HomeMy WebLinkAboutPR 21752: REPLACE LIBRARY'S BOILER PIPING City of ort rthu T Port Arthur Public Library www.PortArthurTx.gov INTEROFFICE MEMORANDUM Date: 1/14/2021 To: The Honorable Mayor and City Council Through: Ron Burton, City Manager From: Steven Williams, Library Director��d 9!" RE: PR 21752 Replace Library's Boiler Piping Introduction: The intent of this Agenda Item is to seek the City Council's approval for the City Manager to replace the Library's boiler piping due to a leak with Industrial and Commercial Mechanical of Beaumont, Texas, through the Texas BuyBoard Contract No. 558-18, in the amount of $31,632.00. Funds are available in account 001-1403-551.32-00. Background: The Library's boiler is not functioning due to a leak in the boiler's piping of that connects to the mechanical room. In 1980 the Library's boiler piping was constructed at the same time the building was, therefore, the boiler piping is at least 40 years old. After the boiler piping is replaced we will be able to have heat in our building and be able to better regulate the humidity which is vital when keeping our collection safe. Budget Impact: Funds in the amount of$31,632.00 will be used from account 001-1403-551.32-00. Recommendation: It is recommended that City Council approve the City Manager to replace the Library's boiler piping with Industrial and Commercial Mechanical. "Remember,we are here to serve the Citizens of Port Arthur" 4615 9th Avenue X Port Arthur,Texas 77642 X 409.985.8838 P.R.No. 21752 01/14/2021 sw RESOLUTION NO. A RESOLUTION AUTHORIZING THE CITY MANAGER TO REPLACE THE LIBRARY'S BOILER PIPING DUE TO A LEAK WITH INDUSTRIAL AND COMMERCIAL MECHANICAL OF BEAUMONT, TEXAS THROUGH THE TEXAS BUYBOARD CONTRACT NO. 558-18, IN THE AMOUNT OF $31,632.00. FUNDS ARE AVAILABLE IN LIBRARY ACCOUNT NO. 001-1403-551.32-00. WHEREAS, the Library's boiler is not functioning due to a leak in the boiler's piping that connects to the mechanical room; and, WHEREAS,the Library' boiler piping is more than 40 years old; and, WHEREAS, our current boiler was replaced after Hurricane Harvey and still under a five (5) year warranty; and WHEREAS,the library contacted eight(8) companies and only two (2) could complete the work outlined above which their bids are attached in Exhibit"A"; and WHEREAS, pursuant to Chapter 271, Subchapter D, of the Local Government Code, the City may participate in cooperative purchasing programs established by the State Facilities Commission for the purchase prices established through purchase contracts of the Commission; and, WHEREAS,the Library has reviewed the Texas BuyBoard Contract No. 558-18 and determined that Industrial and Commercial Mechanical of Beaumont, Texas, is best qualified to complete the scope of work properly attributable to past satisfactory mechanical work completed at the Library; now therefore, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PORT ARTHUR: THAT,the facts and opinions in the preamble are true and correct. THAT, the City Council authorizes the City Manager to replace the Library's boiler piping with Industrial and Commercial Mechanical of Beaumont, Texas, through Texas Buyboard Contract No. 558-18 for $31,632.00, in substantially the same form as attached as Exhibit"A". THAT, funding is available in Library account no. 001-1403-551.32-00. THAT,a copy of this caption be spread upon the Minutes of the City Council. READ, ADOPTED, AND APPROVED this day of , AD, 2021, at a Meeting of the City Council of the City of Port Arthur,Texas, by the following vote: AYES: Mayor: Councilmembers: • NOES: Thurman Bill Bartie,Mayor ATTEST: Sherri Bellard, City Secretary APPROVED AS TO FORM: )1YLi'f-4Val Tizen City Y Attorne j2.4 0 APPROVED FOR ADMINISTRATION: Ron Burton, City Manager Steven iams,Director of Library APPROVED AS TO AVAILABILITY OF FUNDS: Kandy Daniel Finance Director 1,A4,014,4,„ Clifton ' illiams,Purchasing Manager EXHIBIT "A" Mid-County Plumbing The company does not work on anything pertaining to boiler piping. Premium Plumbing The company does not work on anything pertaining to boiler piping. Discount Plumbing The company does not work on anything pertaining to boiler piping. Snell Master Plumber They said that they could not do the insulation and would have to hire out a mechanical engineer to do it which would raise the price past an all in one mechanical engineer shop. Therefore, refused to do the job and did not give a bid. Action Restoration The company could only complete the plumbing but not the mechanical scope of work. Therefore, refused to do the job and did not give a bid. Impact Plumbing The company could only complete the plumbing but not the mechanical scope of work. Therefore, refused to do the job and