Update to Capital Improvement Plan
And Proposed Amendments
City Council Workshop
March 12, 2021
Capital Improvement Plan Update
•Streets
•Drainage
•City Facilities
•Water and Sewer
Street Improvements
•No proposed changes to FY2021 budget
•$10 million proposed funding for FY2022 delayed until FY2023 to allow time to finish existing projects
Project Name 2021 Original
Budget
2021
Proposed
Budget
2022 2023 2024 2025 FY21-25
Project Cost
Street Projects - Reconstruction 10,000,000 10,000,000 - 10,000,000 10,000,000 10,000,000 40,000,000
Street - Remediation/Rehab 4,302,294 4,302,294 4,000,000 4,000,000 4,000,000 4,000,000 20,302,294
TOTAL 14,302,294 14,302,294 4,000,000 14,000,000 14,000,000 14,000,000 60,302,294
Funding Source 2021 Original
Budget
2021
Proposed
Budget
2022 2023 2024 2025
FY 21-25
Project
Funding
General Revenue - Cash 4,000,000 4,000,000 4,000,000 4,000,000 4,000,000 4,000,000 20,000,000
Bonds (GO's, CO's, Revenue)10,000,000 10,000,000 - 10,000,000 10,000,000 10,000,000 40,000,000
CDBG Grant -
FEMA/HMPG Grant -
(1)Other Grant -
EDC Street Maintenance 302,294 302,294 302,294
(2)Other Funding Source -
TOTAL 14,302,294 14,302,294 4,000,000 14,000,000 14,000,000 14,000,000 60,302,294
Drainage Improvements
404 Hazzard Mitigation Projects
•El Vista, Port Acres, Lake Arthur, Stonegate
•Originally budgeted as a $35 million project over 3years
•Now a $64 million project funded primarily through FEMA and CDBG
•$300,000 projected out of pocket cost for City
CDBG Mitigation Projects
•Downtown revitalization, Lakeview drainage
•New -$97 million project with 4 phases funded primarily through CDBG
•No projected out of pocket cost for the City at this time
Replace 7 Drainage Pump Stations
•New -$2 million estimated cost funded through sale of Certificates of Obligation
Master Drainage Plan
•Originally budgeted $1.2 million -Revised estimate $1.35 million
•Funded by $500,000 Flood Infrastructure Fund Grant through TWDB
•$850,000 projected out of pocket cost for the City
Drainage Improvements
Project Name
2021
Original
budget
2021
Proposed
Budget
2022 2023 2024 2025 FY21-25
Project Cost
404 Mitigation Drainage -El Vista (75/25)1,033,300 5,845,628 5,845,628
404 Mitigation Drainage - Port Acres (75/25)3,153,000 14,879,177 14,879,177
404 Mitig Lake Arthur Detention Pond (75/25)5,261,743 15,593,058 15,593,058
Upgrade Drainage Stonegate (Zaharias) (75/25)1,972,133 16,365,225 16,365,225
Drainage Pump Stations (7)2,000,000 2,000,000
CDBG Mitig Drainage (Downtown/Lakeview)19,634,055 14,720,220 14,720,220 48,280,880 97,355,375
Drainage Study 1,200,000 1,350,000 1,350,000
TOTAL 12,620,176 75,667,143 14,720,220 14,720,220 48,280,880 - 153,388,463
Funding Source
2021
Original
budget
2021
Proposed
Budget
2022 2023 2024 2025
FY 21-25
Project
Funding
General Revenue - Cash 1,150,000 1,150,000
Bonds (GO's, CO's, Revenue)2,000,000 2,000,000
CDBG Grant 5,534,144 19,368,005 14,720,220 14,720,220 48,280,880 97,089,325
FEMA/HMPG Grant 7,086,032 41,307,003 - 41,307,003
(1)Other Grant 11,342,135 11,342,135
EDC Street Maintenance -
(2)Other Funding Source 500,000 500,000
TOTAL 12,620,176 75,667,143 14,720,220 14,720,220 48,280,880 - 153,388,463
City Facility Improvements
Relocate Health Department
•Originally budgeted $900,000 in FY2021 to purchase property
•Actual cost to purchase property $1.6 million
•$830,000 additional out of pocket cost to the City
•$4.5 million estimate for engineering and construction which will be funded through the sale
of Certificates of Obligation
Relocate Animal Shelter
•Originally budgeted $150,000 in FY2021 to begin process
•$2.5 million estimate for construction in FY2022
•Revised project budget of $6.65 million to begin in FY2021
•Funded through sale of Certificates of Obligation
City Facility Improvements
Project Name
2021
Original
Budget
2021
Proposed
Budget
2022 2023 2024 2025 FY21-25
Project Cost
Renovations to Equipment Services Building 183,000 183,000 183,000
Relocate Animal Shelter (150K cash) 150,000 6,650,000 6,650,000
New Police Substation 400,000 400,000 1,200,000 1,600,000
Relocate Parks Division - 19th St Renovation 750,000 750,000 750,000
Relocate Health Department (Acquisition) 900,000 1,615,430 - 1,615,430
Relocate Public Safety Facility -Police/Fire/Court 500,000 500,000 10,000,000 10,500,000
Renovations to City Hall 500,000 500,000 500,000 500,000 1,500,000
