INTEROFFICE MEMORANDUM
Date: November 29, 2021
To: The Honorable Mayor and City Council
Through: Ron Burton; City Manager
From: Flozelle C. Roberts, EIT, Meng, MBA; Director of Public Works
RE: P.R. 22087: Sunken Court Roadway Reconstruction Project from Twin City Highway to
North Park Drive, Close Out and Release of Retainage; Project No.: ST1 P02.
Introduction:
The intent of this Agenda Item is to authorize the City Manager to accept the Close Out Documents and
release Retainage in the amount of$104,694.92for the Sunken Court Roadway Reconstruction Project from
Twin City Highway to North Park Drive.
Background:
Pursuant to Resolution No. 19-412,Excavation&Construction,LLC of Port Arthur,Texas was awarded the
project for the Sunken Court Reconstruction Project from Twin City Highway to North Park Drive. Change
Order No. 1 was approved by Council pursuant to Resolution 20-026 that increased the original contract
amount of$2,268,343.13 by $41,225.48 to the new contract amount of$2,309,568.61 for the removal and
replacement of an existing waterline. Change Order No. 2 was approved by Council pursuant to Resolution
20-146 for a waterline tie-in at Bernhardt Drive that increased the contract amount by $11,206.66 to the new
contract amount of$2,320,775.27. Change Order No. 3, approved under Resolution 20-164, increased the
original contract amount of $2,320,775.27 by $20,515.12 to the new contract amount of$2,341,290.39.
Change Order No. 3 also extended the time of completion by adding 60 calendar days to the original
completion date June 21, 2020 changing it to the new completion date of August 20, 2020. Change Order
No. 4, approved under Resolution No. 20-440,added an additional 73 calendar days to the original contract
time due to inclement weather(43 days)and COVID-19(30 days)amending the original contract completion
date of August 20, 2020 to the new contract completion date of October 16, 2020. Additionally, Change
Order No. 4 addressed 24 days of Contract Time Overage assessed at $500.00 per day for the amount of
Liquidated Damages totaling $12,000.00.
"Remember,we are here to serve the Citizens of Port Arthur"
444 4th Street X Port Arthur,Texas 77641-1089 * 409.983.8182 X FAX 409.983.8294
Change Order#5 is being submitted by Excavation & Construction, LLC of Port Arthur, Texas to reflect a
deduct in the amount of$352.00 amending the old contract amount of$2,341,290.39 to the new contract
amount of $2,340,938.39. Retainage for this project is $117,046.92 less the Liquidated Damages of
$12,000.00 and less an overpayment of $352.00 (Check #396053; dated 11/10/2021) making the final
retainage amount due and payable of$104,694.92.
The City of Port Arthur has also received Close Out Documents from Excavation& Construction, LLC
of Port Arthur, Texas that includes the Engineer's Certificate of Substantial Completion establishing
completion as November 24,2020,the Contractor's Certificate and Release,the Contractor's Certificate
of Warranty, and the Contractor's Certificate of Debts Paid.
Budget Impact:
Funds are available in the Capital Improvement Account for Street Maintenance and Repair, Account
No. 307-21-053-8517-00-10-000. Project No. ST1P02.
Recommendation:
It is recommended that the City of Port Arthur City Council approve PR 22087 with Excavation &
Construction, LLC of Port Arthur, Texas authorizing the City Manager to accept the Close Out documents
and release retainage in the amount of$104,694.92.
"Remember, we are here to serve the Citizens of Port Arthur"
P.O.Box 1089 X Port Arthur,Texas 77641-1089 X 409.983.8101 X FAX 409.982.6743
PR No. 22087
11/29/2021 flue
Page 1 of 5
RESOLUTION NO.
