HomeMy WebLinkAboutPR 22460: CHANGE ORDER NO 1 TO THE CONTRACT WITH GULF COAST A CRH COMPANY FOR STREET REHAB 4 City of ort rtItt Texas www.PortArthurTx.gov INTEROFFICE MEMORAN D U M Date: March 22, 2022 To: The Honorable Mayor and City Council Through: Ron Burton, City Manager From: Flozelle C.Roberts, EIT,MEng, MBA, Director of Public Works RE: PR 22460: 5th& 6th Street Pavement Rehabilitation Project from Atlanta Avenue to Nashville Avenue: Gulf Coast a CRH Company of Beaumont, Texas-Change Order#1 for prep and installation of manholes,risers,conflict boxes and addition of 132 calendar days. Introduction: The intent of this Agenda Item is to authorize the City Manager to execute Change Order No. 1 for the 5th and 6th Street Rehabilitation Project from Atlanta Avenue to Nashville Avenue for prep and installation of manholes, risers, conflict boxes and addition of 132 calendar days with Gulf Coast a CRH Company of Beaumont,Texas for the amount of$181,409.00. Background: The City of Port Arthur had identified 5th and 6th Street from Atlanta Avenue to Nashville Avenue, respectively, as needing rehabilitation in order to accommodate the proposed new homes construction project. The Purchasing Department advertised for bids under Bid No. P21-038. The four (4) bids received were opened and evaluated by the Public Works staff on May 12, 2021 with Gulf Coast a CRH Company (Gulf Coast) of Beaumont, Texas being the lowest most qualified bidder for the amount of $1,483,845.00. Gulf Coast is submitting Change Order No. 1 to address the construction of manholes with risers; installation of dual 15" HDPE pipe; prep and construction of conflict boxes; curb and inlet rework; rate increase for concrete,and additional backfill for the amount of$181,409.00. This would amend the original contract amount of$1,483,845.00 to the new contract amount of$1,665,254.00. Change Order No. 1 also requests the addition of 132 calendar days to the contract due to supply chain and material unavailability, manufacturing delays, COVID delays and conflicts not being resolved due to "Remember,we are here to serve the Citizens of Port Arthur" 444 4th Street X Port Arthur,Texas 77641-1089 X 409.983.8182 X FAX 409.9818294 unforeseen underground obstructions.The addition of 132 calendar days would change the original contract completion date of June 1,2022 to the new contract completion date of October 11, 2022. Budget Impact: Change Order No. 1 impacts funds in the Street Maintenance Account No. 307-80-625-8518-00-10-000 and the Community Development Block Grant (CDBG) 105-13-033-8517-00-40-000. Project Nos. ST1P54 and ST1P55, respectively. Recommendation: It is recommended that the City of Port Arthur City Council approve PR 22460 with Gulf Coast from Beaumont, Texas, authorizing the City Manager to execute Change Order No. 1 increasing the original contract amount of$1,483,845.00 to the new contract amount of$1,665,254.00 and adding 132 additional calendar days to the original contract completion date of June 1, 2022 to the new contract completion date of October 11,2022. S:\Engineering\PUBLIC WORKS\PW-ENGINEERING\C.I.P.PROJECTS\Year 2021\5th&6th Street\Change Orders\Change Order 1\Agenda Memo STH&6fH.Docx "Remember,we are here to serve the Citizens of Port Arthur" 444 4th Street X Port