Renovations to Adams Building 100,000 100,000 100,000
Renovations to PW Operations Building 450,000 450,000 450,000
Replace Fire Station 2 1,000,000 2,000,000 3,000,000
Replace Fire Station 3 1,000,000 2,000,000 3,000,000
Health Building Construction 4,500,000 4,500,000
-
TOTAL 3,933,000 15,648,430 3,700,000 14,500,000 - - 33,848,430
Funding Source
2021
Original
Budget
2021
Proposed
Budget
2022 2023 2024 2025
FY 21-25
Project
Funding
General Revenue - Cash 3,033,000 3,862,806 2,500,000 500,000 - - 6,862,806
Bonds (GO's, CO's, Revenue)11,000,000 14,000,000 25,000,000
CDBG Grant -
FEMA/HMPG Grant -
(1)Other Grant -
EDC Street Maintenance -
(2)Other Funding Source 900,000 785,624 1,200,000 1,985,624
TOTAL 3,933,000 15,648,430 3,700,000 14,500,000 - - 33,848,430
Water and Sewer Improvements
•Originally budgeted a total of $20.4 million in FY2021
•Revised project budgets total $11.2 million –a decrease of $9.2 million
•No Budget amendment necessary for FY2021
•Water Line Replacement Plan funded through TWDB postponed until FY2022
•Reallocation of other project timelines
•$9.9 million to be funded through sales of Certificates of Obligation in FY2021
•$1.1 million projected out of pocket cost to the Water Fund –a reduction of $1
million to be reallocated to operations
Water and Sewer Improvements
Project Name
2021
Oriiginal
Budget
2021
Proposed
Budget
2022 2023 2024 2025 FY21-25
Project Cost
Lift Stations - 1,000,000 - 2,000,000 2,000,000 2,000,000 7,000,000
Tank Rehab - - - - - - -
TWDB WL Replacement Plan (57 Water Mains) 18,000,000 - 18,000,000 - - - 18,000,000
Sabine Pass Coll Sys 300,000 500,000 500,000 500,000 500,000 500,000 2,500,000
Lakeside Gravity Sewer Main 200,000 300,000 300,000
Dredge Fresh Water Reservoir - - 2,000,000 - - 2,000,000
El Vista Force Main 1,000,000 1,700,000 1,700,000
Hwy 365 Force Main 500,000 3,000,000 3,000,000
Sewer Main Removal (SNND project) 360,000 300,000 300,000
TWDB Sabine Pass Waste Water Tmt Plant - - 9,000,000 9,000,000
42nd Street Force Main 1,000,000 - 1,000,000
Collection Systems Rehab 1,000,000 - 3,000,000 2,000,000 3,000,000 9,000,000
Install parallel 36" Trunk Trans Line - -
Elevated Storage Tank Rehab - 1,000,000 1,000,000 1,000,000 1,500,000 4,500,000
Water Line Improvement/Replacements - 2,000,000 3,000,000 5,000,000
Landfill New Water Line 2,400,000 2,400,000
TOTAL 20,360,000 11,200,000 19,500,000 17,500,000 7,500,000 10,000,000 65,700,000
Funding Source
2021
Oriiginal
Budget
2021
Proposed
Budget
2022 2023 2024 2025
FY 21-25
Project
Funding
General Revenue - Cash (Water) 2,180,000 1,100,000 1,500,000 1,500,000 1,500,000 2,000,000 7,600,000
Bonds (GO's, CO's, Revenue) (Water)* 18,000,000 9,900,000 18,000,000 14,000,000 6,000,000 8,000,000 55,900,000
CDBG Grant -
FEMA/HMPG Grant -
(1)Other Grant -
EDC Street Maintenance -
(2)Other Funding Source 180,000 200,000 - 2,000,000 2,200,000
TOTAL 20,360,000 11,200,000 19,500,000 17,500,000 7,500,000 10,000,000 65,700,000
Proposed 2021 Certificates of Obligation
Street Improvements 10,000,000
Drainage Pump Stations (7)2,000,000
Animal Shelter 6,500,000
Health Department Building Imp 4,500,000
Water & Sewer Projects 9,900,000
Total 32,900,000
Proposed Amendments to Operations
•General Fund
•Total increase of $2.5 million to FY2021 budget is proposed
•$216,000 increase to Administration for Armory Building Repairs
•$172,000 increase to Development Services for new personnel to accommodate additional
shifts at Equipment Services
•$2.1 million increase in Transfers Out
•$1.2 million to fund additional CIP Drainage Improvements
•$830,000 to fund additional CIP Facility Improvements
•$128,000 to Capital Reserve to fund additional Equipment in Equipment Services Division
Proposed Amendments to Operations
•Capital Reserve Fund
•Total increase of $1.3 million to FY2021 budget is proposed
•$366,000 increase to fund additional equipment
•$172,000 –Increase in cost of scale at Landfill
•$128,000 -Mobile Column Lift for Equipment Services Division
•$66,000 –2 F250 Trucks for Water Utilities
•$945,000 increase to fund equipment budgeted in FY2020 –received in FY2021 (No effect
on Fund Balance)
•Solid Waste Fund -$172,000 to Capital reserve to fund additional cost of scales at
Landfill
•Water Fund -$66,000 to Capital reserve to fund additional vehicles purchases
City Council Workshop March 12