Project Update
Parks and Recreation Department
SSgt. Lucian Adams Park
Project Update
March 2021
➢Updated topographic survey
April 2021
➢Theft of electrical copper wiring
➢Received quote on electrical repairs in the amount of $84,395.68
➢Received completed conceptual drawings for the proposed project
May 2021
➢Voters approved the proposition
➢Adjuster from TML came to investigate the electrical repairs
June 2021
➢Reached out to contractor regarding quote
➢Temporary disconnect was requested
SSgt. Lucian Adams Park
Project Update
July 2021
➢Concession stand and press box was demolished
August 2021
➢Received a quote from Bennett Electric for electrical repairs in the
amount of $690,097.08
➢Received check from TML in the amount of $67,450.72
➢Began conversations regarding receiving dirt from other entities
September 2021
➢Parks and Recreation staff and Purchasing staff met with Bennet Electric
regarding electrical repairs
➢Updated quote was submitted to TML
October 2021
➢Received an updated quote from Bennett Electric for electrical
materials in the amount of $273,209.44
Demolished Concession Stand
Conceptual Drawing
Conceptual Drawing
Conceptual Drawing
City Owned Property
Next Steps
Continue conversations with local entities regarding obtaining dirt
Master Plan