A RESOLUTION AUTHORIZING THE CITY MANAGER TO EXECUTE
CHANGE ORDER NO. 5 DECREASING THE ORIGINAL CONTRACT
AMOUNT BY $352.00 TO A NEW CONTRACT AMOUNT OF
$2,340,938.39 AND ACCEPTANCE OF THE ENGINEER'S
CERTIFICATE OF SUBSTANTIAL COMPLETION, CONTRACTOR'S
CERTIFICATE AND RELEASE, CONTRACTOR'S CERTIFICATE OF
WARRANTY, CONTRACTOR'S AFFIDAVIT OF ALL DEBTS PAID TO
THE CONTRACT BETWEEN THE CITY OF PORT ARTHUR AND
EXCAVATION &CONSTRUCTION, LLC OF PORT ARTHUR, TEXAS FOR
THE SUNKEN COURT ROADWAY RECONSTRUCTION PROJECT FROM
TWIN CITY HIGHWAY TO NORTH PARK DRIVE AND APPROVAL OF
RELEASE OF RETAINAGE, LESS $12,000.00 FOR LIQUIDATED
DAMAGES, AND LESS $352.00 OVERPAYMENT, FOR THE AMOUNT
OF $104,694.92 FROM THE CAPITAL IMPROVEMENTS STREET
MAINTENANCE AND REPAIR ACCOUNT NO. 307-21-053-8517-00-
10-000. PROJECT NO. ST1P02.
WHEREAS, pursuant to Resolution No. 19-412, the City of Port Arthur City Council
awarded a contract for the Sunken Court Reconstruction Project from Twin City Highway to
North Park Drive to Excavation & Construction, LLC (Contractor) of Port Arthur, Texas with a
projected budgetary impact of $2,268,343.13 and a term of 230 calendar days; and,
WHEREAS, pursuant to Resolution No. 20-026, the City of Port Arthur City Council
approved Change Order No. 1 submitted by Excavation &Construction, LLC of Port Arthur, Texas
for the removal and replacement of an existing water line that increased the contract amount
by $41,225.48 from the original contract amount of $2,268,343.13 to the new contract amount
of $2,309,568.61; and,
WHEREAS, pursuant to Resolution No. 20-146, the City of Port Arthur City Council
approved Change Order No. 2 submitted by Excavation &Construction, LLC of Port Arthur, Texas
for the waterline tie-in at Bernhardt Drive that increased the contract amount by $11,206.66
PR No.22087
1 1/29/2021 mje
Page 2 of 5
from the original contract amount of $2,309,568.61 to the new contract amount of
$2,320,775.27; and,
WHEREAS, pursuant to Resolution No. 20-164, the City of Port Arthur City Council
approved Change Order No. 3 submitted by Excavation &Construction, LLC of Port Arthur, Texas
that increased the original contract amount of $2,320,775.27 by $20,515.12 to the new contract
amount of $2,341,290.39 and added 60 calendar days changing it to the new contract
completion date of August 20, 2020; and,
WHEREAS, pursuant to Resolution No. 20-440, the City of Port Arthur City Council
approved Change Order No. 4 submitted by Excavation &Construction, LLC of Port Arthur, Texas
that addressed inclement weather (43 days) and the effects of COVID-19 on personnel
availability (30 days) that added 73 calendar days to the original contract completion date of
August 20, 2020 to the new contract completion date of November 1, 2020 resulting in contract
time overage and liquidated damages in the amount of $12,000.00; and,
WHEREAS, the City has received Change Order No. 5, Exhibit A, submitted to reconcile
all bid items on the project and will decrease the original contract amount by $352.00 to the
new contract amount of $2,340,938.39 along with the Engineer's Certificate of Substantial
Completion dated November 24, 2020 and the work to which the Certificate applies has been
inspected, authorized, and declared to be complete in accordance with the contract documents
and made a part hereof as Exhibit B; together with the Contractor's Certificate of Release (Exhibit
C), the Contractor's Certificate of Warranty (Exhibit D), the Contractor's Certificate of Debts Paid
(Exhibit E); and,
PR No. 22087
1 1/29/2021 mje
Page 3 of 5
WHEREAS, the retainage for the project is 5% of the work completed and billed, the
Release of Retainage has been submitted by Excavation & Construction, LLC of Port Arthur,
Texas $117,046.92, see Exhibit F; and,
WHEREAS, Liquidated Damages, approved by Council under Resolution No. 20-440, in
the amount of $12,000.00 along with an overpayment of $352.00 (Check #396053; dated
November 11, 2021) will be deducted from the retainage amount making the final amount of
retainage due and payable of $104,694.92; and,
WHEREAS, Excavation & Construction, LLC of Port Arthur, Texas has completed the
contracted project to the satisfaction of the Public Works Director and the City Engineering staff,
see Exhibit G; and,
WHEREAS, approval of Change Order No. 5 along with the acceptance of the Close Out
Documents, and Release of Retainage is herein deemed an appropriate action; now, therefore,
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PORT ARTHUR:
THAT, the facts and opinions in the preamble are true and correct; and,
THAT, the City Council hereby authorizes the City Manager to execute Change Order No.
