HomeMy WebLinkAboutPR 22112: CHANGE ORDERS #4 THRU #7 FOR REPAIR OF SEVEN PUMP STATIONS City of "
0, , rthu
Texas
www.PortArthurTx.gov
INTEROFFICE MEMORANDUM
Date: August 23,2021
To: The Honorable Mayor and City Council
Through: Ron Burton, Interim City Manager
Kandy Daniel, Interim Finance Director
From: Clifton Williams, Purchasing Manager
RE: P.R. 22112—Change Orders #4 thru 7 for Repair of Seven Pump Stations
Introduction:
The intent of this agenda item is for City Council's approval of Change Orders #4 thru 7 to
Triangle Rotating Equipment Specialist (TRES) in the decreasing amount of $49,445.12 for
Repairs to Seven Pump Stations. The new Contract total is $635,402.62.
Background:
On February 18, 2020, City Council awarded TRES the contract to repair seven Pump Stations
for the amount of$655,581.97 with Resolution 20-051.We submitted to the contractor in phases.
The 1st phase consisted of 3 of the pump stations which totaled$143,522.97. Resolution 20-211
was a change order in the amount of$7,211 for Gulfway Underpass Pump Station in Phasel.
Phase 2 is the El Vista Pump station which was awarded for $151,000. Resolution 21-109 was
the second change order for the rental of the pumps while the new pump and motor were being
delivered. Once work began to repair the Golf Course Pump Station 1 in Phase 4, it was
determined it was better to replace pump rather than repair it. The additional cost will be
$10,650. Resolutions 21-109 was miscalculated for the additional rentals at El Vista. Pump
Station due to some pumps at Montrose running at the same time at Montrose and a mix up in
pricing. El Vista is an additional$3,487.88 and Montrose Pump Station is an additional$44,464.
These additional months were due to delays in delivery for Montrose and waiting for Precision
Pump to install new motor and pump at El Vista Pump Station. Montrose also had additions for
elevation of gear box to avoid flooding., and reductions for aluminum garage door that the City
"Remember,we are here to serve the Citizens of Port Arthur"
444 4th Street X Port Arthur,Texas 77641-1089 X 409.983.8182 X FAX 409.983.8294
had Overhead Door install, the steel guard rails which were done when STI repaired the screen,
and the access road that the City crew repaired. El Vista contract days extended 303 days and
Montrose extended 305 days. Gulfway Underpass Pump Station had to rent pump due to delivery
delays because of covid. That cost is $3,436. Drainage stated they do not need Landfill Pump
Station. It does not give any relevant help with drainage.
Budget Impact:
Amount is charged to the Hurricane Harvey Account # 147-07-015-8515-00-40-000 Project
#DS2617.
Recommendation:
It is recommended that the City of Port Arthur City Council approve PR 22112 authorizing
Change Orders#3 thru 7 with TRES of Orange, Texas decreasing the contract $49,445.12. The
new Contract total is $635,402.62.
"Remember,we are here to serve the Citizens of Port Arthur"
P.O.Box 1089 X Port Arthur,Texas 77641-1089 X 409.983.8101 X FAX 409.982.6743
P.R. No. 22112
08/23/2021 CEWJ
Page 1of3
RESOLUTION NO.
A RESOLUTION AUTHORIZING THE CITY MANAGER TO EXECUTE CHANGE ORDER
NUMBERS 4 THRU 7 TO THE CONTRACT WITH TRIANGLE ROTATING EQUIPMENT
SPECIALIST OF ORANGE, TEXAS FOR PHASES 1 THRU 4 IN THE DECREASING
AMOUNT OF $49,445.12 FOR DELETION OF LANDFILL PUMP STATION AND
ADDITION OF RENTALS FOR A NEW CONTRACT TOTAL OF $635,402.62 AND
EXTENDING CONTRACT 327 DAYS FUNDING IN HURRICANE HARVEY ACCOUNT
NO. 147-07-015-8515-00-40-000, PROJECT NO. DS2617
WHEREAS, on February 18, 2020 per Resolution No. 20-051, the City Council approved a contract
with Triangle Rotating Equipment Specialist (TRES) of Orange, Texas for the repair of seven (7) drainage
pump stations, for a total of $655,581.97; and,
WHEREAS, the seven (7) locations were given out in four (4) phases and TRES is currently in
Phase 4, which totals $150,333 for Golf Pump Station 1 and the Landfill; and,
WHEREAS, Change Order No. 1 for $7,211.20 was awarded per Resolution No. 20-211 on June
23, 2020; totaling $150,734:17 for Phase 1 with a new total of $662,793.17 for all seven locations; and,
WHEREAS, Change Order No. 2 for $11,404.57 was awarded per Resolution No. 21-109 on March
16, 2021; totaling $162,404.57 for Phase 2 with a new total of $674,197.74 for all seven locations; and,
WHEREAS, Change Order No 3 for $10,650.00 was awarded per Resolution No. 21-281 on July
13, 2021; totaling $161,650 for Phase 4 with a new total of $684,847.74 for all seven locations; and,
WHEREAS, Change Order No. 4 (Exhibit "A") is for an additional cost of $44,464.00; totaling
$255,190 for Phase 3 with a new total of $729,311.74 for all seven locations and an additional 305 days
due to waiting for the new pump and motor to be installed by Precision Pump; and,
WHEREAS, Change Order No. 5 (Exhibit "B") is for an additional cost of $3,436.00; totaling
$154,170.17 for Phase 1 and a new total of $732,747.74 for all seven locations; and,
P.R. No. 22112
08/23/2021 CEW3
Page 2 of 3
WHEREAS, Change Order No. 6 (Exhibit "C") is for an additional cost of $3,487.88; totaling
$165,892.25 for Phase 2 and a new total of $736,235.62 for all seven locations and an additional 303
days due to delay in delivering parts due to COVID; and,
WHEREAS, Change Order No. 7 (Exhibit "D") decreases the contract by $100,833.00; totaling
$60,817.00 for Phase 4 and a new total of $635,402.62 for all seven locations and decreases the contract
term by 30 days.
