INTEROFFICE MEMORANDUM
UTILITY OPERATIONS DEPARTMENT-ADMINISTRATION
Date: March 9, 2021
To: Ronald Burton, City Manager
From: Donnie Stanton, Interim Director of Utilities
RE: P. R. No. 21826—Automation of Existing Manual Controls for the Control System
for Filters and Clarifiers for the Water Purification Plant by Champion Technology
Services
Nature of the Request:
Resolution No. 20-405, passed on November 24th, 2020, and Resolution No. 20-457, passed on
December 22nd, 2020, authorized the design and construction of both the filter control system and
of the clarifier control system at the Water Purification Plant at 1101 H. O. Mills Blvd. The cost
of installation and startup could not be determined until the design and construction of the controls
was complete. This resolution is to authorize the installation and startup of the automation
controls. The automation of existing manual controls for the control system for filters and clarifiers
for the Water Purification Plant are necessary for proper operation. Champion Technology
Services is considered the sole source provider of these services due to prior setup of controls at
the plant and ability to support the current systems at the facility.
Champion Technology Services has submitted a quote in the amount of $41,975.00 for these
services. This project is budgeted and funding is available in Utilities Account No. 410-1252-
532.92-00, Equipment.
The Utilities Department is seeking authorization for Champion Technology Services of Port
Arthur, Texas to install and startup automated control system for filters and clarifiers in the
submitted amount of$41,975.00.
Budget Considerations:
This project is budgeted and funding is available in Utilities Account No. 410-1252-532.92-00,
Equipment.
Recommendation:
I recommend that the City Council approve Proposed Resolution No. 21826, authorizing the
automation of existing manual controls for the control system for filters and clarifiers for the Water
Purification Plant in the amount of$41,975.00.
P.R. 21826
3-9-21 to/bw,
Page 1 of 3
RESOLUTION NO.
A RESOLUTION AUTHORIZING THE INSTALLATION AND
STARTUP OF AUTOMATED CONTROLS FOR FILTERS AND
CLARIFIERS OF THE WATER PURIFICATION PLANT BY
CHAMPION TECHNOLOGY SERVICES OF PORT ARTHUR,
TEXAS IN THE AMOUNT OF $41,975.00; FUNDING IS
AVAILABLE IN UTILITIES ACCOUNT NO. 410-1252-532.92-00,
EQUIPMENT.
WHEREAS, Resolution No. 20-405, passed on November 24th, 2020, authorized the
design and construction of the filter control system at the Water Purification Plant due the existing
electronics being outdated and no longer supportable; and,
WHEREAS, Resolution No. 20-457, passed on December 22nd, 2020, authorized the
design and construction of the clarifier control system at the Water Purification Plant due to the
existing electronics being outdated and no longer supportable; and,
WHEREAS,the design and construction of the replacement controls was necessary before
cost of installation and startup were known for automation of existing manual controls for the
control system for filters and clarifiers for the Water Purification Plant; and,
WHEREAS, City staff has solicited a quote for installation and startup of automation of
controls for the filters and clarifiers for the Water Purification Plant; and,
WHEREAS,Champion Technology Services of Port Arthur,Texas,a sole source provider
(see Exhibit "A"), submitted the quote attached as Exhibit "B", which meets our specifications;
and,
WHEREAS, this purchase is authorized by Procurement Policies and Procedures Section
3-105 Sole Source Procurement, b) Compatibility—The product must match an existing brand of
equipment for compatibility and is available from only one supplier; and,
P.R. 21826
3-9-21 ta/bw
Page 2 of 3
WHEREAS, this procurement is exempt from the bid process under Texas Local
Government Code Section 252. 022, General Exemptions(a)(7) (D), captive replacement parts or
components for equipment.
NOW,THEREFORE,BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF PORT ARTHUR:
THAT,the facts and opinions in the preamble are true and correct; and,
THAT, the City Council of the City of Port Arthur hereby authorizes the installation and
startup of automated controls for filters and clarifiers for the Water Purification Plant by Champion
Technology Services of Port Arthur, Texas for the amount of$41,975.00, as delineated in Exhibit
,,B„
THAT, a copy of the caption of this Resolution be spread upon the Minutes of the City
Council.
