HomeMy WebLinkAboutDisaster Recovery Update to City Council February 2021 FinalDisaster Recovery Update City Council – February 2021 1 REVIEW OF RECOVERY PROCESS 2 CITY EXPENDS FUNDS ON RESPONSE/REPAIRS REVIEW OF PUBLIC ASSISTANCE RECOVERY PROCESS EXPENDED FUNDS BUILT INTO AN ELIGIBLE FEMA PROJECT ELIGIBLE PROJECTS REVIEWED AND FUNDED PER FEMA POLICY APPROVED PROJECTS ARE OBLIGATED FOR FUNDING FEMA RELEASES FUNDS TO TDEM FEMA INCLUDES OBLIGATIONS IN QUARTERLY SPEND PLAN TDEM RELEASES FUNDS TO CITY 3 Disaster Recovery Update City Council – February 2021 Why Ardurra? Partnered with City of Port Arthur since April 2018 Local Presence: Dr. Jeffery Lewis – Griffin Park Kelly Redman – Griffin Park Mounika Parakala – Nederland Craig Taffaro – Port Acres National Expertise and State of Texas Presence working in Port Arthur, Houston, League City, Porter, Humble, Pearland, Gulf Coast Water Authority (Galveston), Mt. Belvieu, Beaumont; New York, Louisiana, Florida, South Carolina, North Carolina Effective working relationships with departments Responsive and flexible to City needs Support City personnel in the recovery efforts so that the ongoing operations continue 4 Port Arthur Disaster Recovery Update City Council – February 2021 DISASTER PROJECTS HARVEY DR-4332-TX Public Assistance/406 Mitigation Harvey DR-4332-TX 404 Hazard Mitigation Program COVID 19/CRF HURRICANE LAURA FLOOD INFRASTRUCTURE FUND (SB7) (Master Drainage Plan) BUILDING RESILIENT INFRASTRUCTURE & COMMUNITIES (WWTP Screens) CDBG-MITIGATION (Downtown Revitalization/Lakeview Drainage) WINTER STORM 2021 DR-4586-TX 5 Port Arthur Disaster Recovery Update City Council – February 2021 ALL PROJECTS Payments to Ardurra to Date Funds Received/Obligated to Date $3.84M $24.39M Additional Potential Payments Ardurra Potential Additional Project Funding $7.65M $193.65M Projected Total Ardurra Payments Projected Total Project Funding $11.49M $218M Projected Reimbursement Projected Reimbursement $9.93M $214M Projected Out of Pocket to Ardurra Projected Out of Pocket to Projects $1.6M $4M 6 Port Arthur Disaster Recovery Update City Council – February 2021 HARVEY DR-4332-TX Public Assistance/406 Mitigation Payments to Ardurra to Date Funds Received/Obligated to Date $2.8M $19.6M Additional Potential Payments Ardurra Potential Additional Project Funding $500K $24M Projected Total Ardurra Payments Projected Total Project Funding $3.3M $43M Projected Reimbursement Projected Reimbursement $1.9M $42.3M Projected Out of Pocket to Ardurra Projected Out of Pocket to Projects $1.4 $700K Additional payments to Ardurra over the next year will be driven by the number of projects that are approved that are currently under review with FEMA. If no additional projects are approved, the additional payments will likely be 50% less. 7 Port Arthur Disaster Recovery Update City Council – February 2021 Harvey DR-4332-TX 404 Hazard Mitigation Program Payments to Ardurra to Date Funds Received/Obligated to Date $900K $1.8M Additional Potential Payments Ardurra Potential Additional Project Funding $2.2M $63.7M Projected Total Ardurra Payments Projected Total Project Funding $3.2M $65.5M Projected Reimbursement Projected Reimbursement $3.1M $65.5M Projected Out of Pocket to Ardurra Projected Out of Pocket to Projects $100K $200K The four drainage improvement projects included in this program are at the bid stage and projected to be completed by– El Vista (2/22), Port Acres (7/22), Lake Arthur (7/22), and Stonegate (11/22). 8 Port Arthur Disaster Recovery Update City Council – February 2021 COVID 19/CRF Payments to Ardurra to Date Funds Received/Obligated to Date $125K $2.99M Additional Potential Payments Ardurra Potential Additional Project Funding $50K $500K Projected Total Ardurra Payments Projected Total Project Funding $175K $3.5M Projected Reimbursement Projected Reimbursement $170K $3.4M Projected Out of Pocket to Ardurra Projected Out of Pocket to Projects $5K $100K Additional payments to Ardurra above $145K will only occur if a FEMA Public Assistance claim is developed. 