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PORT
ARTHUR:
Section 1. That, the facts and opinions in the preamble are true and correct.
Section 2. That, the City Council herein authorizes the City Manager to execute Change Order
Nos. 4 thru 7 with Triangle Rotating Equipment Specialist of Orange, Texas, for Phases 1 thru 4 decreasing
the total contract amount by $49,445.12 to a new contract total for all seven locations of $635,402.62,
copies of the Change Orders are attached hereto in substantially the same forms as Exhibits "A"thru "D".
Section 3. That, a copy of this caption be spread upon the Minutes of the City Council.
READ, ADOPTED AND APPROVED on this day of August A.D., 2021, at a Regular
Meeting of the City Council of the City of Port Arthur, Texas, by the following vote:
Ayes: Mayor: _
Councilmembers:
NOES:
Thurman "Bill" Bartie
Mayor
CHANGE ORDER NO. 4
ORIGINAL AGREEMENT DATE: August 23, 2021
PROJECT DESCRIPTION: Seven Drainage Pump Stations Phase 3
CHANGE IN SCOPE: Reduction for aluminum door, steel guard rails &road replacement. Addition for
elevation for electrical gear box.
CHANGE TO CONTRACT AMOUNT:
ORIGINAL CONTRACT PRICE: $210,726,00
CURRENT CONTRACT PRICE(adjusted by previous CHANGE ORDER):$210,726.00
The Contract Amount due to this CHANGE ORDER will increase by: $44,464.00
The new CONTRACT AMOUNT including the CHANGE ORDER will be: $255,190.00
ORIGINAL CONTRACT DAYS: 30
NEW CONTRACT DAYS: 365
SIGNED AND AGREED TO on the_day of , 2021.
TRIANGLE ROTATING EQUIPMENT SPECIALIST
Print Name:
Title:
SIGNED AND AGREED TO on the_day of , 2021.
CITY OF PORT ARTHUR
BY:
RON BURTON,
CITY MANAGER
EXHIBIT "B"
CHANGE ORDER NO. 5
ORIGINAL AGREEMENT DATE: August 23, 2021
PROJECT DESCRIPTION: Seven Drainage Pump Stations Phase 1
CHANGE IN SCOPE: Extended days for rental of pumps for bypass due to Covid. And reduction for cost of
wet well.
CHANGE TO CONTRACT AMOUNT:
ORIGINAL CONTRACT PRICE: $143,522.97
CURRENT CONTRACT PRICE(adjusted by previous CHANGE ORDER):S150,734.17
The Contract Amount due to this CHANGE ORDER will increase by: $3,436.00
The new CONTRACT AMOUNT including the CHANGE ORDER will be: $154,170.17
ORIGINAL CONTRACT DAYS: 90
NEW CONTRACT DAYS: 90
SIGNED AND AGREED TO on the_day of , 2021.
TRIANGLE ROTATING EQUIPMENT SPECIALIST
Print Name:
Title:
SIGNED AND AGREED TO on the_day of , 2021.
CITY OF PORT ARTHUR
BY:
RON BURTON,
CITY MANAGER
EXHIBIT "C"
CHANGE ORDER NO. 6
ORIGINAL AGREEMENT DATE: August 23, 2021
PROJECT DESCRIPTION: Seven Drainage Pump Stations Phase 2
CHANGE IN SCOPE: Extended days for rental of pumps for bypass.
CHANGE TO CONTRACT AMOUNT:
ORIGINAL CONTRACT PRICE: $143,522.97
CURRENT CONTRACT PRICE(adjusted by previous CHANGE ORDER):$162,404.57
The Contract Amount due to this CHANGE ORDER will increase by: $3,487.88
The new CONTRACT AMOUNT including the CHANGE ORDER will be: $165,892.25
ORIGINAL CONTRACT DAYS: 30
NEW CONTRACT DAYS: 363
SIGNED AND AGREED TO on the_day of , 2021.
TRIANGLE ROTATING EQUIPMENT SPECIALIST
Print Name:
Title:
SIGNED AND AGREED TO on the_day of , 2021.
CITY OF PORT ARTHUR
BY:
RON BURTON,
CITY MANAGER
EXHIBIT "D"
CHANGE ORDER NO. 7
ORIGINAL AGREEMENT DATE: August 23, 2021
PROJECT DESCRIPTION: Seven Drainage Pump Stations Phase 4
CHANGE IN SCOPE: Remove Landfill Pump Station from contract
CHANGE TO CONTRACT AMOUNT:
ORIGINAL CONTRACT PRICE: $151,000
CURRENT CONTRACT PRICE(adjusted by previous CHANGE ORDER):$161,650
The Contract Amount due to this CHANGE ORDER will decrease by: $100,833.00
The new CONTRACT AMOUNT including the CHANGE ORDER will be: $60,817
ORIGINAL CONTRACT DAYS: 60
NEW CONTRACT DAYS: 30
SIGNED AND AGREED TO on the_day of , 2021.
TRIANGLE ROTATING EQUIPMENT SPECIALIST
Print Name:
Title:
SIGNED AND AGREED TO on the_day of , 2021.
CITY OF PORT ARTHUR
BY:
RON BURTON,
CITY MANAGER