READ, ADOPTED,AND APPROVED this the day of , A.D. 2021 at
a meeting of the City of Port Arthur, Texas by the following vote:
Ayes: Mayor:
Councilmembers:
Noes:
Mayor
Thurman"Bill" Bartie
P.R. 21826
3-9-21 ta/bw
Page 3 of 3
ATTEST:
City Secretary
Sherri Bellard
APPROVED AS TO FORM: APPROVED FOR ADMINISTRATION:
/)/7i Valecia T. eno U/1 Ronald Burton
City Attorney City Manager
Donnie Stanton
Interim Director of Water Utilities
APPROVED AS FOR AVAILABILITY
OF FUNDS:
1"<-0\-- -- 6-y
Kandy Daniel
Interim Director of Finance
IuL/& ,
Clifton`Williams, CPPB
Purchasing Manager
Exhibit "A"
/ •' Champion Technology Services,Inc.
C M P I 0 N 7980 Anchor Drive,Bldg.200
Port Arthur,TX 77642
; SERVICES P:(409)527-6545
Jeff Wyble
City of Port Arthur Water Purification Plant
Dear Mr. Wyble,
Champion has served the needs for this facility since 2014 and is the only Automation Systems Integrator
in the southeast Texas and southwest Louisiana area to hold partnerships with the two automation
manufacturers implemented at this site. These include:
• Recognized Systems Integrator for Rockwell Automation with engineers certified in PlantPAx.
• GE Industrial Solution Partner for the RX3i line of products.
Feel free to reach out to me directly if additional information is required.
Regards,
Scott Thompson
Automation Manager
Champion Technology Services, Inc.
(337) 533-8800
scott.thompson@champtechnology.com
Exhibit "B"
CHAMPION
TECHNOLOGY
Collaborate Innovate Accelerate
ESTIMATE NO. Q20210065
ON-SITE INSTALLATION
SERVICES
CITY OF PORT ARTHUR WATER
PURIFICATION PLANT
Scott Thompson
Automation Manager
Beaumont, TX
February 23, 2021
www.ChampTechnology.com
Champion Technology Services,Inc.
C H! M P I 0 N 7980 Anchor Drive, Bldg.200
Port Arthur,TX 77642
SERVICES (409)527-6545
Jeff Wyble
City of Port Arthur Water Purification Plant
Dear Mr. Wyble,
Thank you for giving Champion Technology Services, Inc. ("Champion")the opportunity to provide City of
Port Arthur Water Purification Plant ("City of Port Arthur")with this estimate for On-Site Installation
Services.
At Champion, we take pride in the quality of our work, the value of our experience, and the importance we
place on our continued partnership with our customers. Our dynamic team makes it a priority to deliver
high-quality solutions, dedicated customer service, and exceptional workmanship.
Sincerely,
Scott Thompson
Automation Manager
Champion Technology Services, Inc.
(409) 527-6545
scott.thompson@champtechnology.com
CONFIDENTIALITY NOTICE:This proposal and its contents are confidential and proprietary to Champion Technology Services,Inc.This
information is specifically provided in confidence to the individual or entity named in the document with the understanding that it may not be
disclosed,copied,or distributed,in whole or in part,to a third party or used for any purpose other than evaluation of this proposal.
Issue Date: 2/23/2021 CONFIDENTIAL INFORMATION Estimate: Q20210065
On-Site Installation Services
Revision: 0.0 www.ChampTechnology.com Page 2 of 9
Champion Technology Services, Inc.
C M P I O N 7980 Anchor Drive,Bldg.200
Port Arthur,TX 77642
TECHNO SERVICES (409)527-6545
BASIS FOR PROPOSAL
Champion has two (2) current projects with City of Port Arthur Water Purification Plant:
• Old Clarifier MicroLogix Upgrade
• PLC600 HMI Upgrade
Champion is providing the following estimate for on-site support for these two projects on a time and
materials basis.
