HomeMy WebLinkAboutPR 12073:CRABTREE BARRICADECITY OF PORT ARTHUR PUBLIC WORKS DEPARTMENT Electrical Division COUNCIL ACTION MEMO TO: FROM: SUB.1ECT: DATE: Steve Fitzgibbons, City Manager Leslie E. McMahen, P.E., Director of Public Works P.R. No. 12073 January 31, 2003 RECOM 14 EN DATION: It is recommended that the City Council approve. Proposed Resolution No. 12073 authorizing the City Manager to execute Change Order No. I and Final in the Amount of $6,350.22 to the contract dated September 3, 2002 between the City of Port Arthur and Crabtree Barricade Systems for pavement markings in the City. Funding is available as holdover funds from FY 2002 and current FY 2003 funds in Account No. 001-1205-531.59-00. BACKGROUND: Advertisements for Bids were published on July 28, 2002 and August 4-, 2002, with the contract being awarded to Crabtree Barricade Systems of Beaumont, Texas, as the lowest bidder, on September 3, 2002 in the amount of $27,165.69. The work subject to the Change Order was (1.) striping for two (2) streets recently overlaid by the City; and (2.) railroad crossing symbols for two (2) streets recently overlaid by the City and two (2) older overlay projects. The Change Order amount does not exceed 25% of the original contract amount. The work was necessary to provide the appropriate pavement markings for the recently completed streets. BUDGETARY/FISCAL EFFECT: Funds in the amount of $27,165.69 were held over from FY 2002 Account No. 001-1205-531.59-00 to FY 2003, $6,350.22 of FY 2003 Account No. 001-1205- 531.59-00 will cover this amount in the Change Order. STAFFING/EHPLOYEE EFFECT: None Memo: January 31, 2003 Re; P.R. No. 12073 Page 2 SUMMARY: It is recommended that the City Council approve Proposed Resolution No. 12073 authorizing the City Manager to execute a Change Order No. 1 and Final in the Amount of $6,350.22 to the contract dated September 3, 2002 between the City of Port Arthur and Crabtree Barricade Systems for pavement markings in the City. Funding is available as holdover funds from FY 2002 and current FY 2003 funds in Account No. 001-1205-531.59-00. Leslie E. McMahen, P. E. Director of Public Works iris Word; d:\cams\closeoutstreetstriping P.R. No. 12073 01/31/03klb RESOLUTION NO. A RESOLUTION AUTHORIZING THE CITY MANAGER TO EXECUTE CHANGE ORDER NO. I AND FINAL IN THE AMOUNT OF :$6,350.22 TO THE CONTRACT DATED SEPTEMBER 3, 2002 BETWEEN THE CITY OF PORT ARTHUR AND CRABTREE BARRICADE SYSTEMS FOR PAVEMENT MARKINGS IN THE CITY. FUNDING IS AVAILABLE AS HOLD-OVER FUNDS FROM FY 2002 AND CURRENT FY 2003 FUNDS IN ACCOUNT NO. 00:L- 1205-53:t.59-00. WHEREAS, Crabtree Barricade Systems has completed pavement marking work on various streets in the City of Port Arthur as of December 31, 2002; and, WHEREAS, additional work necessitated by the overlay of four (q) City streets is set out in Change Order No. 1 and Final in the amount of $6,350.22, a copy being attached hereto as Exhibit "A"; and, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PORT ARTHUR, TEXAS: THAT, the City Manager be and he is hereby authorized to execute on behalf of the City of Port Arthur Change Order No. 1 and Final in the amount of $6,350.22 for pavement markings on various streets in the City of Port Arthur; and, THAT, the new contract amount is $33, 515.81; and, THAT, funding for the work is available as hold-over funds from FY 2002 and current FY 2003 funds in Account No. 001-1205-531.$9-00; and, THAT a copy of the caption of this Resolution be spread upon the Minutes of the City Council; and, MS Word: D:\myfiles\resolutions At a Ayes READ, ADOPTED AND APPROVED this the day of P.R. No. 12073 Page 2 ., A. D. 2003 meeting of the City of Port Arthur, Texas by the following vote: Mayor: Noes: Attest: Mayor City Secretary APPROVED AS TO FORM' Mark Sokolow, City Attorney APPROVED AS TO ADMINISTRATION: Steve Fitzgibbons, City Manager Leslie E. McMahen, P.E., Director of Public Works A~UNDS: Rebecca Underhill Finance Director MS Word: D:\myfiles\resolutions CHANGE ORDER EXHIBIT "A' ORIGINA PROJECT: Street Marking; CHANGE ORDER NO: 1 and Final CONTRACTOR: CRABTREE BARRICADE SYSTEMSr INC. P.O. BOX 20195 BEAUMONT, TX 77720 The Contract is changed as follows: Item QuanUb/ 1. 7 2. 13,914 DATE: January 17~2003 CONTRACT DATE: CONTRACT FOR: AucJust 21, 2002 Street Markincj Description Unit Price Extended Price Reft W RxR Xing Item 1 not in original contract. 4"Y SLD Reft. Pav Mrk Item 2 locations of work: Lakeshore Drive from Woodworth to Augusta 32nd Street from Twin City Hwy to Lombardy $ 450.00/ea $ 3,150.00 $ 0.23/ea $ 3,200.22 TOTAL $ 6,350.22 Not valid until signed by the Owner, and Contractor The original Contract sum was ...................................... $ Net change by previously authorized Change Orders ........................ The Contract sum prior to this Change Order was ........................ $ The Contract sum will be increased by this Change Order in the amount of ........ $ The new Contract Sum including this Change Order will be .................. $ 27~165.59 27,165.59 6,350.22 33,515.81 The Contract Time will be increased by zero (0) days. The date of Substantial Completion as of the date of this Change Order therefore is Unchanged NOTE: The summary does not reflect changes in the Contract Sum or Contract Time which have been authorized by Construction Change Directive. CRAB'TREE BARRICADE SYSTEMS, INC. P.O. BOX 20195 City of Port Arthur P.O. Box 1089 ~ Arthur, Texas 77641 By: Date: EXCEL: Change Order