HomeMy WebLinkAbout(P1) USACE_SWG_Port Arthur_Port Arthur City Council Presentation_FinalCharles Wheeler
Project Manager
US Army Corps of Engineers
10/8/2021
SABINE PASS TO GALVESTON BAY, TEXAS COASTAL STORM RISK MANAGEMENT
PORT ARTHUR AND VICINITY (PAV)PROJECT OVERVIEW Hurricane Ike –9/13/08 ~ HWY 73 Rainbow Bridge
Hurricane Ike–HWY 73 Taylor Bayou
2
AGENDA
•Coastal TX Resiliency Plan
•Project Purpose and History
•Project Delivery Team
•Project & Contract Overview
•Future Public Information Sessions
•Questions & Closing
3
10/8/2021
4
SABINE PASS TO GALVESTON BAY STUDY
Focused: Examined CSRM problems and
opportunities for the Sabine Region (Orange
and Jefferson Counties) and the Brazoria
Region (Freeport Vicinity).
Study Sponsor
Texas General Land Office
Implementing Sponsors
Orange County (Design only)
Jefferson County Drainage District 7 (Port
Arthur)
Velasco Drainage District (Freeport)
5
▪2005 Hurricane Rita
•111 deaths/$10 billion in losses
▪Tropical Storm Allison
•41 deaths/$5 billion in losses
▪1900 Galveston Storm
•6000 deaths/$20 million in losses
▪2017 Hurricane Harvey (Initiated push for BB18)
•2nd most destructive in US history
•107 deaths
•Thousands of homes destroyed
•$125 billion in losses
▪2008 Hurricane Ike
•3rd most destructive in US history
•112 deaths
•Thousands of homes destroyed
•$29 billion in losses
Since 1854, 64 tropical storms have hit the Upper TX Coast
STUDY PURPOSE
6
PROJECT HISTORY AND TIMELINE
2011/12 -Identification of new Non-Federal Sponsor (TX GLO) and re-scoping efforts to increase study area.
2013 -Feasibility Cost Share Agreement signed by GLO / Study resumes
2015 -Tentatively Selected Plan identified
2017 -Final Report submitted for approval
2018 –Bipartisan Budget Act of 2018 signed into law
2019 –Sign Project Partnership Agreement (November 19)
2020 –Awarded 1st Construction Contract (March 20)
First
Construction
Contract
Mar 2020
5-Contract
Awards
2022-2024
Construction
2020-2026
Project
Partnership
Agreement
Nov 2019
7
PROJECT FUNDING
Project Name Federal cost Non-Federal cost
Estimated total cost
to complete the
project
Sabine Pass to Galveston Bay,TX -Freeport-Design and
Construction $457,687,000 $246,447,000 $704,134,000
Sabine Pass to Galveston Bay,TX -Port Arthur -
Design and Construction $560,950,000 $302,050,000 $863,000,000
Sabine Pass to Galveston Bay,TX -Orange -
Design and Construction $1,553,500,000 $836,500,000 $2,390,000,000
TOTAL $2,572,137,000 $1,384,997,000 $3,957,134,000
86th TEXAS Legislature
•Directs $200M to the GLO for required costs associated with USCAE projects and
studies.