OLD CLARIFIER MICROLOGIX UPGRADE
City of Port Arthur has requested support services from Champion to remove existing hardware, install
new hardware, and provide on-site installation supervision and commissioning for the Clarifier MicroLogix
Upgrade project (1243-021).
INSTALLATION
Champion estimates the following hours on-site for installation.
Automation Support Automation Electrician
Engineer
Personnel 1 2
Days 2 2
Hours Per Day 10 10
Total 20 40
MATERIAL
The following material will be provided during installation.
Supplied Materials
Item Manufacturer Description Quantity
1 Phoenix Contact Fused and Unfused Terminal Blocks, Wireway, DIN Rail, Lot
etc. for up to 20 fused channels
CONFIDENTIALITY NOTICE:This proposal and its contents are confidential and proprietary to Champion Technology Services,Inc.This
information is specifically provided in confidence to the individual or entity named in the document with the understanding that it may not be
disclosed,copied,or distributed,in whole or in part,to a third party or used for any purpose other than evaluation of this proposal.
Issue Date: 2/23/2021 CONFIDENTIAL INFORMATION Estimate. Q20210065
On-Site Installation Services
Revision: 0.0 www.ChampTechnology.com Page 3 of 9
Champion Technology Services, Inc.
C M P I O N 7980 Anchor Drive,Bldg 200
Port Arthur,TX 77642
SERVICES (409)527-6545
COMMISSIONING
Champion estimates the following hours for on-site commissioning and support.
On-Site Support Quantity
Automation Engineer(s) 1
Days 1.5
Hours Per Day, including portal-to-portal travel 8
Total 12
PLC600 HMI UPGRADE
Champion will provide on-site installation and commissioning services for the PLC600 HMI Upgrade
project (1243-019).
This involves providing services to automate existing manual controls for the PLC600 HMI Upgrade
project. This service will add automated back flushing to the automation system.
Champion is providing all services on a time and materials basis.
AUTOMATIC BACKWASHING SEQUENCE
Champion estimates 60 hours in-house to create logic and graphics associated with automatic
backwashing of five (5)filters.
INSTALLATION
Champion estimates the following hours on-site for installation.
Automation Support Automation Electrician
Engineer
Personnel 1 2
Days 5 5
Hours Per Day 10 10
Total 50 100
CONFIDENTIALITY NOTICE:This proposal and its contents are confidential and proprietary to Champion Technology Services,Inc.This
information is specifically provided in confidence to the individual or entity named in the document with the understanding that it may not be
disclosed,copied,or distributed,in whole or in part,to a third party or used for any purpose other than evaluation of this proposal.
Issue Date: 2/23/2021 CONFIDENTIAL INFORMATION Estimate. Q20210065
On-Site Installation Services
Revision: 0.0 www.ChampTechnology.com Page 4 of 9
' Champion Technology Services,Inc.
C MP I ON 7980 Anchor Drive,Bldg.200
Port Arthur,TX 77642
SERVICES (409)527-6545
MATERIAL
The following material will be provided during installation.
Supplied Materials
Item Manufacturer Description Quantity
Fused and Unfused Terminal Blocks, Wireway, DIN Rail,
1 Phoenix Contact Lot
etc. for up to 20 fused channels
COMMISSIONING
Champion estimates the following hours for on-site commissioning and support.
On-Site Support Quantity
Automation Engineer(s) 1
Days 3
Hours Per Day, including portal-to-portal travel 10
Total 30
I CLARIFICATIONS AND EXCEPTIONS
• All services, including portal to portal travel and standby time, will be billed on a time and
materials basis.
• Estimated hours do not include weekends, holidays and outside of regular business hours.
• Respective multipliers will be applied per listed terms and conditions.
• Champion assumes all field devices are in good working order. Materials or services to
troubleshoot, repair, or replace field devices are not included in this proposal.