5 submitted by Excavation & Construction, LLC of Port Arthur, Texas to reconcile all bid items
on the project and will decrease the original contract amount by $352.00 to the new contract
amount of $2,340,938.39, Exhibit A; and,
THAT, the City Council hereby accepts the Engineer's Certificate of Substantial
Completion dated November 24, 2020 (Exhibit B); together with the Contractor's Certificate of
Release (Exhibit C), the Contractor's Certificate of Warranty (Exhibit D), the Contractor's
Certificate of Debts Paid (Exhibit E); and,
PR No. 22087
11/29/2021 mje
Page 4 of 5
THAT, the City Manager of the City of Port Arthur is hereby authorized to execute on
behalf of the City of Port Arthur a Certificate of Acceptance (Exhibit H) for the completion of the
Sunken Court Roadway Reconstruction Project from Twin City Highway to North Park Drive; and,
THAT, the Release of Retainage be paid to Excavation &Construction, LLC of Port Arthur,
Texas in the amount of $104,694.92; and,
THAT, a copy of the caption of this Resolution No. be spread upon the Minutes of the
City Council.
READ, ADOPTED AND APPROVED this the day of , A.D. 2021 at
a meeting of the City of Port Arthur, Texas by the following vote:
Ayes: Mayor:
Councilmembers:
Noes:
Thurman "Bill" Bartie
Mayor
ATTEST:
Sherri Bellard
City Secretary
PR No.22087
11/22/2021 mje
Page 5 of 5
APPROVED AS TO FORM: APPROVED FOR ADMINISTRATION:
146(
Valecia Tizeno Ron Burton
City Attorney City Manager
APPROVED AS FOR AVAILABILITY OF
FUNDS:
Kandy DanielY
Interim Director of Finance
Flozelle Roberts, EIT, MEng, MBA
Director of Public Works
I .1
( /(k GAA
Clifton Williams, CPPB
Purchasing Manager
EXHIBIT A
CITY OF PORT ARTHUR
DATE: June 30,2021
PROJECT: SUNKEN COURT ROADWAY RECONSTRUCTION
OWNER: CITY OF PORT ARTHUR
CONTRACTOR: EXCAVATORS AND CONSTRUCTORS,LLC.