•Port Arthur and Vicinity (DD7) ~ $106 M
•Orange County ~$54 M
•Freeport and Vicinity (VDD)~$ 40 M
8
PROJECT DELIVERY TEAM
USACE Galveston District PDT
U.S. Army Engineer Research and Development
Center--(ERDC)
Regional Planning and Environmental Center
(RPEC)
Non-Federal Sponsor:
Jefferson County Drainage District No. 7 (DD7)
USACE-Chicago District (LRD)USACE-New Orleans District
USACE-Buffalo District (LRB) USACE-Memphis District (MVD)
PAV03A Design Contractor “AE”PAV01 Construction Contractor
9
10/8/2021
ENGINEERING AND DESIGN ANALYSIS
Ship Induced Wave Flooding
Port Arthur Interior Drainage
ERDC Hurricane Impact Modeling
Storm Modeling
ERDC Elevation Modeling
Port Arthur Floodwall Scour Failure Analysis
10PORT ARTHUR –OVERVIEW
Contract #Scope
PAV01 1.1 miles levee raise
PAV02 0.2 miles floodwall
replacement
PAV03 0.1 miles levee raise, 1.0
miles floodwall
replacement, 11 gates
PAV03A 3.3 miles levee raise, 1.9
miles floodwall
replacement, 1 gate
PAV03B 0.02 miles levee raise, 0.5
miles floodwall
replacement, 7 gates
PAV04 0.4 miles levee raise, 0.4
miles new levee, 2.0 miles
floodwall replacement, 3
gates
Contract Award Const
Complete
PAV01 Mar-20 (A)Dec-21
PAV02 Aug-23 Aug-24
PAV03 Apr-22 Dec-25
PAV03A Jun-22 Nov-24
PAV03B Mar-22 Jan-24
PAV04 Apr-23 Oct-26
11
❑Scope:1.1 miles levee raise
❑Landowners:
−Valero
❑Status:In construction (Forgen
Construction)
❑Schedule
−Const Award:Mar 20 (A)
−Const Comp:Dec 21
PORT ARTHUR PAV01 –OVERVIEW1
1
12
❑Scope:0.2 miles floodwall
replacement
❑Landowners:
−GLO/Valero/Union Pacific
Railroad
❑Status:
−Preliminary design
−Jefferson County Drainage
District No.7 conducting
Geotech and Survey
−Evaluating 3 alternatives
before proceeding with design
❑Schedule
−Const Award:Aug 23
−Const Comp:Oct 24
PORT ARTHUR PAV02 –OVERVIEW1
2
13
❑Scope:1.0 mile floodwall
replacement,0.1 mile levee raise,
8 gates
❑Landowners:
−Valero
❑Status:
−USACE finalizing 100% design
❑Schedule:
−Const Award:Apr 22
−Const Completion:Dec 25
PORT ARTHUR PAV03 –OVERVIEW1
3
14
❑Scope:3.3 miles levee raise,1.9
miles floodwall replacement,1
gate
❑Landowners:
−Motiva,Kinder Morgan,DD7,TX
Gas,Chevron,Union Pacific RR,
Kansas City Southern RR,
Centana Pipeline,GT Pipeline,
City of Port Arthur
❑Status:
−A-E (Freese and Nichols,CDM
Smith,and COWI)submitted
95%design
−Will be performing a deep dive
of construction sequencing
❑Schedule
−Const Award:Jun 22
−Const Completion:Nov 24
PORT ARTHUR PAV03A –OVERVIEW1
4
15
❑Scope:0.02 miles levee raise,0.5
miles floodwall construction,5
Gate Structures
❑Landowners:
−Port of Port Arthur,Kansas City
Railroad
❑Status:
−USACE updating 100%design
❑Schedule
−Const Award:Mar 22
−Const Completion:Jan 24
PORT ARTHUR PAV03B –OVERVIEW1
5
16
❑Scope:
−Original Scope:0.4 miles levee
raise,0.4 miles new levee,2.0
miles floodwall replacement,3
gates
−Revised Scope: 11.3 miles
levee raise,3.0 miles new
levee,2.0 miles floodwall
replacement,3 gates,5 pump
station fronting protection
❑Landowners:
−TBD
❑Status:
−Preliminary design
−Design Charrette held week of
15 September to identify final
SCOPE of project phase
❑Schedule
−Const Award:Apr 23
−Const Completion:Oct 26
PORT ARTHUR PAV04 –OVERVIEW1
6
17
FUTURE PUBLIC INFORMATION SESSIONS
Port Arthur Public Outreach
First virtual public information session: 27/28 October 2021
https://www.swg.usace.army.mil/S2G/
QUESTIONS
19