To: Mayor, City Council and City~/~anager
From: Ike Mills, Executive Director,~,~
Date: April 24, 2003
Re: P.R. No. 12151; Council Meeting Apd129. 2003
Attached is P.R. No. 12151 approving contract for construction s~gn in the
amount of $1,957.34 and temporapj sign in the amount of $4,125.87 as it pertains to
the Port Arthur Business Park as approved by the Section 4A Port Arthur Economic
Development Corporation awarding the contract to Fast Sign.
cc: Mark Sokolow, City Attomey
Jim Wimbedey, EDC Attomey
RESOLUTION NO.
A RESOLUTION APPROVING
P. R. NO. 12151
04/14/03 bjm
THE AWARD OF A
CONSTRUCTION SIGN IN THE AMOUNT OF $1,957.34
AND A TEMPORARY SIGN IN THE AMOUNT OF
$4,125.87 TO FAST SIGN FOR THE PORT ARTHUR
BUSINESS PARK AS APPROVED BY THE SECTION 4A
PORT ARTHUR ECONOMIC DEVELOPMENT CORPORATION
WHEREAS, the Section 4A Economic Development Corporation
advertised for bidders to provide and install project signs for the
Port Arthur Business Park signs; and
WHEREAS, the bids were received on February 8, 2003 and were
reviewed and evaluated by Schaumburg & Polk as well as by Diamond
consulting;
WHEREAS, the report and recommendations of Schaumburg & Polk
and Diamond Consulting are attached as Exhibits "A" and "B";
WHEREAS, the Board of Directors of the Port Arthur Section 4A
Economic Development Corporation awarded the construction sign and
temporary sign to Fast Signs on March 31, 2003; and
WHEREAS, the actions of the Section 4A Economic Development
Corporation require the approval by the City Council; and
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF PORT ARTHUR:
Section 1. That the facts and opinions in the preamble are true
and correct.
Section 2. That the City Council herein approves the awa. rd of
these sign contracts (Construction Sign $1,957.34 and Temporary
Sign$4,125.87) to Fast Sign by the Section 4A Economic
Development Corporation.
Section 3. That a copy of
spread upon the Minutes of the City Council
READ, ADOPTED AND A~PROVED on this __ day of
A.D., 2003, at a Regular Meeting of the City Council of
of Port Arthur, Texas, by the following vote: AYES:
Mayor , City Council
the caption of this Resolution be
the City
NOES:
ATTEST:
OSCAR ORTIZ, MAYOR
EVANGELINE GREEN, CITY SECRETARY
PROVED AS TQr~FORM: /'~/'~
~----~G~J~IOUS ~IKE - MILLS, ~XECUTIVE DIRECTOR
APPRO~D AS TO FO~:
5LARK T, SOKOLOW, CITY ATTOP-NEY
APPROVED FOR ADMINISTRATION:
STEVE FITZGIBBONS, CITY MANAGER
APPROVED AS TO AVAILABILITY OF FUNDS:
REBECCA UNDERHILL, DIRECTOR OF FINANCE
EXHIBIT "A"
Diamond Consulting
11 Gambrel Oak Place
The Woodlands, Texas 77380
April 14, 2003
Mr. lke Mills
Executive Director
Port Arthur Economic Development Corporation
P.O. Box 1089
Port AYchur, Texas 77640-1089
Re: City Council Meeting to Award Contracts and Change Order~ for Business Park
Dear Ike,
As you know, bids for Can~racts I and VII were recdved in January and February respectively. I delayed submitting
them for award until they could be considered as one package along with Change Order 2 for Contract VI and
Agreement letters t~om the utility companies. As you will recall The March EDC board meeting was delayed
several weeks. But these have not been included on either of the two subsequent City Council meeting agendas and
are thus still pending.
Change Order 2 to Contract VI is now critical. The contractor must receive the alternate valve called for in this
change order before he can complete construction of the retantion pond and outfall structures. This valve has a lead-
time of weeks in order to allow it to be fabricated specifically for our application.
The following agreements that were approved by the EDC Board on March 31:
Contract VI - Change Order 2 -Substitution of outfall valves + $15,406.00
Contract I - General Requirements - award of the following:
Contact for Construction Sign - $1,957.34 to Fast Sign
Contract for Temporary Project Sign - $4,125.87 to Fast Signs
Cun~ract for Modular Office - $48,893.00 to Eagle Pro Engineering Inc.
Contact VII Landscaping and Final Grading - award of the following:
Contract for construction -
Utility Agreements
Agreement f~r Power Services-
Gas Service-
$597,672.00 to Excavators and Constructors Inc.
$351,000.00 with Entergy
Not to exceed $165,000-with Texas Gas
In addition to these items we have since uncovered two additional items that may require action by both the EDC
Board and City Council. They are:
Economic Development
Architecture
Planning
Change Order 3 to Contract 12I - Underground Utilities - This change order is for revisions in the Jade
Road connection to a new offsite water line being constructed by the City under: separate contract. These
ph281 3677821 fax281 2927552 emaildiaconsult@woridnet, att.net
Potential changes to Con~act v- Road Improvements as a result of changes in soil moisture content (see
Monthly Report for March and April). Additional soil tests are currently underway to resolve concerns and
revise paving section and sub grade design if required.