CHANGE ORDER NO.: OS
THE FOLLOWING CHANGES IN THE PLANS AND/OR SPECIFICATIONS ARE HEREBY MADE:
Add/Delete Construction Items and/or quantities to the Contract:
Rem New Item Original New Unit
No. Item Code Description Unit Dirt. Amount
Quantity Quantity Price
PAVING AND DRAINAGE
DEDUCTION
14 644.001 Small Roadside Assemblies EA 43 30.0 113.0) S546.25 (57,101.25)
15 666.002 Rellecturiaed Pavement Markings LF 4,621 4,600 (21.0) S1.44 ($30.24)
'
16 678.002 Pavement Surface Preparation LF 4,620 4,600 (20.0) SOSB (S17,60)
32 465.003 Standard Type"C"Catch Basin(with two extensions) EA 2 0 12.0) 58,050.00 (SI6,I00.00)
35 5265.002 Furnish and Install 24"HOPP LF 421 391 (30.0) S80.02 IS2,400.60)
TOTAL AMOUNT DEDUCTED (S25,643.69)
ADDITION
11 666.001 Crosswalk Striping LF 563 1,136 573,0 59.20 S5,271.60
30 465.001 Standard Type"C"Catch Basin EA 2 4 2,0 54,025,00 S8,050.00
33 465,001 Junction Box constructed of reinforcnl concrete FA 3 4 I.0 S5,750.00 S5,750.00
TOTAL AMOUNT ADDED S19,071.60
UTILITIES +
DEDUCTION
10 809.001 Testing and Sterilisation of Water llnes IF 2,030 1,990 (60.0) SLIS 1569.00)
25 811.002 Furnish and Install 4"Gate Valve EA 2 0 (10) S618.59 (51,237.18)
34 5165.001 Furnish and Insult 18"ROPP LF 757 687 170.0) S64.26 154,498.20)
TOTAL AMOUNT DEDUCTED •
(S5,80438)
ADDITION
17 810.001 Remove and Replace misting 2"Waterline LF . 20 20.0 $1631 $326,20
18 810.002 Remove and Replace Existing 6"Waterline LF 1,860 1913 53.0 S39.49 S2,091.97
23 810.004 Connect to Existing Waterline _ EA 8 9 1.0 S4.128.78 S.128.78
26 811.003 Furnish and install 6"Gate Valle EA 8 9 1.0 S769.66 S769.66
48 811.008 Furnish and Install 6"45 Degree Band EA 2 4 2.0 S951.59 $1,903.18
50 Sl I.010 Furnish and Install 6":2"Reducer EA - 2 2.0 SN9A3 $1,698.84
31 811.011 Furnish and Install 2"C.oupiing EA 2 IV 5552.42 S1,104.84
TOTA1.AMOUNT ADDED 512,024.47
TOTAI.AMOUNT DEDUCTED FROM CONTRACT (S31,448.07)
TOTAL AMOUNT ADDED TO CONTRACT S31,096.07
CHANGE ORDER TOTAL AMOUNT ,a3:;.,10)
ORIGINAL CONTRACT AMOUNT: S1,268,343.13
NET FROM PREVIOUS CHANGE ORDERS:1.2,3,4 S72,947,26
TOTAL AMOUNT OF THIS CHANGE ORDER: S352,00
PERCENT OF THIS CHANGE ORDER: -0.0155%
TOTAL PERCENT CHANGE ORDER TO DATE: 3.20%
NEW CONTRACT AMOUNT: S2,340,938.39
NO CALENDAR DAYS HAVE BEEN ADDED IN THE CONTRACT BY THIS CHANGE ORDER
Troy U'"�" "M clo-�..r
ACCEPTED BY: RED BY: - .r-o4".w
Whitehead o,.:,,.e,0.,,,>nm;,
EXCAVATORS AND CO UCTORS,LLC. SCHAUMBURG&POLK,INC.
APPROVED BY:
PUBLIC WORKS
Flozelle C.Roberts,
E.I.T,M.Eng.,M.B.A,Public Work Director
ATTESTED BY:
RON BURTON CLIFTON WILLIAMS.CPBB
EXHIBIT B
CERTIFICATE OF SUBSTANTIAL COMPLETION
Purchase Order No.: 217678
Project Name: Sunken Court Roadway Reconstruction Project
Contractor: Excavation and Construction,LLC
Description of Work: Reconstruction of roadway between North Park Drive and Twin City Hwy/Hwy 347.
The work performed under this contract has been reviewed and found to be substantially complete.
The date of substantial completion is hereby established as November 24,2020.
KNOW ALL MEN BY THESE PRESENTS:
1.) The stage of construction where,in the opinion of the City of Port Arthur,all items of the work necessary
to enable the assets to be utilized without restrictions for the purpose for which the asset was
constructed have been completed;and
2.) All pay items are complete and all necessary testing as required by the Laws and regulations and/or
Contract Documents have been completed.
