D f J o- =D - , N CCm C :^ P O w w Q N IO - 7 O O N I N to C) = t O 00 O 00 C •X X. 4 - X 2 3C - C .0 C .0 C ., .. 00 - a -_+ O' M O v n 0 _ — = = > a' =- > _ = D 3zrf - 7 = - m o ., _ - = - v ., . _ — 1 J UI im 7 ' : nC et 0, 3, If - - f, c a - =0 fz - T _ ,..m.S-• B7r r - CQ ,- Z V ti z � - 7 MtZTi '. [0 Zr ^ — f , Oc: = — 7 - 3 ` - r. - I/ `< C � A , z` $ ' = ^ ^ J: 7DNq R 3 -• n - y O v o 0 .Nuuq 7� ^ r O = 73 z _ r,•� Z , it �K. = = 1 :ii'ii • 5 r g s -1 = m 8 in m a r. _ Z 1.. 0 3 < r 70 70 N c - m c 3� o o n n m c - - I - Cr ?c z -3 ..i to ti F - 0 v o r•€ o. Ow z w m I N w ` D C ` mO CI, Al N.) x N 01 41 C ^ gc': A — o .0 00 J a LA -C. W N - .... re P; 0 Ci S. 000 = p g• rc ,T. = W Z C " ., ��'. r, a of `' aX c`�. �' C a Ccr: z $ ,' 3 v to- U 0 5 r C 7 �) _, P; n 5 to es x Z X a n Z a.Er Z n � z m _ 1a .= n m ► VI 6n fn EA S `< N 6R H4 us C U 4R A w 4/) - >Vm - 71.-7 n O O r) C' to .0 A N W to C 00 U -- v m. 7 m C'tv C .0 C .0 J U J th ,0C ...l - f� -� -i 00 C u .^.� p to .D N .O J an Z c 'C C N O' N N N sC N OC T n j� til Q Z 'O -, < z n o O p tan O z En O --� 0 3 E = a G 0' (A -fcsa N 5A 69 69 d9 6 VI T 9 i 5 3 ),.., — 44 69 EA O U r. w .- U :11- 7 T ticO I) N O A O ,..o EOJ ntitpop --I "4 0 A O O Fro, 7-7 pp co v a •C C N C 0• EJ N N 'C IQ 00 3, ..I a W. LT1 244 z - C EA -` z v 6 69 EA - 3440 c^oo oo 4 to:cp 3 0 C C 0 0 C 0 0 C o C > o a > .-; = n EA 69 EA b9 C 3 -� Y nN C .P o w N a U. 'C 'C P - -- [r „�C, �-,� ' V) li r ) 00 C J O O U .p N 'C J -- y. r .0 O N O 0' N N tJ 0 N 00 T G C) X "O ""i n 3 Or" O > o til Z - r o 0 0 0 0 p 0 � 00cc0009 c o �-IpCz G CCCci COCZC00 Z —l � Z c 3 e' o o , o e o e o e O O m 0 m C �' T. > d +I N.) O O 6A Vs 69 EA b9 69 64 69 EA EA 4A �4 =') Z fZ"� J N m J 2 C o 0 0 0 0 0 0 0 0 �, o N 0 0 0 0 C C o 0 0 0 0 0 r o No H. o -T, z Cl) > > E., ni c tn Q