HomeMy WebLinkAboutPR 21876: PORT ACRES DRAINAGE IMPROVEMENTS a ._ Ciry of i, ort rthu — Texas www.PortArthurTx.gov INTEROFFICE MEMORANDUM Date: March 31, 2021 To: The Honorable Mayor and City Council Through: Ron Burton, City Manager From: Alberto Elefano, P.E., Public Works Director RE: PR 21876: Port Acres Drainage Improvements; Amend the contract amount by increasing original contract amount by $24,205.00 to a new contract amount of $710,072.00. The Texas Division of Emergency Management(TDEM) and the Federal Emergency Management Agency (FEMA)has required additional technical data, environmental assessments, additional flood modeling, and impact be applied to this project. Project#DR1P03 Introduction: The intent of this Agenda Item is to authorize the City Manager to amend the contract by increasing the original contract amount of$685,867.00 by $24,205.00 to the new contract amount of$710,072.00 for the Port Acres Drainage Improvements Phase I Engineering and Design for drainage facilities by Arceneaux, Wilson and Cole of Port Arthur, Texas. Background: Pursuant to Resolution 20-023, approved by Council, authorizing the City Manager to enter into an agreement with Arceneaux, Wilson and Cole of Port Arthur, Texas for the Phase I Engineering and Design for drainage facilities to serve the Port Acres area in Port Arthur for a fee not to exceed $685,867.00. The Texas Division of Emergency Management (TDEM) and the Federal Emergency Management Agency(FEMA)has mandated that additional technical data, environmental assessments, additional flood modeling, and impact studies be applied to this project. The additional requirements increased the original contract amount of$685,867.00 by $24,205.00 to the new contract amount of $710,072.00. The City of Port Arthur has obtained funding from Hazard Mitigation Grant Program (HMGP) and Community Development Block Grant — Disaster Recovery (CDBG-DR) and has approved the additional cost of the Phase I project. Budget Impact: Funding is available in HMGP Engineering Account No. 154-00-000-8515-00-10-000 AND CDBG- DR Engineering Account No. 148-00-000-8515-00-10-000. "Remember,we are here to serve the Citizens of Port Arthur" 444 4th Street X Port Arthur,Texas 77641-1089 X 409.983.8182 X FAX 409.983.8294 S:\Engineering\PUBLIC WORKS\PW-DRAINAGE PROGRAM\Port Acres\Agenda Memo Port Acres CO 1.docx Recommendation: It is recommended that the City of Port Arthur City Council approve PR 21876 to authorize the City Manager to amend the contract amount of$685,867.00 by $24,205.00 to the new contract amount of $710,072.00 for the Port Acres Drainage Improvements executed by Arceneaux, Wilson and Cole of Port Arthur, Texas for the Phase I Engineering and Design. "Remember, we are here to serve the Citizens of Port Arthur" P.O.Box 1089 X Port Arthur.Texas 77641-1089 X 409.983.8101 X FAX 409.982.6743 PR No. 21876 3/31/2021 mje Page 1 of 3 RESOLUTION NO. A RESOLUTION AUTHORIZING THE CITY MANAGER TO EXECUTE AMENDMENT NO. 1 THE CONTRACT BETWEEN THE CITY OF PORT ARTHUR AND ARCENEAUX WILSON AND COLE OF PORT ARTHUR, TEXAS FOR THE PORT ACRES SUBDIVISION DRAINAGE IMPROVEMENTS BY INCREASING THE AMOUNT BY $24,205.00 TO A NEW CONTRACT AMOUNT OF $710,072.00 AND INCREASING THE CONTRACT TERM BY 60 DAYS TO A NEW CONTRACT TERM OF 330 DAYS FOR THE ADDITIONAL DESIGN WORK MANDATED BY THE TEXAS DIVISION OF EMERGENCY MANAGEMENT(TDEM)AND THE FEDERAL EMERGENCY MANAGEMENT AGENCY(FEMA). FUNDING IS AVAILABLE IN HMGP ENGINEERING ACCOUNT NO. 154-00-000- 8515-00-10-000 AND CDBG-DR ENGINEERING ACCOUNT NO. 148-00- 000-8515-00-10-000. PROJECT #DR1P03. WHEREAS, the City of Port Arthur obtained funding from Hazard Mitigation Grant Program (HMGP) and Community Development Block Grant— Disaster Recovery (CDBG-DR) to fund the following four(4)drainage projects: (1)El Vista Subdivision, (2)Port Acres Drainage, (3) Lake Arthur Detention and (4) Stonegate Golf Course (Babe Zaharias Golf Course); and, WHEREAS, pursuant to Resolution 20-023, approved by Council, authorizing the City Manager to enter into an agreement with Arceneaux, Wilson and Cole of Port Arthur, Texas for the Phase I Engineering and Design for drainage facilities to serve the Port Acres area in Port Arthur for a fee not to exceed $685,867.00; and, WHEREAS, the Texas Division of Emergency Management (TDEM) and the Federal Emergency Management Agency (FEMA) has mandated that additional technical