Punch List
A list of items to be completed or corrected,prepared by the CONTRACTOR and verified and amended by the
ENGINEER,is attached hereto.The failure to include any items on such list does not alter the responsibility of the
CONTRACTOR to complete all work in accordance with the contract documents.The CONTRACTOR shall complete
or correct the work on the list of items attached hereto within 60 days from the above date of substantial
completion.The responsibilities shall be as set out in the Contract Documents or on the attached hereto. If not
specified in an attachment or in the Contract Documents the CONTRACTOR is responsible for maintenance,
utilities and
,(insuranc/e.,� ( C� / i
"�icc,.dot t f t/ �� . lJ'.S J`►�4 1y t ��I� _ l '/ �� 1 CONTRACTOR NAME SIGNATURE DATE
RECOMMENDED FOR ACCEPTANCE
i7--7 TtL 7-4'
1?"-GAL, -LW -z7- 2/
ENGINEER NAME GNA'f'URE DATE
The City of Port Arthur accepts the work as Substantially Complete.
City of Port Arthur,Department of Public Works.
PROJECT MANAGER SIGNATURE DATE
CITY ENGINEER SIGNATURE DATE
PUBLIC WORKS DIRECTOR SIGNATURE DATE
EXHIBIT C
CONTRACTOR'S CERTIFICATE AND RELEASE
FROM.: E/K u' f Cpn f v G ! n� �LC
(Name of Contractor)
TO:
(Owner)
REFERENCE CONTRACT NO.: 19-239
CONTRACT ENTERED INTO THE DAY OF , BETWEEN
THE CITY OF PORT ARTHUR AND
OF
FOR THE SUNKEN COURT ROADWAY RECONSTRUCTION PROJECT
KNOW ALL MEN BY THESE PRESENTS:
1) The undersigned hereby certifies that there is due from,and payable by,the Owner to the Contractor under
the contract and duly approved Change Orders and modification the balance of$117,046.92.
2) The undersigned further certifies that in addition to the amount set forth in Paragraph 1, there are
outstanding and unsettled the following items which he claims are just and due and owing by the Owner
to the Contractor:
a.
b.
c.
d.
(Itemize claims and amounts due) (If none,so state)
3) The undersigned further certifies that all work required under this contract, including work required under
Change Order(s) numbered 1-5 , has been Performed in accordance with the terms thereof, and that
there are no unpaid claims for material,supplies,or equipment and no claims of laborers or mechanics for
unpaid wages arising out of the performance of this contract, and that the wage rates paid by the
contractor were in conformity with the contract provisions relating to said wage rates.
4) Except for the amounts stated under Paragraphs 1 and 2 hereof,the undersigned has received from the
Owner all sums of money payable to the undersigned under,or pursuant to,the above-mentioned contract
or any modifications or changes thereof.
5) That in consideration of the payment of the amount stated in Paragraph 1 hereof,the undersigned does
hereby release the Owner and Operator from any and all claims arising under or by virtue of this contract,
except the amount listed in Paragraph 2 hereof due from the Owner, provided however, that if for any
reason the Owner does not pay in full he amount stated in Paragraph 1 hereof, said deduction shall not
affect the validity of this release, but the amount so deducted shall be automatically included under
Paragraph 2 as an amount which the Contractor has not released but will release upon payment thereof.
The Contractor further certifies that upon the payment of the amount listed in Paragraph 2 hereof,and of
an amount which may be deducted from Paragraph 1 hereof,he will release the Owner and Operator from
any and all claims of any nature whatsoever arising out of said contract of modification thereof, and will
execute such further releases or assurances of the Owner and Operator may request.
4
IN WITNESS WHEREOF,the undersigned has signed and sealed this instrument this 1 day of
pr ,2021.
(SEAL) FXCC VLI$'.koin `. CorY/ rVGItor)LLc-
(Contractor)
BY: .'
(Signature and Title of 0 Icer)
, being first duly sworn on oath,deposes and says,first,that he is the
yaw t
vct Ai 0
fr74 n r k^ of Con cif c,c/ inn ,second,that he has read the foregoing certificate by him
rtle) (Name of Company) ff
subscribed as /41 G n(t of X[ a . ,, r,U n `. Co (vc j re .