Arthur,Texas 77641-1089 X 409.983.8182 X FAX 409.983.8294 PR No. 22460 3/22//2022 mje Page 1 of 4 RESOLUTION NO. A RESOLUTION AUTHORIZING THE CITY MANAGER TO EXECUTE CHANGE ORDER NO. 1 TO THE CONTRACT BETWEEN THE CITY OF PORT ARTHUR AND GULF COAST A CRH COMPANY OF BEAUMONT, TEXAS FOR THE INSTALLATION OF MANHOLES, RISERS, CURB AND INLET REWORK AND THE ADDITION OF 132 CALENDAR DAYS FOR THE AMOUNT OF $181,409.00 INCREASING THE ORIGINAL CONTRACT AMOUNT TO $1,665,254.00 AND AMENDING THE CONTRACT COMPLETION DATE TO OCTOBER 11, 2022 FOR THE 5TH AND 6TH STREET REHABILITATION PROJECT WITH FUNDING FROM STREET MAINTENANCE ACCOUNT 307-80-625-8518-00-10-000 AND THE COMMUNITY DEVELOPMENT BLOCK GRANT (CDBG) ACCOUNT 105-13-033-8517-00-40-000. PROJECT NOS. ST1P54 AND ST1P55. WHEREAS, the City of Port Arthur has identified 5th & 6th Streets from Atlanta Avenue to Nashville as needing rehabilitation to accommodate the proposed new home construction project; and, WHEREAS, the Purchasing Department advertised for bids under Bid No. P21-038 with four (4) bids being received; and, WHEREAS, the Public Works staff opened and reviewed each bid on May 12, 2021 with Gulf Coast a CRH Company (Gulf Coast) of Beaumont, Texas being the lowest most qualified bidder for the amount of $1,483,845.00; and, WHEREAS, pursuant to Resolution No. 21-223, the City of Port Arthur City Council awarded the for the 5TH & 6T" Street Rehabilitation Project from Atlanta Avenue to Nashville Avenue, Texas to Gulf Coast with a projected budgetary impact of $1,483,845.00 and a term of 240 calendar days; and, PR No. 224620 3/22/2022 mje Page 2 of 4 WHEREAS, Change Order No. 1 is being submitted by Gulf Coast to address the preparation for the construction of additional manholes with risers, installation of double 15" HDPE pipe, preparation for conflict boxes, construction of conflict boxes, curb and inlet rework, ring risers and additional backfill for the amount of $181,409.00; and, WHEREAS, Change Order No. 1 amends the original contract amount of $1,483,845.00 to the new contract amount of $1,665,254.00; and, WHEREAS, Change Order No. 1 also requests the addition of 132 calendar days to the contract due to supply chain and material unavailability, manufacturing delays, COVID delays and conflicts not being resolved due to unforeseen underground obstructions; and, WHEREAS, the addition of 132 calendar days to the original 240 calendar days for completion would change the original contract completion date of June 1, 2022 to the new contract completion date of October 11, 2022; and, WHEREAS, Change Order No. 1 impacts funds in the Street Maintenance Account No. 307-80-625-8518-00-10-000 and the Community Development Block Grant (CDBG) 105-13-033-8517-00-40-000. Project Nos. ST1P54 and ST1P55, respectively. WHEREAS, approval of Change Order No. 1 is herein deemed an appropriate action; now, therefore, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PORT ARTHUR: THAT, the facts and opinions in the preamble are true and correct; and, THAT, Change Order No. 1 is herein approved and the City Manager is authorized to execute said Change Order No. 1 to the contract between the City of Port Arthur and Gulf Coast PR No.22460 3/22//2022 mje Page 3 of 4 a CRH Company of Beaumont, Texas for increasing the original contract