CONFIDENTIALITY NOTICE:This proposal and its contents are confidential and proprietary to Champion Technology Services,Inc.This
information is specifically provided in confidence to the individual or entity named in the document with the understanding that it may not be
disclosed,copied,or distributed,in whole or in part,to a third party or used for any purpose other than evaluation of this proposal.
Issue Date: 2/23/2021 CONFIDENTIAL INFORMATION Estimate. Q20210065
On-Site Installation Services
Revision: 0.0 www.ChampTechnology.com Page 5 of 9
Champion Technology Services, Inc.
C M P I O N 7980 Anchor Drive,Bldg.200
Port Arthur,TX 77642
S E R v f C E 5 (409)527-6545
ON-SITE SERVICES (T&M)
CLARIFIER
Installation (60 Hours at Standard Hourly Rates + Material &Travel) $10,768
Commissioning (12 Hours at Standard Hourly Rates + Travel) $2,994
Total 13762 $13,762
PLC 600
Automatic Backwashing Sequence $10,175
Installation (150 Hours at Standard Hourly Rates+ Material &Travel) $25,363
Commissioning (30 Hours at Standard Hourly Rates+Travel) $6,437
Total $41,975
3!LLNG TERMS
100% Billed Biweekly
READY TO START?
1. Email your purchase order to orders.LC@champtechnology.com
2. Please reference the Champion proposal number Q20210065
Just a reminder...
• Champion is providing this document as a time and materials estimate.
• Services outside the scope will be billed on a T&M basis.
• Quotation is good for 60 days.
• Taxes are not included.
• Freight is not included; any freight(FOB Beaumont, TX)will be prepaid and added to the
final invoice.
• Services and/or products provided are subject to the terms and conditions below.
Again, thank you for the opportunity to submit this estimate to City of Port Arthur. We look forward to
working with you on this project.
Questions? How Are We Doing?
Take Our 5 Minute Survey.
Please contact Scott Thompson at(409) 527-6545 or
scott.thompson@champtechnology.com with any questions or concerns.
CONFIDENTIALITY NOTICE:This proposal and its contents are confidential and proprietary to Champion Technology Services,Inc.This
information is specifically provided in confidence to the individual or entity named in the document with the understanding that it may not be
disclosed,copied,or distributed,in whole or in part,to a third party or used for any purpose other than evaluation of this proposal.
Issue Date: 2/23/2021 CONFIDENTIAL INFORMATION Estimate: Q20210065
On-Site Installation Services
Revision: 0.0 www.ChampTechnology.com Page 6 of 9
•' Champion Technology Services,Inc.
C M P I 0 N 7980 Anchor Drive, Bldg.200
Port Arthur,TX 77642
TECHNOLOGY SERVICES (409)527-6545
STANDARD TERMS AND CONDITIONS
CHAMPION TECHNOLOGY SERVICES, INC.
STANDARD TERMS AND CONDITIONS
(Effective January 1,2017)
Terms Applicable to All Contracts
1. Agreement.The entire agreement between Champion Technology Services, Inc. ("Champion")and the entity
purchasing goods of services from Champion ("Purchaser")consists of these terms and conditions, any
accompanying Proposal issued by Champion, and any purchase order issued by Purchaser(except to the extent
such purchase order contains additional, different, or inconsistent terms or conditions, all of which are expressly
rejected; Purchaser acknowledges this rejection by allowing Champion to commence performance of the work
required by this Contract). All of these documents collectively comprise the Contract. To the extent any Proposal
issued by Champion conflicts with these terms and conditions, these terms and conditions shall control. Price
Proposals issued by Champion are valid for 30 days and, if not accepted by Purchaser via purchase order within that
time, may be changed by Champion without notice. "Purchaser"means the party to whom the accompanying
Proposal issued by Champion is directed. "Deliverables"means the systems, services, software, materials, and
equipment to be supplied by Champion under the Contract. "Proposal"means any written or oral proposal, quote,
quotation, or other offer by Champion to supply Deliverables. The provisions of this Contract are severable. If any
part of the Contract is found to be invalid or unenforceable, the remainder of the Contract shall remain in full force
and effect.