(Name of Company)
Affiant further states that the matters and things stated herein are true.
4-eAfa
nt)
Subscribed and sworn to before me this day of'p 2021.
My commission expires 1- `^-
U(2c/t/ U9a,11611L---
(Notary)
i5S
EXHIBIT D
CONTRACTOR'S CERTIFICATE OF WARRANTY
�!
FROM: E�Ca ✓C4 �r(�n e-o '1STl vL- ;ron
(Name of Contractor)
TO:
(Owner)
REFERENCE CONTRACT NO.: 19-239
CONTRACT ENTERED INTO THE DAY OF_ , BETWEEN
THE City of Port Arthur,Texas AND K c 4 r c, ]f •D r . C O n5f l vc J<,(0►/7
OF
FOR THE SUNKEN COURT ROADWAY RECONSTRUCTION PROJECT
KNOW ALL MEN BY THESE PRESENTS: _r
1) Ei C u v ci 3b 1 e on5)-�� %C n,does hereby guarantee all of the work done under the above
(Contractor)
referenced contract to be free from faulty materials in every particular, and free from improper
workmanship,and against injury from proper and usual wear;and agrees to replace or re-execute without
cost to the Owner and Operator such work as may be found to be improper or imperfect,and to male good
all damage caused to other work or materials,due to such required replacement or re-execution.
2) This guarantee shall cover a period of one (1) year from the date of acceptance of all work under this
contract,as evidenced by the Contractor's Certificate of Completion.
3) This Certificate is given in connection Qf the final payment under the contract between the Owner and
r'c et v cl lf'tr , • et,„1 2tf(-7-4.rT n,and with the knowledge that it will be relied upon in making
such payment ant that such payment would not be made except upon the truth of the matter contained
in this affidavit.
5"r
IN WITNESS WHEREOF,the undersigned has signed and sealed this instrument this day of
YJt1 ,2021.
SEAL FXrG{.VC: 7�{On s l9rao"c-1-0')
(Contractor)
BY: Atr,//
(Signature and Title o,Officer)
44tiAd his being first duly sworn on oath,deposes and says,first,
(Afrwnt) r
That he is the /i Qn 4 9 G f of j c et act )1,G' I- Cow/c'vc-1 F-rtecond,that he has read the
(Title) (Name of Company) ,,��//
foregoing certificate by him subscribed as /('i c n CGS t.C of Fx Ca✓�r i p.t r Disk.,r X,ru'r
(Name of Company)
Affiant further states that the matters and things stated herein are true.
,gj-et( /(-$77:
(Afftant)
Subscribed and sworn to before me this )6 day of 2021.
My commission expires C'_ .
U/1211 & "I
(Notary)
5
its3
EXHIBIT E
CONTRACTOR'S CERTIFICATE OF DEBTS PAID
PROJECT: Sunken Court Roadway Reconstruction Project
LOCATION: Port Arthur,Texas
OWNER: City of Port Arthur
STATE OF TEXAS;
COUNTY OF JEFFERSON;
The undersigned hereby certifies that, except as listed below, payment has been made in full and all obligations
have otherwise been satisfied for all material and equipment furnished,for all work,labor,and services performed,
and for all known indebtedness and claims against the Contractor for damages arising in any manner in connection
with the performance of the Contract referenced above for which the Owner's property might in any way be held
responsible or encumbered.
Exceptions:
Contractor: E rtl :'t � '�� C-6 n of ri O /1 C. , Texas
Signature:
Printed Name: A,C /6
Date: 9 .1 .2 1
Subscribed and sworn to before me this 5 day off_-t.k ,2021
My Commission expires
(Notapr
521 sS
EXHIBIT F
2 }
3 p
3 v
6
sl
I. iiiii iii g ii116 Ylailso.t gai3 fvg"iq t y
I
3 lllllltil 3 iq if i �yx l3 Il
r ii1F;filil li 11411 ."f WIWI 0'1
} = 8
CIS FA 11
- 3is; ill + g if& 2;1 .. l
x q `{ 1 0 F�$ =S gt
F HI R x
Y Est Ali g
I
1 Mq sccGyu§cccpq"s4`q;,—;v^>">C>^c cccc:<cc:ccck7x79c F i
ri
B 3
m j 5_1 -scM is_& isi-slie>s§l.zf9?YEIi- 4 R€
�. aBMP22,a.2xiiB59eaaicaasc,i.e'avixgBss.Bk_s,r8 t
m s
i 1
r m a_ v a
g88 :ices a E8 Bve s8 .8nhn
e M aI g, k9.... .. o asso 3 t,.st 8 1 15
F' g 1 NsNie F"" 's in MIN!