Ike Mills
April 14, 2003
Page 2 of 2
revisions are the results of changes requested by the City's Utility Director. R and will increase the length
of bore under FM 365, require the removal and replacement ora portion of Jade Ave south of FM 365 and
add valves and other appurtenances at the connection point. A proposal in the amount of $25,798.50 has
been received from E&C thc and reviewed by our Engineer. This change order is also time critical.
I respectfully request that a special meeting be scheduled with the City Council at fl~e earliest practical date. It this
is not possible, I request that the city include these items on its next regular council meeting. If it is possible I also
request that a special meeting of the EDC Board be scheduled prior to the Council meeting to consider Change
Order 3 to Contract III and (if matters can be resolved in time) any changes to Contract V.
ffyon have any questions please let me know.
Warm regards,
~rilliara E. Diamond 1I
Cc: Tim Alexand~
Bill Hughes
EXHIBIT "B"
Schaumburg & Polk, Inc.
CONSULTING ENG]NEERS
8865 College Street, Suite 100
Beaumont, Texas 77707
Phone (409)866-0341
Fax (409)866-0337
January I0, 2003
Mr. Bill Diamond
Diamond Consulting
11 Gambrel Oak Place
Houston, Texas 77380
RECEIVED
E~ONO~P-
i]¥~~. -, _
Re:
Port Arthur Business Park
Recommendation of Award - Re-Bid Contract No. I
Dear Mr. Diamond,
The second Contract I bid opening was held January 7, 2003 at City Hall in Port Arthur,
Texas for "General Requirements" for the proposed Port Arthur Business Park. Bids
were received for three separate items that could be awarded either together or
individually. This letter includes recommendations for award based upon the results of
the competitive bids received and an evaluation of those bids based upon the
requirementv of the contract documents.
The attached bid tabulation shows that we received a total of three (3) bid proposals and
displays the pricing submitted by each bidder for the three base bids. Only one bidder
submitted a bid for all three base bid items. A second bidder submitted a price for Base
Bid No. 3 only and the third bidder submitted a price for Base Bid Nos. l&2 only. This
essentially gave us two bids for each of the three Base Bids. One bidder, Fast Signs, did
not submit their price on the requested proposal form with a legal signature;therefore, we
requested that they send a copy of the signed proposal form to us to attach with this letter.
Recommendation of Award:
Base Bid No. 1: This included the scope of work to provide and install the construction
sign and we received a low bid from Fast Signs of $1,957.34 and a second bid of
$4,547.00 from Eagle-Pro Engineering, Inc. The project budget for the construction sign
was $6,000.00, therefore, we recommend award of Base Bid No. 1 to Fast Signs. The
sign can be installed within 30 calendar days from award.
Base Bid No. 2: This included the scope of work to provide and install the project sign
and we received a low bid from Fast Signs of $4,125.87 and a second bid of $7,437.00
from Eagle-Pro Engineering, Inc. The project budget for the project sign was $9,000.00,
therefore, we recommend award of Base Bid No. 2 to Fast Signs. The sign can be
installed within 30 calendar days from award.
Schaumburg & Polk, Inc.
Page 2
Mr. William E. Diamond
Port Arthur Business Park
Base Bid No. 3: This included the scope of work to provide and install the Modular
Construction Office & Porches for the project and we received a low bid of $48,893.00
from Eagle-Pro Engineering, Inc. and a second bid of $70,000.00 from Green
Construction. The project budget for the office building is $55,000.00, therefore, we
recommend award of Base Bid No. 3 to Eagle-Pro Engineehng, Inc. The building can be
delivered and installed within 65 calendar days from award.
Other Bid items in the original Contract I scope of work include the following list which
we recommend to be directly purchased by the Port Arthur EDC as the project
progresses:
1) Portable Toilet Service - Project Budget of $2,100.00
2) Non-Potable Water Well - Project Budget of $4,000.00
3) Temporary Security Fencing- Project Budget of $3,000.00
4) Refuse Dumpster Service - Project Budget of $2,400.00
Based upon our review and evaluation of the bids for this project and the information
provided by the contractors in their proposals, we respectfully submit these
recommendations for your consideration and for approval of the Port Arthur Economic
Development Corporation and City of Port Arthur Council. Please advise as to how we
are to proceed with Notice of Award at your earliest convenience.
Sincerely,
Schaumburg & Polk, Inc.
William R. Hughes, Jr., P.E.
Project Manager
Attachments
Copy to:
Ike Mills, Executive Director - Port Arthur EDC
PAEDC Business Park Files c/o Diamond Consulting
SPI Project File No. 3602
Schaumburg & Polk, Inc.
CONSULTING ENGINEERS
BID TABULATION
PORT ARTHUR BUSINESS PAP~K
CONTRACT I - GENERAL REQUIREMENTs
Ea~le-Pro
BID DATE: JANUARY 7, 2003 AT 3:00 P.M. Bng±neerin~ Inc. Green Construction Fa~t Sig~s
ENGINEER: SCHAUMBURG & POLK, 1NC. 510 Park Street 2211 Oulfway Drive 4108 N. Dowlen Road
Suite 100 Port Arthur, Texas Beaumont, Texas
Beaumont, Texas 77648 77706
77701
BASE BID NO.I:
I LS $4,547.00 $1,957.34
LABOR & EQUIPMENT ] LS $3~247.00
I LS $ 7,437.00 $4,12S.87
TOTAL ,OF ALL BASE BIDS $60,877.0(
NO
The Bid Proposals submitted have been reviewed: and to the best of m} knowledge this is an accurate
OAT : /-
tabulation of the Bids received.