HomeMy WebLinkAbout(D2) Utilities Dept Capital ProgramProject
Name
Project
Description Engineering Firm
Year
Project
Funded
Project
Cost
Engineering
Status
Construction
Status Notes
Main WWTP - Procter Main WWTP Design FNI 6/24/2015 6,995,000$ 100%TWDB Approved Design in
September 2021
Main WWTP - Procter Main WWTP Construction Awaiting Bids for
Construction 4/29/2020 60,560,000$ 0%
Will be Advertised for Bids in
October 2021.
(Qualified for $4,250,000 of Loan
Forgiveness)
Sanitary Sewer Collection
System Rehabilitation
Replace Sanitary Sewer
Lines, Manholes and
Service Lines City Wide
In-house design/
Golden Triangle
Consulting Engineers
6/17/2021 1,000,000$ 20% 0%
Staff Evaluating Different Areas for
this Project.
Will Advertise for Bids in
December 2021
Sabine Pass Sanitary Sewer
Collection System
Pipeburst Sanitary Sewer Pipe
and Replace Manholes and
Service Lines in Sabine Pass
In-house design/
Golden Triangle
Consulting Engineers
6/17/2021 500,000$ 50% 0%
SSOI Approved by TCEQ in
September 2021.
Will Advertise for Bids in
December 2021
Lakeside Gravity Sewer Main Replace Sanitary Sewer
Lines on Lakeside Soutex Surveyors 6/17/2021 300,000$ 90% 0%Will Advertise for Bids in
December 2021
El Vista Force Main El Vista Sewer Force Main AWC 6/17/2021 1,700,000$ 95% 0%
Waiting for Permits from Railroad.
Will Advertise for Bids in
December 2021
Hwy 365 Force Main Hwy 365 Sewer Force Main SPI 6/17/2021 3,000,000$ 10% 0%
Phase 1 of Engineering will be
Completed by February 2022
46th Street Force Main 46th Street Force Main AWC 6/17/2021 1,000,000$ 100% 90%
Construction to be Completed in
October 2021
Landfill New Water Line Landfill Water Line AWC 2,400,000$ 95% 0%
Waiting for Permits from Army
Corps of Engineers.
TxDot Permits Issued.
Total 2021 COs 9,900,000$