HomeMy WebLinkAboutPR 21884: REPAIRS AT ROSEHILL MANOR Memorandum
City of Port Arthur, Texas
Robert A. "Bob"Bowers Civic Center
To: The Honorable Mayor and City Council
Through: Ron Burton,City Manager
From: Adam J Saunders, Civic Center Dir
RE: Proposed Resolution No. P.R. 21884
REQUEST:
At Rosehill Manor, much repair and maintenance are needed. Some repairs have been completed, and are
designated as Phase I. Additional work is needed. The next segment of work is Phase II and it focuses on
exterior needs, mainly on the lower half of the building. The City Council approved Resolution Number
20-200 for Phase II work as well as Change#2 in Resolution Number 20-471.
It has been determined some additional work to the exterior is needed to complete Phase II. This
additional work is to replace a corner column and some support beams. This is needed to adequately
support the corner of the porch roof.
A change order for this work is needed. Change Order#3 for additional exterior work to complete Phase
II in the amount of $2,650.00 will be added. This brings the total for Phase II exterior work to
$263,650.00 (original contract amount of$211,000.00, plus Change Order#2 amount of$50,100.00, plus
this Change Order#3 of$2,650.00.)
ANALYSIS/CONSIDERATION:
There are a lot of needed repairs at the building. Additional work is needed to complete Phase II.
RECOMMENDATION
A resolution authorizing the City Manager to enter into an agreement with American Restoration of
Wylie,Texas for Change Order#3 to Phase II repairs and maintenance of the Rosehill Manor in the
amount of$2,650.00, bringing the total for Phase II exterior work to$263,650.00.
BUDGETARY AND FISCAL EFFECT
Funds are available in Hotel Occupancy Tax Fund Account No. 140-15-600-5470-00-20-000 Project
#H07908.
STAFFING EFFECT
None
Pr21884
P.R. No. 21884
04/06/2021 AJS
PAGE 1 of 3
RESOLUTION NO.
A RESOLUTION AUTHORIZING THE CITY MANAGER TO EXECUTE CHANGE
ORDER NO. 3 TO THE CONTRACT BETWEEN THE CITY OF PORT ARTHUR AND
AMERICAN RESTORATION OF WYLIE, TEXAS, TEXAS FOR PHASE II REPAIRS
TO THE ROSEHILL MANOR THAT INCREASES THE CONTRACT AMOUNT BY
$2,650.00, BRINGING THE TOTAL FOR PHASE II EXTERIOR WORK TO $263,650.00.
FUNDS AVAILABLE IN HOTEL OCCUPANCY TAX FUND ACCOUNT NO. 140-15-
600-5470-00-20-000 PROJECT #H07908
WHEREAS, the City Council approved Resolution No. 20-200 on June 23, 2020, an
agreement with American Restoration of Wylie, Texas for Phase II repairs to the Rosehill Manor
in the amount of$211,000.00; and
WHEREAS, the City Council approved Resolution No. 20-470 on December 22, 2020,
for Change Order No. 1 for Phase II repairs to the Rosehill Manor increasing the contract term
by four days to a new completion date of May 18, 2021; and
WHEREAS, the City Council approved Resolution No. 20-471 on December 22, 2020,
for Change Order No. 2 for Phase II repairs to the Rosehill Manor in the amount of$50,100.00,
bringing the total of the contract to $261,100.00; and
WHEREAS, it has been determined that additional work is needed to complete Phase II
work on the exterior of Rosehill Manor; and
WHEREAS, the additional work is the replacement of a corner column and some
support beams of Rosehill Manor, thus adequately supporting the porch roof; and
WHEREAS, American Restoration of Wylie, Texas has submitted Change Order No. 3
for an additional work in an amount of$2,650.00; and
WHEREAS, approval of Change Order No. 03 is deemed an appropriate action.
Pr2l 884
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE
CITY OF PORT ARTHUR:
Section 1. That the facts and opinions in the preamble are true and correct.
Section 2. That, the City Manager is hereby authorized to execute Change Order No.
3 with American Restoration of Wylie, Texas for Phase II repairs at the Rosehill Manor in the
amount of$2,650.00 to a new total of$263,650.00, in substantially the same form as attached
hereto as Exhibit"A".
Section 3. That, a copy of the caption of this Resolution be spread upon the Minutes
of the City Council.