data, environmental assessments, additional flood modeling, and impact studies be applied to this project; and, WHEREAS, the additional required items by TDEM and FEMA increased the original contract amount of$685,867.00 by $24,205.00 to the new contract amount of$710,072.00 and >:'la'v}er`2021`,PR 21876 Port Acres Co18370.docx PR No. 21876 3/31/2021 mje Page 2 of 3 increasing the contract term by 60 days to a new contract term of 330 days, as attached as Exhibit A; now therefore, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PORT ARTHUR: THAT,the facts and opinions in the preamble are true and correct; and, THAT, the City Council hereby authorizes the City Manager to execute amendment No.1 (attached as Exhibit"A")to the contract between the City of Port Arthur and Arceneaux, Wilson and Cole of Port Arthur, Texas; and, THAT, the original contract amount of$685,867.00 increased by $24,205.00 to the new contract amount of$710,072.00; and, THAT, a copy of the caption of this Resolution be spread upon the Minutes of the City Council. READ, ADOPTED AND APPROVED this the day of , A.D. 2021 at a meeting of the City of Port Arthur, Texas by the following vote: Ayes: Mayor: Councilmembers: Noes: Thurman "Bill" Bartie Mayor PR No. 21876 03/31/2021 mje Page 3 of 3 ATTEST: Sherri Bellard City Secretary APPROVED AS TO FORM: APPROVED FOR ADMINISTRATION: Valecia zeno Ron Burton City Attorney City Manager APPROVED AS FOR AVAILABILITY OF FUNDS: 4.< Kandy Daniel Interim Director of Finance c. Alberto Elefano, P.E. Director of Public Works Ljtiot Clifton Williams, CPPB Purchasing Manager EXHIBIT A AMENDMENT NO. 1 DATE: 04/08/2021 ORIGINAL AGREEMENT DATE: 03/5/2020 ARCENEAUX WILSON & COLE PROJECT DESCRIPTION: Port Acres Drainage Improvements ORIGINAL CONTRACT TERM: 270 days NEW CONTRACT TERM including the AMENDMENT will be approximately 60 days CHANGE TO CONTRACT AMOUNT: $24,205.00 (see attached additional repairs listed) ORIGINAL CONTRACT AMOUNT: $685,867.00 CONTRACT AMOUNT due to this AMENDMENT will be: $710,072.00 Executed this day of April, 2021. ARCENEAUX WILSON & COLE By: Print Name: Title: Executed this day of April, 2021. CITY OF PORT ARTHUR By: Ronald Burton City Manager AIM •4) âVX ARCENEAUX WILSON &COLE Gnyuieerl y uiveyniy ulurvnny March 22, 2021 Mr. Alberto Elefano, PE City of Port Arthur PO Box 1089 Port Arthur, Texas 77641-1089 RE: Proposal for Additional Engineering for Port Acres, Port Arthur, Texas Dear Mr. Elefano, Thank you for requesting our proposal for additional engineering design for drainage facilities to serve the Port Acres area in Port Arthur. Based on our understanding, Arceneaux Wilson & Cole LLC (AWC) will provide a Hydrology and Hydraulics (H&H) report for the Port Acres drainage project designed by AWC. The H&H report will be utilized in the Benefit Cost Analysis (BCA) for the proposed improvements in the Port Acres drainage basin. The area for the H&H report in Port Acres is described and delineated by exhibits provided by Ardurra. For this project, we propose the following Scope of Services: SCOPE OF SERVICES 1. AWC will provide a Hydrology and Hydraulics Report for the Port Acres drainage area in accordance with FEMA guidelines. 2. AWC will perform a survey to determine the finished floor elevation of approximately 460 +/- residences in the Port Acres drainage study area. Deliverables to include address and finish floor elevation for each selected residence. 3. AWC will provide an analysis of the expanded Port Acres drainage area. Analysis will include a water surface elevation for a 25-, 50-, 100-, & 500- year rainfall events at the residences where finished floor elevations are obtained. Analysis data and a summary of the data will be included in the H&H report. 409.724.7888 2901 Turtle Creek Dr.,Suite 320 Port Arthur,TX 77642 Engineering Surveying awceng.com F 16"94 10194049 A .