did not give a bid. SpawGlass Bid is attached... Industrial and Commercial Mechanical Bid is attached... SpawGlass Building Services SpawGlass Building Services 350 Pine Street,Ste. 310-Beaumont,Texas 77701-Phone(409)681-4547 Answering Service-877-206-0944 Proposal November 19,2020 Steve Williams Port Arthur Public Library 444 4th St. Port Arthur,TX 77642 Re: Re-route new supply and return hot water lines from exterior boiler to inside the Mechanical room. SpawGlass Job No.: Address of Service: 4615 9th Ave Port Arthur,TX 77642 Dear Mr.Williams, SpawGlass Construction Corp. is pleased to offer our proposal to perform the scope as described in the following inclusions: I. INCLUSIONS We have estimated: 1) Tap into exsiting supply and return lines outside. 2) Drill(2)6in. holes into the side of the building to run pipes through. 3) Build Three(3)pipe supports-Two(2)exterior and One(1)interior. 4) Install new 3"supply/return pipes from the exterior mechanical yard to inside the mechanical room. 5) Tap into the existing supply and return lines in the interior mechanical room. 6) Remove non functioning pipe to the connector. 7) Cap the connectors from old underground lines. 8) Pressure test new lines up to 100 PSI 9) Insulate new pipe lines,with a metal jacket on the outside of the building. 10) Clean up job related trash. 11) Provide all supervision,labor,equipment,material,safety,and insurance for job scope above. Cost of Service $ 43,900.00 Sales Tax(8.250/0) TAX EXEMPT Total Cost of Service $ 43,900.00 II. EXCLUSIONS/CLARIFICATIONS 1) Testing of any other existing equipment. 2) Fixing any problems relating to the exisiting boiler. 3) Sales Tax, Performance&Payment Bonds 4) Work not listed under inclusions above is hereby excluded III. OWNER-SUPPLIED 1) Unencumbered access to and about the site for work duration 2) Water and electrical utility for work duration Any work performed outside of this scope of work is to be considered a change order and paid in addition to the stated contract amount.This offer is subject to arrangements being made,which are satisfactory to Contractor,for payment of the contract sum and security thereof. Note:This proposal is valid for thirty(30)days only. 11/19/2020 Shawn Thurman Date Steve Williams Date SpawGlass Construction Corp. Port Arthur Public Library CITY OF PORT ARTHUR—PA LIBRARY—ICM PROPOSAL TO INSTALL NEW BOILER PIPING-TO BYPASS A SECTION OF LEAKING UNDERGROUND BOILER PIPING. Industrial and Commercial Mechanical TACLA23943C 4445 Westpark Avenue Beaumont,TX 77705 Phone(409)842-3737 Fax (409)842-3738 January 13 2021 CITY OF PORT ARTHUR TEXAS 444 4TH STREET I PORT ARTHUR,TX 177640 ATTN: Mr.MIKE FLORES—Facility Director of Operations,Mr.Steve Williams Subject: PROPOSAL TO PERFORM REPAIRS TO BOILER PIPING REFERENCE PA-CITY LIBRARY-INSTALLATION OF NEW SECTION OF BOILER SUPPLY&RETURN PIPING. Dear Mr. Flores,Mr.Williams, Industrial Commercial Mechanical is pleased to offer the following proposal to furnish and install new Boiler supply return Piping,to bypass a section of leaking underground boiler piping as listed below for your consideration, Scope of Work: To Fabricate,Install,and Insulate,100 Linear Feet of 3"-SCH40 C/S Boiler Pipe proposing to replace approximately 100LF of 3"underground Supply and Return Pipe with new 3"-SCH40 C/S Pipe to be 8ft in the air from the outside Boiler Pipe through the Brick outside wall over the door to the existing Pipe inside the Mechanical Room. ICM would first install a new 3"-#150 Ball in the Supply and Return Lines inside the Mechanical Room so that the underground Pipe could be Hydro Tested to check for leaks before Building New Pipe. ITEMS NOT INCLUDED IN PROPOSED WORK Overtime-After Hours work not included—All work is performed during regular time work hours. v Any Changes or Modifications,other than specified as part of proposal,or proposed scope of work. i Any Changes or Work delays;due to problems beyond our control. Warranty of Any Parts or Materials not furnished and installed by ICM PRICE TO PERFORM THE QUOTED WORK THIS PROPOSAL IS VALID FOR 30 DAYS-FROM THE DATE OF PROPOSAL INDUSTRIAL&COMMERCIAL MECHANICAL IS AN AWARDED VENDOR FOR BUYBOARD CONTRACT#558-18. Thank you for your request for this proposal. We would appreciate the opportunity to provide these services.Please let me know if you would like to proceed with the proposed service repair,and what purchase order number we will utilize,for our billing for services. As always,we thank you for your business and the opportunity to provide our services. Regards, Jerry E. Johnson 9fr1o6i1.409-658-8797 TACLA 23943C—Regulated by the Texas Department of Licensing and Regulation PO Box 12157 Austin,TX 78711 1-800-803-9202,512-163-6599