amount of $1,483,845.00 by $181,409.00 to the new contract amount of $1,665,254.00; and, THAT, Change Order No. 1, submitted by Gulf Coast a CRH Company of Beaumont, Texas to add 132 calendar days will amend the original completion date of June 1, 2022 to its new completion date of October 11, 2022; and, THAT, a copy of the caption of this Resolution be spread upon the Minutes of the City Council. READ, ADOPTED AND APPROVED this the day of , A.D. 2022 at a meeting of the City of Port Arthur, Texas by the following vote: Ayes: Mayor: Councilmembers: Noes: Thurman "Bill" Bartie Mayor ATTEST: Sherri Bellard City Secretary PR No.224620 3/22/2022 mje Page 4 of 4 APPROVED AS TO FORM: APPROVED FOR ADMINISTRATION: l�zU d a� .e� Valecia izeno Ron Burton City Attorney City Manager APPROVED AS FOR AVAILABILITY OF FUNDS: Kandy Dani ( Interim Dire or of Finance Flozelle C. Roberts, EIT, MEng, MBA Director of Public Works Clifton Williams, CPPB Purchasing Manager EXHIBIT A CITY OF PORT ARTHUR Public Works Engineering DATE: MARCH 21,2022 PROJECT: 5TH STREET PAVEMENT REHABILITATION PROGRAM OWNER: CITY OF PORT ARTHUR CONTRACTOR: GULF COAST OF BEAUMONT,TEXAS CHANGE ORDER NO.:01 THE FOLLOWING CHANGES IN THE PLANS AND/OR SPECIFICATIONS ARE HEREBY MADE: Adjust the Estimated Quantities to reflect the Actual Quantities used in the completion of the project: Item Item Description Unit Original Unit Price Original New Quantity New Amount No. Code Quantity Amount 5TH STREET SUBCONTRACTOR AREA PREP AND MANHOLE CONSTRUCTION EA 0 $ 23,594.47 $ - 4.0 $ 94,377.88 INSTALL DOUBLE 15'AT 5TH AND ATLANTA AVE LF 0 $ 246.98 $ - 33.0 $ 8,150.34 6TH STREET 104 002 REMOVE CONCRETE DRIVEWAY SY 308 $ 16.50 $ 5,082.00 101.0 $ (1,666.50) 104 003 REMOVE CONCRETE SIDEWALK SY 1,364 $ 10.00 $ 13,640.00 366.0 $ (3,660.00) 104 004 REMOVE CONCRETE CURB AND GUTTER LF 4,086 $ 2.45 $ 10,010.00 658.0 $ (1,612.10) SUBCONTRACTOR CURB INLET REWORK 6TH AT CHARLESTON EA 0 $ 1,581.85 $ - 1.0 $ 1,581.85 SUBCONTRACTOR RING RISERS AND ADDITIONAL BACKFILL 6TH AT CHARLESTON EA 0 $ 2,703.45 S - 1.0 $ 2,703.45 SUBCONTRACTOR AREA PREP AND CONFLICT BOX CONSTRUCTION EA 0 $ 10,444.42 5.0 $ 52,222.10 UNIT RATE INCREASE 5TH AND 6TH STREET 104 004 REMOVE CONCRETE-CURB AND GUTTER LF 8,226 $ 2.21 8226.0 $ 18,179.46 110 001 EXCAVATE-CURB AND GUTTER CY 1,828 $ 6.09 $ - 1828.0 $ 11,132.52 ADD $ 181,409.00 ORIGINAL CONTRACT AMOUNT $ 1,483,845.00 NEW CONTRACT $ 1,665,254.00 AMOUNT ORIGINAL CONTRACT AMOUNT: $ 1,483,845.00 NET FROM PREVIOUS CHANGE ORDERS: $ - TOTAL AMOUNT OF THIS CHANGE ORDER NO.1: $ 181,409.00 PERCENT OF THIS CHANGE ORDER NO.1: 12.23% TOTAL PERCENT CHANGE ORDERS NO.1: 12.23% FINAL CONTRACT AMOUNT: $ 1,665,254.00 132 ADDITIONAL CALENDAR DAYS HAVE BEEN ADDED TO CHANGE ORDER NO.1 NOTICE TO PROCEED DATE:OCTOBER 4,2021 NUMBER OF CALENDAR DAYS FOR PROJECT: 240 ORIGINAL CONTRACT COMPLETION DATE:JUNE 1,2022 NUMBER OF ADDITIONAL CALENDAR DAYS ADDED:132 NEW CONTRACT COMPLETION DATE:OCTOBER 11,2022 PREPARED BY: QUANTITIES VARIFIED BY: M.Jennifer Edwards,BAAS,MPA Martin Flood,Project Manager CIP Manager APPROVED BY: APPROVED BY: Zech Leggett,Project Manager John Cannatella,PE,City Engineer Gulf Coast a CRH Company APPROVED BY: APPROVED BY: Flozelle C.Roberts,ER,MEng,MBA Clifton Williams,CPPB,Purchasing Manager Public Works Director