` Tory BREAKDOWN OF ADDITIONAL SERVICES Additional Surveying $12,650 Analysis for Additional Storm Events $11,555 PROPOSED FEE AND SCHEDULE For the services rendered, we propose a maximum fee not to exceed Twenty- Five Thousand Two Hundred Five Dollars ($24,205.00). Please let me know if you have any questions or concerns about the scope, fee, or schedule. We appreciate this opportunity to serve the City of Port Arthur. Very truly yours, ARCENEAUX WILSON & COLE LLC Joe M. Wils n Jr., PE President THURMAN BARTIE,MAYOR RON BURTON CHARLOTTE MOSES,MAYOR PRO TEM City of CITY MANAGER VAL TIZENO COUNCIL MEMBERS: — CITY ATTORNEY ENGRID HOLMES o r t r t h a r CAL J.JONES SHERRI BELLARD THOMAS J.KINLAW,III CITY SECRETARY REV.DONALD FRANK KENNETH MARKS • To: City of Port Arthur Departments of Purchasing, Finance,Legal, Public Works, and City Council From: Ron Burton, City of Port Arthur-City Manager Date: March 24, 2021 Re: Task orders for additional costs incurred for 404 HMGP projects#32, #33,#34 and#109 The City of Port Arthur is seeking federal funding for projects #32—Lake Arthur detention, #33 —Port Acres drainage improvements, #34—El Vista drainage improvements and#109— Stonegate drainage under the 404 Hazard Mitigation Grant Program(I-IMGP). Post submission and review of the Phase I — Engineering and design deliverables by Texas Division of Emergency Management (TDEM) and FEMA, FEMA has mandated that additional technical data be supplied for the four projects - namely H & H studies, environmental assessment, additional flood modeling and impact studies for the projects in relation to the additional protection to be provided. Below is a breakdown of estimated additional cost to fulfil the FEMA requirements by AWC Engineering and Stuart consulting Group, respectively. This is a time sensitive activity and, hence, a task order is needed for these amended costs and activities under the current contracts between the City of Port Arthur and the vendor as identified herein: Contract# Vendor FEMA Project Name Additional Project# project Cost 20-022 AWC Engg 32 El Vista Drainage Improvements $17,305.00 20-023 AWC Engg 33 Port Acres Drainage Improvements $24,205.00 20-020 Stuart Consulting 34 Lake Arthur Detention $113,225.00 20-021 Stuart Consulting 109 Stonegate Drainage $40,525.00 Respec ly @0°r Ron : o City Manager City of Port Arthur 444 4th Street, Port Arthur, TX, 77640 Ph: (409) 983 —8102 Email: ron.burton@portarthurtx.gov Ron Burton,City Manager* ron.burtonritoortarthurtx.gov PO Box 1089*Port Arthur,Texas 77641-1089 THURMAN BARTLE,MAYOR RON BURTON CHARLOTTE MOSES,MAYOR PRO TEM City of L CITY MANAGER t `'" VAL TIZENO COUNCIL MEMBERS: CITY ATTORNEY ENGRID HOLMES o r E r t Ia u r CAL J.JONES SI-LERRI BELLARD THOMAS J.KINLAW,III Texas CITY SECRETARY REV.DONALD FRANK KENNETH MARKS To: The Mayor and City Council From: Alberto Elefano, City of Port Arthur—Public Works Director Date: 4/8/21 RE: FEMA 4332-DR-TX City of Port Arthur HMGP 404 Projects #32, #33, #34, #109 — Reason for additional phase I costs incurred Post the Phase I deliverable submission for projects #32—Lake Arthur Detention, #33 —Port Acres Drainage Improvements, #34—El Vista Drainage Improvements and#109—Stonegate Drainage Improvements, FEMA has reviewed and requested that the City provide additional water surface elevations for each structure, H&H modeling, and foundation details for each of the properties in the project impact area. This has resulted in additional phase I cost for each project. These additional requests are based on new FEMA standards that are being implemented that will evaluate flood insurance premiums not just on risk based on zone but actual elevation information. As the City already has contracts with AWC Engineering for project#33 and#34 and with Stuart Engineering for project#32 and#109, it is recommended to amend the existing contracts with AWC and Stuart engineering to complete the additional work. The increase in cost to meet the FEMA requests will be $195,260. These additional costs were submitted to FEMA as budget amendments for obligation. FEMA will amend the approved budget for the projects which will cover the 75% cost share and the City's remaining 25% responsibility will be reimbursed under the CDBG-DR project. There is no change to the City's responsibility that will impact the City's contribution. Respectfully 6_,4,X C. 6.*--..: Alberto Elefano Public Works Director City of Port Arthur 444 4th Street, Port Arthur, TX, 77640 Ph: (409) 983 — 8189 Email: alberto.elefano@portarthurtx.gov Ron Burton,City Manager*ron.burton@portarthurtx.go,i PO Box 1089*Port Arthur,Texas 77641-1089 ATTACHMENT 2 DESIGN FEE SCHEDULE Design Fees Preliminary Phase (30% Engineering Report) $137, 200 Design Plans Submittal (60%) $200,000 Pre-Final Plans Submittal (90%) $200,000 Final Plans Bid Package Submittal (100%) $138 , 667 Additional TDEM and FEMA requirements $ 24, 205 Bid Phase $ 10 , 000 Engineer Subtotal $710 , 072