INTEROFFICE MEMORANDUM
Date: December 15, 2020
To: The Honorable Mayor and City Council
Through: Ron Burton,City Manager
From: Alberto Elefano,P.E.,Public Works Director
RE: P.R.21723:Authorizing the City Manager to amend the payment schedule in Appendix B-
Billing Milestones of the contract for management and consultant services between the
City of Port Arthur and Ardurra Group, Inc. of Houston,Texas for the Community
Development Block Grant Mitigation Program(CDBG-MIT).
Introduction:
The intent of this Agenda Item is to authorize the City Manager to amend the payment schedule in Appendix
B-Billing Milestones of the contract with Ardurra Group, Inc. of Houston, Texas (Consultant) for
management and consulting services for the Community Development Block Grant Mitigation Program
(CDBG-MIT).
Background:
Pursuant to Resolution 20-126,approved by Council,the City entered into a contract with Ardurra Group of
Houston, Texas to help fulfill State and Federal Community Development Block Grant Mitigation(CDBG-
MIT)responsibilities related to recovery in connection with any federally declared disaster. The Consultant
has assisted the City and the Texas General Land Office(GLO) in the completion of CDBG-MIT qualified
housing or non-housing project applications and has provided Grant Administration services for housing
projects,non-housing projects,or both. The Consultant has proposed that the existing payment schedule of
Appendix B-Billing Milestones be amended as follows: (1) billing milestones for the Project Application
Submission through Notice of Selection be paid at 2% of the projected administrative allowance, not to
exceed $50,000.00; and (2) that Notice of Selection to Project Closeout maintain levelized billing for the
duration of the project divided by the project schedule ending with the project Close Out with the average
monthly allowance varying by no greater than a 10%variance above the allowance on any monthly invoice.
The modification to the Consultant's billing schedule will allow invoicing for percentage of work completed
as opposed to payment when certain project milestones are met, since these projects have a five to ten year
duration.
"Remember,we are here to serve the Citizens of Port Arthur"
444 4t Street X Port Arthur,Texas 77641-1089 X 409.983.8182 X FAX 409.983.8294
Budget Impact:
Funds are available in the CDBG Mitigation Account No. 148-2300-901.60-00.
Recommendation:
It is recommended that the City of Port Arthur's City Council approve PR 21723 with Ardurra Group of
Houston, Texas authorizing the City Manager to amend the payment schedule in Appendix B-Billing
Milestones of the contract for management and consulting services for the Community Development Block
Grant Mitigation Program (CDBG-MIT).
"Remember,we are here to serve the Citizens of Port Arthur"
P.O.Box 1089 X Port Arthur,Texas 77641-1089 X 409.983.8101 X FAX 409.982.6743
PR No.21723
12/15/20 mje
Page 1 of 3
RESOLUTION NO.
A RESOLUTION AUTHORIZING THE CITY MANAGER TO AMEND THE
PAYMENT SCHEDULE OF THE CONTRACT WITH ARDURRA GROUP,
INC. OF HOUSTON, TEXAS FOR PROFESSIONAL SERVICES
ASSOCIATED WITH THE MANAGEMENT AND ADMINISTRATION OF
THE CITY OF PORT ARTHUR'S COMMUNITY DEVELOPMENT BLOCK
GRANT MITIGATION PROGRAM (CDBG-MIT). FUNDS ARE
AVAILABLE IN THE CDBG MITIGATION ACCOUNT NO. 148-2300-
901.60-00.
WHEREAS, pursuant to Resolution 20-126, approved by City Council, the City entered
into a contract with Ardurra Group of Houston,Texas (Consultant) to help fulfill State and Federal
Community Development Block Grant Mitigation (CDBG-MIT) responsibilities related to recovery
in connection with any federally declared disaster; and,
WHEREAS,the Consultant has assisted the City and the Texas General Land Office (GLO)
in the completion of CDBG-MIT qualified housing or non-housing project applications and has
provided Grant Administration services for housing projects, non-housing projects, or both; and
WHEREAS, the Consultant has proposed that the existing payment schedule of Appendix
B-Billing Milestones, see Exhibit A be amended as follows: (1) billing milestones for the Project
Application Submission through Notice of Selection be paid at 2% of the projected administrative
allowance, not to exceed $50,000.00; and (2) that Notice of Selection to Project Closeout
maintain levelized billing for the duration of the project divided by the project schedule ending
with the project Close Out with the average monthly allowance varying by no greater than 10%
variance above the allowance on any monthly invoice, See Exhibit B; and,
PR No. 21723
12/15/2020 mje
Page 2 of 3
WHEREAS, the modification to the Consultant's billing schedule will allow invoicing for
percentage of work completed at the time as opposed to payment when certain project
milestones are met, since these projects tend to have a five to ten year duration; and,
WHEREAS, approval of amending the payment schedule of Appendix B-Billing Milestones
of the contract with Ardurra Group, Inc. of Houston, Texas is herein deemed an appropriate
action; now, therefore,
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PORT ARTHUR:
THAT, the facts and opinions in the preamble are true and correct; and,
THAT, the City Manager is hereby authorized to amend the payment schedule in
Appendix B-Billing Milestones of the contract with Ardurra Group, Inc. of Houston, Texas
(Consultant) for management and consulting services for the Community Development Block
Grant Mitigation Program (CDBG-MIT); and,
THAT, a copy of the caption of this Resolution be spread upon the Minutes of the City
Council.
READ,ADOPTED AND APPROVED this the day of , A.D. 2020
at a meeting of the City of Port Arthur, Texas by the following vote:
Ayes: Mayor:
Councilmembers:
Noes:
PR No.21723
12/15/20 mje
Page 3 of 3
Thurman "Bill" Bartie
Mayor
AiiEST:
Sherri Bellard
City Secretary
APPROVED AS TO FORM: APPROVED FOR ADMINISTRATION:
Valecia Tizeno Ron Burton
City Attorney City Manager
APPROVED AS FOR AVAILABILITY OF
FUNDS:
Kandy Daniel
Acting Director of Finance
Alberto Elefano, P.E.
Director of Public Works
Lih\ L,
Cliftor4'Williams, CPPB
Purchasing Manager
EXHIBIT A
APPENDIX B—Billing Milestones
Compensation for this agreement shall be a lump sum percentage, not to exceed, of 6%of the grants received by
the OWNER for all projects more than $1,000,000. Projects under$1,000,000 shall be compensated at 8%. Total
fee is based on actual project value approval by the Texas General Land Office(GLO).
A review of contract performance and budget status shall be conducted with the OWNER and the CONSULTANT at
the below milestones of each separate project:
Deliverable Billing Milestone
Environmental Review Completed 5%
Bid Advertisement 25%
Construction Notice to Proceed 50%
Final Wage Compliance Report 90%
Project Closeout 100%
REMAINDER OF PAGE LEFT BLANK INTENTIONALLY
17
EXHIBIT B
APPENDIX B—Billing Milestones
Due to the nature of the application and selection processes and the potential duration of each
project, Ardurra Group, Inc. proposed that the payment schedule as noted in the current contract
be amended to the following:
Deliverable Billing Milestone
Project Application Submission to Notice of 2%of Projected Admin Allowance Not To Exceed
Selection $55,000
Notice of Selection to Project Closeout based Levelized billing for duration of the project
on Approved Project calculated by the remaining Administrative
Allowance for the approved project divided by
the project schedule ending with project Close-
out. The average monthly allowance may vary
by no greater than a 10% variance above the
allowance on any monthly invoice.