INTEROFFICE MEMORANDUM
Date: August 4, 2021
To: The Honorable Mayor and City Council
Through: Ronald Burton, City Manager
From: Donnie Stanton, Interim Director of Utilities
RE: PR 22082—Approval of Change Order 1 for Pioneer Park Lift Station
Introduction:
The intent of this Agenda Item is to seek City Council's approval of Change Order 1 for the
Rehabilitation Project at the Pioneer Park Lift Station. In April of 2021, the Council passed
Resolution No. 21-133, awarding the Rehabilitation of the Pioneer Park Lift Station contract to
BDS Constructors, LLC dba MK Constructors of Vidor, Texas. The project engineer is
Arceneaux, Wilson, & Cole. Change Order 1 is a non-monetary Change Order extending the
contract time for sixty (60) days due to shipping delays by the equipment supplier for the
project's submersible pumps.
Background:
In April of 2021, the Council passed Resolution No. 21-133, awarding the Rehabilitation of the
Pioneer Park Lift Station contract to BDS Constructors, LLC dba MK Constructors of Vidor,
Texas. The project engineer is Arceneaux, Wilson, & Cole. Change Order 1 is a non-monetary
Change Order extending the contract time for sixty (60) days due to shipping delays by the
equipment supplier for the project's submersible pumps.
Budget Impact:
No impact.
Recommendation:
It is recommended that City Council adopt Proposed Resolution No. 22082, which authorizes
the acceptance of Change Order 1 for the Rehabilitation Project at the Pioneer Park Lift Station.
"Remember,we are here to serve the Citizens of Port Arthur"
P. R. No. 22082
08/04/21 bw
Page 1 of 2
RESOLUTION NO.
A RESOLUTION AUTHORIZING THE CITY MANAGER
TO EXECUTE CHANGE ORDER NO. 1 BETWEEN THE
CITY OF PORT ARTHUR AND BDS CONSTRUCTORS,
LLC DBA MK CONSTRUCTORS OF VIDOR, TEXAS,
EXTENDING THE CONTRACT TIME FOR SIXTY (60)
DAYS AT NO ADDITIONAL COSTS, FOR THE PIONEER
PARK LIFT STATION REHABILITATION PROJECT.
WHEREAS, pursuant to Resolution No. 21-133, the City awarded a contract to BDS
Constructors, LLC dba MK Constructors of Vidor, Texas, for the Pioneer Park Lift Station
Rehabilitation Project in the amount of$774,065.00; and,
WHEREAS, the project engineering firm, Arceneaux Wilson & Cole LLC, has
submitted Change Order #1, attached hereto as Exhibit "A", requesting to extend the contract
time by sixty (60) days due to shipping delays by the equipment supplier for the project's
submersible pumps at no additional costs associated.
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE
CITY OF PORT ARTHUR:
THAT,the facts and opinions in the preamble are true and correct; and,
THAT, the City Manager of the City of Port Arthur is hereby authorized to execute
Change Order No. 1 submitted by Arceneaux Wilson and Cole on behalf of BDS Constructors.
LLC dba MK Constructors of Vidor, Texas, extending the contract time for an additional sixty
(60) days due to shipping delays by the equipment supplier for the project's submersible pumps
at no additional costs; and,
THAT, a copy of the caption of this Resolution be spread upon the Minutes of the City
Council.
P. R. No. 22082
08/04/21 bw
Page 2 of 2
READ, ADOPTED, AND APPROVED THIS day of , 2021 at
a Regular Meeting of the City Council of the City of Port Arthur, Texas, by the following vote:
AYES: Mayor ;
Councilmembers ;
NOES:
DONALD FRANK, SR.
MAYOR PRO TEM
ATTEST: APPROVED AS TO FORM:
iddr-d
Sherri Bellard alecia Tizeno
City Secretary City Attorney
APPROVED FOR ADMINISTRATION: APPROVED FOR FUNDING:
Ronald Burton Kandy Dan' 1
City Manager Interim Finance Director
itiWL
Ptii
Donnie Stanton Clifton Williams, CPPB
Interim Utilities Director Purchasing Manager
EXHIBIT A
(Change Order No. 1)
.4w.A
.' ARCENEAUX WILSON&COLE
August 04, 2021
Mr. Donald Stanton
City of Port Arthur
Assistant Director of Utilities
444 4th Street
Port Arthur, Texas 77640
RE.. Proposal For Change Order No. 07 for
PIONEER PARK L/FT STATION REHABILITATION
AWC Job No. CPA-975
Mr. Stanton:
Attached is Change Order No. 1 for the Pioneer Park Lift Station Rehabilitation
project. This change order is for extending the contract time by sixty (60)
calendar days.