READ, ADOPTED, AND APPROVED, this day of April, 2021, A.D., at a
Regular Meeting of the City Council of the City of Port Arthur, Texas by the following vote:
AYES:
Mayor:
Councilmembers:
NOES:
Thurman"Bill"Bartie, Mayor
ATTEST:
Sherri Bellard, City Secretary
AP ROVED AS TO FORM:
kil,tayeD
Valecia Ti eno, City Attorney
Pr21884
APPROVED FOR ADMINISTRATION:
Ronald Burton, City Manager
APPROVED AS TO FUND AVAILABILITY:
�►, tom
Kandy Daniel, 0 Clifton Williams, CPPB
Interim Director of Finance Purchasing Manager
Pr21884
EXHIBIT "A"
1.■
1 .1
AMERICAN RESTORATION LLC
March 25, 2021
The LaBiche Architectural Group
7999 Gladys Avenue
Beaumont, Texas 77706
Attention: Dohn LaBiche
Project: Rose Hill Manor—Exterior Historic Restoration
Port Arthur, Texas
Regarding: Request for Change Order(RFC 3)
Dear Dohn:
Pursuant to your request, American Restoration, LLC (ARL) has included herein pricing
information related to additional repairs required at the above referenced project. It is our
understanding that the Owner has decided not to move forward with the recommendations
documented in our February 3 request for change order (RFC) as part of this project, with the
exception of a single column structural repair (Column No. 21). Please be advised that most of
the porch columns will require structural repair due to wood deterioration most likely caused by
leaks through the overlying roof and gutter, as documented in our RFC. We have been instructed
by your office to proceed with the contracted scope of work without performing all of the proposed
structural repairs identified in the February 3 RFC, including all structural columns and
components inspection and repair and the roof replacement. As such, we will reconvene the
painting portion of the work this week without addressing any issues not specifically required by
our existing agreement.
1.0. Structural Repair of Column No. 21: ARL proposes to install a new 4x4 wood column in
the place of the removed Column No. 21. The incoming roof support beams (2x10's)
between Column Nos.20 and 21 and 21 and 23 will be replaced as required and connected
to the new wood support post. The column capital, base, and shroud will be addressed as
specified in the existing contract documents.
2.0. Proposed Price- $2,650.00
Rose Hill Manor—Port Arthur, TX
March 25,2021
Page 2 of 2
I trust this information will be helpful in your continued dealings with this project. if you have
any questions, please contact me at your convenience.
Respectfully,
AMERICAN RESTORATION, LLC.
Rad T400.44
Butch Thomas
Project Manager
CHANGE ORDER
PROJECT: Rose Hill Manor-Phase II CHANGF ORDER NO: 3
CONTRACTOR: American Restoration DATE: 04.06.2021
2002 W. Kirby St ARCHITECT'S PROJECT NO.: 19028
Wylie,Texas 75098 CONTRACT DATE: 06.2.2020
CONTRACT FOR: Restoration
Contract Changes as Follows:
• 1.0 Structural Repair of Column No. 21: ARL proposes to install a new 4x4
wood column in the place of the removed Column No. 21. The incoming
roof support beams(2x10's) between Column Nos. 20 and 21 and 21 and
23 will be replaced as required and connected to the new wood support
post. The column capital, base,and shroud will be addressed as specified
in the existing contract documents. $2,650.00
TOTAL: $2,650.00
**See attached breakdown
Not valid until signed by the Owner,Architect,and Contractor.
The original Contract Sum was $211,000.00
Net change by previously authorized Change Orders $50,100.00
The Contract Sum prior to this Change Order was $261,100.00
The Contract sum will be increased by this Change Order in the amount of $2,650.00
The new Contract Sum including this Change Order will be $263,750.00
1 The Contract Time will be increased by zero(0)days.
The date of Substantial Completion as of the date of this Change Order therefore is
NOTE: The summary does not reflect changes in the Contract Sum or Contract Time which have been authorized by
Construction Change Directive.
The LaBiche Archit ral Group American Restoration City of Port Arthur
7999 Glad e e 101 2002 W. Kirby St 3401 Culture Ctr. Dr.
Beaumo Wylie,Texas 75098 Port Arthur,Texas 77640
By: By: By:
Date: __ ,
/� _ _..'� Date: Date:
�Y ��1. CaQ�
C7. 1 m
• Ili: Q rTh
cn� 11592 __P
gTFIOF � +