2. Proposals. Proposals issued by Champion address specific scope of work, pricing, scheduling and other items
unique to the project, the Purchaser, and the Deliverables. The Proposals will indicate whether Champion intends to
supply the Deliverables on the basis of a fixed-price, time&materials, or both.
3. Resource Assignments. Champion will assign technical resources of varying levels and hourly rates to proposed
projects at its sole discretion. No resources shall be assigned or reserved for any project until a purchase order from
Purchaser is accepted.
4. Schedule and Delays. Champion schedules and prioritizes projects based upon the date a purchase order from
Purchaser is accepted by Champion. Schedules may be modified to reflect agreed changes or as a result of delays
caused by Purchaser or occurrences outside the control of the parties. If Purchaser delays a project for more than 30
days, Purchaser will be invoiced and responsible for timely payment of the greater of a)the next project milestone
billing or b)the sum of all services and materials delivered in excess of the sum of all previous billings. If the work of a
Champion employee is postponed or suspended by Purchaser, or is delayed or does not proceed within reasonable
time that it was initially scheduled for, due to no fault of Champion, Champion may demobilize all personnel and once
requested remobilize same or different personnel when available. In this case, any additional charges, including
travel time and expenses, and remobilization fees are the responsibility of the Purchaser.
5. Changes. Purchaser and Champion are authorized to change the terms or scope of the Contract. Changes may
include but are not limited to: (a)redevelopment due to significant specification changes made by Purchaser; and (b)
wiring, troubleshooting, debugging, or reverse-engineering any materials, software, or systems supplied by
Purchaser. Changes may be authorized in writing, orally or by the conduct of the parties. Champion will provide
Purchaser with pricing for the change in accordance with the Change Pricing provisions set forth below.
6. Payment. Payment is due within 30 days of invoicing. Any delinquent amounts will be subject to a 1.5% per
month late fee. Purchaser is responsible for all costs and expenses incurred by Champion in collection, including
reasonable attorneys'fees. Failure to make payment when due shall entitle Champion to suspend its work under the
Contract until all past-due amounts are paid and the Contract price shall be increased by any costs incurred by
Champion for demobilization and remobilization. All prices represent a cash payment discount of 4%. Regardless the
number of invoices per project, credit card payments will only be accepted up to an aggregate amount of$5000 per
Champion project. If payment is made by credit card then the cash payment discount shall be removed and collected
at the time the payment is processed. In the event Purchaser is not the end user or project owner, Purchaser agrees
to release all funds paid to Purchaser covering Champion's work under the Contract immediately and irrespective of
any retainage on the project or retainage held from Purchasers billings. Purchaser will pay Champion in accordance
CONFIDENTIALITY NOTICE:This proposal and its contents are confidential and proprietary to Champion Technology Services,Inc.This
information is specifically provided in confidence to the individual or entity named in the document with the understanding that it may not be
disclosed,copied,or distributed,in whole or in part,to a third party or used for any purpose other than evaluation of this proposal
Issue Date: 2/23/2021 CONFIDENTIAL INFORMATION Estimate. Q20210065
On-Site Installation Services
Revision: 0.0 www.ChampTechnology.com Page 7 of 9
I
' Champion Technology Services, Inc.
C M P O N 7980 Anchor Drive,Bldg.200
Port Arthur,TX 77642
SERVICES (409)527-6545
with the Contract irrespective of whether Purchaser actually receives payment from third parties, including the end
user or project owner, covering Champion's work.
7. Limitation of Liability. Champion is not liable for any damages to equipment, property, or persons resulting from
the improper use of Deliverables. Champion is not liable for any indirect, special, liquidated, consequential or
incidental damages of any kind, including but not limited to,damages for LOSS OF USE of facilities or equipment,
LOSS OF REVENUE, LOSS OF PROFITS or LOSS OF GOODWILL, regardless of whether Champion(a)has been
informed of the possibility of such damages or(b)is negligent. Any damages for which Champion may be found
liable under any circumstance under this Contract shall be limited to the amount actually paid by Purchaser under the
Contract. In the event the work under the Contract is delayed for any reason, including an act or omission of
Champion, Purchaser's sole remedy against Champion shall be to extend the time for performance of the Contract.