The equipment supplier for the project's submersible pumps has informed the
Contractor of a 6-8 week shipping delay beyond the original anticipated delivery
timeframe. The Contractor has currently completed all the necessary submittal
processes for the project. Considering the nature of this lift station rehabilitation,
all of the proposed piping, electrical, and structure modification construction
activities are directly dependent upon the new pump and associated
appurtenances arrival to the site.
This change order and add 60 Calendar Days to the original contract time. There
are no costs associated with this change order. We recommend that the City of
Port Arthur authorize this change order to the contract as submitted. We have
attached Change Order No. 1 which modifies the contract to reflect this change
for your consideration and action.
409.724.7888
2901 Turtle Creek Dr.,Suite 320
Port Arthur,TX 77642 Engineering Surveying
awceng.com F-16194 1 C 194049
a.4
"Airy
Should you have any questions or require additional information, please contact
our office.
ARCENEAUX WILSON&COLE LL C
TEXAS REGISTERED I NGINEERING FIRM F-16 194
Keith zotzky, P. ., CFM
Attached.
Change Order#01
MK Constructors Time Suspension Request
/'_
, avic
/_#'
4.' ARCENEAUX WILSON&COLE
engineering I surveying I Plonnfng
CHANGE ORDER NO. I
DATE: August 4, 2021 JOB NO.: CPA-975
AGREEMENT DATE: April 13, 2021
NAME OF PROJECT: Pioneer Park Lift Station Rehabilitation
OWNER: CITY of PORT ARTHUR
CONTRACTOR: MK CONSTRUCTORS
The following changes are hereby made to the CONTRACT DOCUMENTS:
1. Extend Contract Time by 60 Calendar Days to account for submersible pump delivery delay.
TOTAL $0.00
CHANGE TO CONTRACT PRICE:
ORIGINAL CONTRACT PRICE: $774,065.00
CURRENT CONTRACT PRICE adjusted by previous CHANGE ORDER(S): $774,065.00
The CONTRACT PRICE due to this CHANGE ORDER will be
by: $0.00
The new CONTRACT PRICE, including this CHANGE ORDER, will be $774,065.00
1 of
aim
K.) CHANGE ORDER N .
'" Job No. CPA-975
ARCENEAUX WILSON&COLE
engineering I sunicying I planning
CHANGE TO CONTRACT TIME:
ORIGINAL CONTRACT TIME: 180 Calendar Days
CURRENT CONTRACT TIME adjusted by previous CHANGE ORDER: 0 Calendar Days
CURRENT DATE OF COMPLETION: January 11, 2022
CONTRACT TIME due to this CHANGE ORDER will be increased by 60 Calendar Days
The New DATE OF COMPLETION: March 12, 2022
No other Terms and Conditions of the Contract are changed as a result of this Change Order.
Contractor's acceptance of Change Order relieves OWNER of any liability for additional costs incurred
by Contractor in his performance of the work covered by the Change Order.
RECOMMENDED BY NGINEER: ACCEPTED BY:
S\\\A\c'n \).1.)\)..
ARCENEAUX WIL COLE LLC (CONTRACTOR,OFFICER OR OWNER)
MK CONSTRUCTORS
ACCEPTED BY:
CITY of PORT ARTHUR
fI
2 of 2
Wk. www.mkconstructors.com
CONSTRUCTORS
08/04/21
Keith Zotzky, P.E. (TX, LA),CFM/Project Manager
Keith.Zotzky@awceng.com/281.543.2663
Arceneaux Wilson&Cole LLC
3120 Central Mall Drive
Port Arthur,TX 77642
RE: Pioneer St. Lift Station Time Suspension
Keith,
We have been notified by the pump suppliers for the Pioneer St lift station about a 6 to 8 week delay
from the original delivery schedule. MK is requesting an 8 week time suspension on the project as
discussed at the pre con meeting. Please consider this suspension immediately with time resuming
on September 29, 2021. Contact me anytime with any questions or concerns you may have. Thank
you.