9 Port Arthur Disaster Recovery Update City Council – February 2021 LAURA DR-4572-TX Payments to Ardurra to Date Funds Received/Obligated to Date $0 $0 Additional Potential Payments Ardurra Potential Additional Project Funding $120K $750K Projected Total Ardurra Payments Projected Total Project Funding $120K $750K Projected Reimbursement Projected Reimbursement $38K $563K Projected Out of Pocket to Ardurra Projected Out of Pocket to Projects $82K $187K At the end of 2020, FEMA expanded the Laura declaration to cover all damages which provides an opportunity for any damages not previously evaluated to be a potential source of reimbursement for the City. 10 Port Arthur Disaster Recovery Update City Council – February 2021 FLOOD INFRASTRUCTURE FUND (SB7) (Master Drainage Plan) Payments to Ardurra to Date Funds Received/Obligated to Date $0K $0 Additional Potential Payments Ardurra Potential Additional Project Funding $75K $1.3M Projected Total Ardurra Payments Projected Total Project Funding $75K $1.3M Projected Reimbursement Projected Reimbursement $25K $507K Projected Out of Pocket to Ardurra Projected Out of Pocket to Projects $50K $800K Of the $75K in potential payments, only $25K is for application and project development costs; $50K is only accessible if the grant is awarded to the City. 11 Port Arthur Disaster Recovery Update City Council – February 2021 BUILDING RESILIENT INFRASTRUCTURE & COMMUNITIES (WWTP Screens) Payments to Ardurra to Date Funds Received/Obligated to Date $0 $0 Additional Potential Payments Ardurra Potential Additional Project Funding $75K $5.9M Projected Total Ardurra Payments Projected Total Project Funding $75K $5.9M Projected Reimbursement Projected Reimbursement $75K $4.43M Projected Out of Pocket to Ardurra Projected Out of Pocket to Projects $0 $1.47M Of the $75K in potential payments, only $25K is for application and project development costs; $50K is only accessible if the grant is awarded to the City. 12 Port Arthur Disaster Recovery Update City Council – February 2021 CDBG-MITIGATION (Downtown Revitalization/Lakeview Drainage) Payments to Ardurra to Date Funds Received/Obligated to Date $15K $0 Additional Potential Payments Ardurra Potential Additional Project Funding $4.6M $97M Projected Total Ardurra Payments Projected Total Project Funding $4.6M $97M Projected Reimbursement Projected Reimbursement $4.6M $97M Projected Out of Pocket to Ardurra Projected Out of Pocket to Projects $0 $0 – 1M The current contract authorizes $50K for application and project development costs. The remainder of the potential costs for Ardurra services are only accessible if the grant is funded. 13 Port Arthur Disaster Recovery Update City Council – February 2021 WINTER STORM 2021 DR-4586-TX Payments to Ardurra to Date Funds Received/Obligated to Date $0 $0 Additional Potential Payments Ardurra Potential Additional Project Funding $25K $500K Projected Total Ardurra Payments Projected Total Project Funding $25K $500K Projected Reimbursement Projected Reimbursement $25K $375K Projected Out of Pocket to Ardurra Projected Out of Pocket to Projects $0 $125K 14 Port Arthur Disaster Recovery Update City Council – February 2021 ADDITIONAL BENEFITS In addition to direct project and program management, Ardurra provides expert support to the City through procurement review, insurance analysis, bid specifications and contractor selection, Ike Close-out review, real-time emergency operations support during incidents, financial projections and budgetary impacts of recovery projects. Ardurra has assisted the City in securing millions of dollars in insurance claims as part of disaster recovery project development and provided expert policy guidance relative to insurance needs following federal support to repairs to damages. While these services will not show up on a balance sheet, these services are significant to the overall recovery and long-term protection of the City during post event audits and reviews. 15 Port Arthur Disaster Recovery Update City Council – February 2021 NEXT STEPS In an effort to continue to provide relevant updates to the council, Ardurra is happy to present a quarterly presentation with specific project updates across all of the projects that are being worked on. Please feel free to reach out to our team with any questions that may be of interest to you: Craig- ctaffaro@ardurra.com (504)401-3654 Mounika- mparakala@ardurra.com (904)207-0267 Jefferey Lewis- jlewis@chica-assoc.com (409)549-2269 Kelli Redman- kredman@chica-assoc.com (409)519-1720 16