All money damages caused by the delay are expressly waived by Purchaser. As the provider of system integration
services, Champion's scope of responsibility as defined in any proposal is limited to the individual controls of the
system only.The overall performance and design of the process, including safety features and failure modes, are the
responsibility of others and shall not be in Champion's scope of work. Any claim by Purchaser against Champion
relating to the Contract, performance of the Contract, or otherwise arising out of Champion's work under the Contract,
must be brought within two years and one day of the date when Purchaser first discovers the claim or the date when
Purchaser could have discovered the claim using reasonable diligence or inquiry.
8. Recruiting. Purchaser shall not directly or indirectly offer to solicit the employment of, or attempt to establish a
contract or work relationship with, any Champion employee during the term of this Contract, or any active contract
between Purchaser and Champion, and for one year following the completion of all work thereunder. Purchaser
acknowledges that Champion will suffer damages if Purchaser violates this section and that these damages will be
difficult to calculate. As a good faith, fair, and just estimate of the damages, Purchaser agrees to pay Champion
$150,000 for every employee it solicits in violation of this provision.
9. Governing Law.The Contract is governed by and construed in accordance with the laws of the state where the
project is located. Any controversy or claim arising out of this Contract, or its breach, shall be settled by a court of
law in Baton Rouge, Louisiana.
10. Travel and Living Expenses. Unless otherwise specified in the Champion Proposal, whenever it is necessary
for a Champion employee to work at a Purchaser-designated location or if an overnight stay is required, travel and
living expense charges shall apply(mileage, meals, lodging,etc.). If air travel is required to reach the work location,
Purchaser shall be responsible for air fare costs in addition to the travel time.All travel charges will be added to the
invoice issued subsequent to the return travel date. In the event that a customer does not want to pay directly for
Portal to Portal Travel Time,then Champion is willing to increase all hourly labor rates by$15/hr to account for the
lost revenue. In the event that a customer does not want to pay directly for markup on mileage,then Champion is
willing to increase all hourly labor rates by$5/hr to account for the lost revenue. In the event that a customer does
not want to pay directly for markup on other travel related expenses such as flights, hotel, or meals,then Champion is
willing to increase all hourly labor rates by$3/hr to account for the lost revenue.
11. Technical Support Hotline Call Rate. The support line will charge a minimum of one hour per call for technical
assistance by any Champion employee.
12. Intellectual Property.Any intellectual property developed by Champion in connection with this Contract shall
remain the sole intellectual property of Champion. Unless there is a separate, signed licensing agreement, upon
acceptance and final payment by Purchaser, Champion shall be deemed to have granted to Purchaser a
nonexclusive limited license(the"License")to use any Deliverable of the Contract for Purchaser's internal purposes
only without any right to assign or sublicense. Unauthorized copying, sale, or transfer of any software comprising the
Deliverable is expressly prohibited,which conduct shall automatically terminate the License. Purchaser shall
indemnify, defend, and hold harmless Champion from and against any and all claims, liability, and expenses,
including reasonable attorneys'fees, arising from Purchaser's modification or use of any software component of the
Deliverables in violation of the Contract and/or License.
13. Warranties.Systems, custom hardware and custom software Deliverables are warranted for a period of six
months following Purchaser's acceptance against failure. For purposes of this Paragraph, acceptance shall be
deemed to have occurred 30 days after delivery if Purchaser has not expressly accepted the Deliverables before that
time. An extended warranty or maintenance agreement,for an additional fee, is available upon request and must be
CONFIDENTIALITY NOTICE:This proposal and its contents are confidential and proprietary to Champion Technology Services,Inc.This
information is specifically provided in confidence to the individual or entity named in the document with the understanding that it may not be
disclosed,copied,or distributed, in whole or in part,to a third party or used for any purpose other than evaluation of this proposal.