" *firIi 1
o a B wibeafaea H B i�ca"x M „ekli 6 Of s ! ii R
I it
C i Y" tvv rx" tvr" " -M" g � gp P. 3Biid2 ;f$8yysar
Y Et21sa88881igyy gg8g :g aa a 8gaE" i6 MI 1
8fl>c"�t2"a yp��p�7F y!} .s ss'yp yp 5yp�¢y}aa Yxi?y.x r ypg $ & Ij� F w
Bi=EkkiBiBMe- YiBB$BBbYCfYUB+=3FC� SkbB � akSB
Oiliiiiilligitifilliinlliiti[ filliiiiilittilliiii
r= - .1Fzf= Fxx t"E a" xrr " x rl AI1j'si&�"sE� ° 1is B� a ..a Bg88g8 "k lii a
i gpl?gs
Ni-1-11NR....i.i..---istalsili..,ithAigf_ l
tEtttyryV _ Y '"DE
Se
tilifilAx li:ri t 8$iB11gEirETaSESEY LMEke8y
icij
1
i$ i`i 1
i -
11111111 g asggggggg8gg8gBs8986888yy6688a8ggB8Eg6gBggae8ayyggBy9ggg68686 8d
$g8B8Bgiial88$a8B88igBiiiigigiiiillilidigaildli ` 1
xs fxxnit�nrAiWP icAPAAFcrer rt!r E iE"xxHPIEP$rk}�f'.8 i s
B EI:: 1 6Y5SktiBs�aarerBaibEeiiiea&e8'e678ESitl84g ialEl lEigea s .
EXHIBIT G
u
City of
or1 rfhu�
www.PortArthurTx.gov
CERTIFICATE OF COMPLETION
Date: November 22, 2021
Project: Sunken Court Roadway Reconstruction Project—Close Out
Project No.: ST1 P02
To: All Concerned
Gentlemen:
I HEREBY CERTIFY THAT this project was completed on November 24, 2020 and that the work
was under periodic inspection during construction by Public Works Engineering, City Inspector. That
to the best of my knowledge,the project was constructed substantially in accordance with the plans
and specifications, and that record documents were received and are on file in Public Works
Engineering.
Subm:. :
fir/ 60/
lozel 'ob- IT, - ng, MBA
Dire, o' of P. • c Works
"Remember,we are here to serve the Citizens of Port Arthur"
P.O.Box 1089 X Port Arthur,Texas 77641-1089 X 409.983.8101 X FAX 409.982.6743
EXHIBIT H
CITY OF PORT ARTHUR, TEXAS
DEPARTMENT OF PUBLIC WORKS
CERTIFICATE OF ACCEPTANCE FOR...
SUNKEN COURT ROADWAY RECONSTRUCTION PROJECT FROM TWIN CITY
HIGHWAY TO NORTH PARK DRIVE
To: Excavation& Construction, LLC of Port Arthur, Texas
This document is to certify that the City of Port Arthur,Texas accepts the completion of the Sunken
Court Roadway Reconstruction Project from Twin City Highway to North Park Drive,on the basis
of the recommendation of the City of Port Arthur's Public Works' Engineering Department and
receipt of the Engineer's Certificate of Completion, Contractor's Affidavit of All Debts Paid,
Contractor's Certificate of Release, Contractor's Certificate of Warranty executed by Excavation
& Construction, LLC of Port Arthur, Texas.
Ron Burton
City Manager
Sherri Bellard
City Secretary