Issue Date: 2/23/2021 CONFIDENTIAL INFORMATION Estimate: Q20210065
On-Site Installation Services
Revision: 0.0 www.ChampTechnology.com Page 8 of 9
Champion Technology Services,Inc.
CIAMPION 7980 Anchor Drive,Bldg.200
Port Arthur,TX 77642
SERVICES (409)527-6545
specifically agreed to in writing. Purchaser's sole remedy for failure of the Deliverables to perform as contracted is to
require Champion to repair, patch, debug or replace the items in question or, at Champion'sole option,to refund all
moneys received from Purchaser for the affected Deliverables. Commercial off-the-shelf hardware and software
Deliverables supplied by Champion are warranted to the extent of any manufacturer's warranty alone, and does not
include Champion labor. No warranty is made regarding the accuracy, completeness, or suitability of any software
or data supplied by third parties.ALL OTHER WARRANTIES ARE EXPRESSLY DISCLAIMED.
14. Taxes. Purchaser shall pay to Champion, in addition to amounts stated in the Proposal,the amount of all sales,
use, or other taxes that may be imposed upon this transaction by the federal government or any state government,
or, any subdivision, but only when Champion is required by law to collect or pay such taxes.
Terms Applicable to Fixed-Price Contracts
15. General Provisions. The terms under this heading apply to Contracts and Deliverable where Champion'
Proposal is based on a fixed-price and are not applicable to services performed by Champion under a time&
materials Proposal, also referred to as"work for hire,"and work performed off of Champion's standard rate sheets.
16. Fixed-Price Proposals. Fixed-price Proposals represent the total lump sum cost(and any subdivisions thereof)
for the Deliverables.
17. Change Pricing. If additional or unforeseen services, materials or other Deliverables are needed on a fixed-
price contract, Champion will make reasonable effort to: (a) request written authorization in the form of an
engineering change order before proceeding; and (b)provide a new Proposal for the additional services. In any
case, Purchaser shall be responsible for all services and goods delivered.
Terms Applicable to Hourly Contracts
18. General Provisions. The terms under this heading apply to Contracts where Champion' Proposal is based on
hourly services, time&materials, and/or standard rate sheets. These terms do not apply to Deliverables provided
under a fixed-price Proposal.
19. Rate Sheet Proposals. Champion may propose services on an hourly basis in accordance with the standard
rate sheet provided with this Contract. Hourly price Proposals may include an estimate of hours to perform the
requested services. Champion may perform more or fewer hours of services than contained in such estimate, and
Purchaser agrees to pay Champion for actual and not estimated hours of services performed. Invoices for hourly
services will be issued on a semi-monthly basis reflecting the actual hours worked. Unless otherwise specified in the
Champion Proposal, Services required by Purchaser to be performed over 8 hours during normal business hours
(7AM to 5PM), or outside normal business hours(7AM to 5PM)from Monday through Friday shall be charged at 1.5
times the hourly rates provided to Purchaser. Unless otherwise specified in the Champion Proposal, Services
required by Purchaser to be performed on Saturday shall be charged at 1.5 times the hourly rates provided to
Purchaser. Unless otherwise specified in the Champion Proposal, Services required by Purchaser to be performed
on Sundays and Holidays shall be charged at 2 times the hourly rates provided to Purchaser. Unless otherwise
specified in the Champion Proposal,travel time to and from the work location will be charged at straight time hourly
rates.
20.Work Time. Work time shall include all hours that Champion service personnel are on Purchaser's job site,
either working or ready for work, or off Purchaser's job site and working for Purchaser and shall be payable at the
applicable specified rates.
21.Technical Support Hotline Call Rate. Technical phone support will be charged at a minimum of one hour per
call for technical assistance by any Champion employee.
22.Travel Time("Portal to Portal"). Travel time is billed at the applicable hourly rate for the work to be performed
once on-site, unless a one-way trip is greater than 4 hours, in which case discounted rates will apply.
23. Holiday.When used on Champion's rate sheet, Holiday means holidays observed by Champion Technology
Services, Inc. (available upon request).
24.Activation Fee.When used on Champion's rate sheet,Activation Fee means a fee(based on hours stated in
Champion's rate sheet)that Purchaser agrees to pay for time called to work outside of the office on an immediate
service call within 24 hours
25. Minimum Callout.When used on Champion's rate sheet, Minimum Callout means the minimum amount of time
that shall be paid for time called to work outside of the office.
CONFIDENTIALITY NOTICE:This proposal and its contents are confidential and proprietary to Champion Technology Services,Inc. This
information is specifically provided in confidence to the individual or entity named in the document with the understanding that it may not be
disclosed,copied,or distributed,in whole or in part,to a third party or used for any purpose other than evaluation of this proposal.
Issue Date: 2/23/2021 CONFIDENTIAL INFORMATION Estimate:Q20210065
On-Site Installation Services
Revision: 0.0 www.ChampTechnology.com Page 9 of 9
Champion Technology Services, Inc.
C NA'v' �//�^'O N 7980 Anchor Drive, Bldg.200
Port Arthur,TX 77642
SERVICES P:(409)527-6545
Jeff Wyble
City of Port Arthur Water Purification Plant
Dear Mr. Wyble,
Champion is uniquely suited to perform this work for the City of Port Arthur Water Purification Plant as our
team is familiar with the architecture of the automation system used at Port Arthur Water's sites.
Our organization recommends work associated with automation system be sole sourced to Champion for
the following reasons:
• Solid project history with the Port Arthur Water's GE RX3i PLC control system, which Champion
installed in 2014, and supports.
• In-depth knowledge and training of the following automation technologies used at the site.
o GE QuickPanel HMI and PLC integration
Based on the above qualifications, rooted in site-specific knowledge of the process and various
technologies implemented, Champion is the only automation integrator in the area that can expediently
execute support for the automation systems at this facility and address the architecture as a whole.
Feel free to reach out to me directly if additional information is required.
Regards,
Scott Thompson
Automation Manager
Champion Technology Services, Inc.
(337) 533-8800
scott.thompson@champtechnology.com
Tessa Artis
From: Jeff Wyble
Sent: Tuesday, February 23, 2021 1:34 PM
To: Tessa Artis
Subject: Champion
Attachments: Port Arthur Water Sole-Source Letter-1.0.pdf
Tessa,
The explanation for the work we talked about is as follows:
The services proposed by Champion in the current proposal include installation and startup/commissioning of one
automated control system for Clarifiers 1 and 2 as well as an additional automated control system for filters 1-5 that
Champion is currently developing under a separate purchase order that has already been issued. Please see the attached
sole source letter in lieu of additional quotes and let me know if you need more clarification about the work included in
their proposal.
Thanks,
Jeff
i
Champion Technology Services, Inc.
C M P ION 7980 Anchor Drive,Bldg.200
Port Arthur,TX 77642
Tf ' SERVICES P:(409)527-6545
Jeff Wyble
City of Port Arthur Water Purification Plant
Dear Mr. Wyble,
Champion is uniquely suited to perform this work for the City of Port Arthur Water Purification Plant as our
team is familiar with the architecture of the automation system used at Port Arthur Water's sites.
Our organization recommends work associated with automation system be sole sourced to Champion for
the following reasons:
• Solid project history with the Port Arthur Water's GE RX3i PLC control system, which Champion
installed in 2014, and supports.
• In-depth knowledge and training of the following automation technologies used at the site.
o GE QuickPanel HMI and PLC integration
Based on the above qualifications, rooted in site-specific knowledge of the process and various
technologies implemented, Champion is the only automation integrator in the area that can expediently
execute support for the automation systems at this facility and address the architecture as a whole.
Feel free to reach out to me directly if additional information is required.
Regards,
Scott Thompson
Automation Manager
Champion Technology Services, Inc.
(337) 533-8800
scott.thompson@champtechnology.com