INTEROFFICE MEMORANDUM
Date: March 24, 2022
To: The Honorable Mayor and City Council
Through: Ronald Burton, City Manager
:fet,
From: Timothy Duriso, Chief of Police �y e
RE: PR 22471 Construction Managers of Southeast Texas, LLC—proposal to install
new awning at the back of the Police Department.
Introduction:
The intent of this Agenda Item is to authorize the City Manager to accept the proposal
submitted by Construction Managers of Southeast Texas, LLC for the installation of a new
awning and repairs made to the Police Department.
Background:
The awning located at the back of the Police Department sustained severe damage during TS
Laura. The awning was attached to the bricks along the back of the Police Department and also
had the rain gutters attached to the awning. It is the desire of the Police Department to replace
the awning and make repairs to the building. Construction Managers of Southeast Texas,
LLC,has submitted a proposal for the repairs in the amount of$24,850.00. Construction
Managers of Southeast Texas, LLC, is a participant in the Interlocal Purchasing System (TIPS)
cooperative under Reference No. 200201, so no other quotes were needed.
Budget Impact:
Funds for this purchase are available in account number 001-17-045-5312-00-30-000 Building
Maintenance.
"Remember,we are here to serve the Citizens of Port Arthur"
P.O.Box 1089 X Port Arthur,Texas 77641-1089 X 409.983.8101 X FAX 409.982.6743
City of
I ;0
0, t rthur
www.PortArthurTx.gov
Recommendation:
It is recommended that the City Council approve the City Manager to accept the proposal from
Construction Managers of Southeast Texas, LLC for the installation of the new awning and
repairs made to the Police Department building.
"Remember,we are here to serve the Citizens of Port Arthur"
P.O.Box 1089 X Port Arthur,Texas 77641-1089 X 409.983.8101 X FAX 409.982.6743
P.R. No. 22471
JLH 3/24/2022
RESOLUTION NO.
A RESOLUTION AUTHORIZING THE CITY MANAGER TO ENTER
INTO A CONTRACT WITH CONSTRUCTION MANAGERS OF
SOUTHEAST TEXAS, LLC THROUGH TIPS COOPERATIVE
PURCHASING PROGRAM REFERENCE NO. 200201 TO MAKE
REPAIRS TO THE AWNINGS FOR THE BACK LOT OF THE
POLICE DEPARTMENT IN THE AMOUNT OF $24, 850 . 00 .
FUNDING IS AVAILABLE IN BUILDING MAINTENANCE
ACCOUNT NO. 001-17-045-5312-00-30-000 .
WHEREAS, Chapter 271 of the Texas Government Code allows
a city, by resolution of its governing body, to participate
in cooperative purchasing programs, such as TIPS Cooperative
Purchasing Program, as an alternative to formal bid process ;
and
WHEREAS, pursuant to Resolution No. 12-008 , the City of
Port Arthur entered into an interlocal agreement for
cooperative purchasing with Region VIII Education Service
Center for participation in the Interlocal Purchasing System
(TIPS) ; and
WHEREAS, Construction Managers of Southeast Texas,
LLC, is an approved vendor through the TIPS Cooperative
Purchasing Program under Reference NO. 200201; and
WHEREAS, Construction Managers of Southeast Texas, LLC
has provided a quote for the installation of two awnings
above the rear back doors of the Police Department and
repairs to the building which were damaged during tropical
storm Laura in the amount of $24 , 850 . 00 , under TIPS
Reference No. 200201 attached as Exhibit A; and
WHEREAS, funds for this purchase are available in
Account No. 001-17-045-5312-00-30-000 Building Maintenance
Account .
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE
CITY OF PORT ARTHUR:
Section 1. That the facts and opinions in the preamble
are true and correct .
Section 2 . That the City Council hereby authorizes the
City Manager to enter into an agreement with Construction
P.R. No. 22471
JLH 3/24/2022
Managers of Southeast Texas, LLC for the installation of the
awning and repairs made to the Police Department in the amount
of $24 , 850 . 00 under TIPS Reference No. 200201, in
substantially the same form as Exhibit "B" .
Section 3 . That a copy of the caption of this resolution
shall be spread upon the Minutes of the City Council .
READ, ADOPTED AND APPROVED on this day of April,
A.D. , 2022, at a Regular Meeting of the City Council of the
City of Port Arthur, Texas, by the following vote : AYES:
Mayor:
Councilmembers :
NOES:
Thurman Bill Bartie
Mayor
ATTEST:
Sherri Bellard
City Secretary
APPROVED AS TO FORM: APPROVED FOR ADMINISTRATION
UA4��32
Val T zeno Ronald Burton
City Attorney City na r
Tim by Duriso
Chief of Police
P.R. No. 22471
JLH 3/24/2022
APPROVED AS TO AVAILABILITY OF FUNDS:
Kandy Dan i 1
Interim Finance Director
Ailb""k
Cli ton illiams, CPPB
Purchasing Manager
P.R. No. 22471
JLH 3/24/2022
EXHIBIT "A"
Ge-t, Construction Managers
or Southeast Texas, LLC
225 HIGHWAY 365—PORT ARTHUR,TEXAS 77640—PHONE(409)736—9010—FAX (409) 7369020
February 17, 2022 TIPS Reference#: 200201
Port Arthur Police Department
645 4th Street
Port Arthur, TX 77640
Al:
Please find below the cost associated with installing the awning above the two rear back doors and canopy at
the smoking area. Pricing includes the following items:
• Installation of two awning above door ways (approx.. 9'X5')
• Install canopy over smoking area at table (approx. 11'X30')
• All canopy post to be 4x4 galvanized anchored into concrete
• All 4"c-channel galvanized
• All 4"closed c-channel galvanized
• All galvalume roof panels
• All metal flashing galvalume
• Remove existing flashing, repair holes in brick, reset damaged brick and paint to match existing as
close as possible
• Remove area of brick masonry that pulled out from wall
• Re-use all bricks that can be saved or replace with new brick as needed
• Patch all holes in brick walls with mortar
• Re-point mortar joints after flashing has been removed
• Install new gutters and downspouts —stainless steel—match existing profile in size and will tie into
existing gutters.
• Repair bent refrigerant lines
Cost for scope identified above: $24,850.00
If you have any questions,please feel free to give me a call. Note that proposal excludes sales tax.
Awnings/canopies will not be windstorm rated.
Sincerely,
Construction Managers
of Southeast Texas, LLC
Jose Cardenas
Project Manager
CC:Bruce Reyes—CMOST
P.R. No. 22471
JLH 3/24/2022
EXHIBIT "B"
CONTRACT FOR POLICE DEPARTMENT
INSTALLATION OF AWNINGS AND REPAIRS
THIS AGREEMENT, made this day of , 2022, by and
between the City of Port Arthur, a municipal corporation organized under the laws of the
State of Texas, hereinafter called "OWNER" or "CITY" and Construction Managers of
Southeast Texas, LLC of Port Arthur, Texas hereinafter called "CONTRACTOR"
WITNESSETH: That for and in consideration of the payment terms, conditions and
agreements set forth herein, OWNER and CONTRACTOR agree as follows:
1. The term of this Agreement shall be for 45 days from the date stated on the Notice to
Proceed, unless sooner terminated under the provision hereof. The City can terminate
this contract at its convenience which includes, but is not limited to, funding not
being available in any budget cycle with thirty (30) days written notice.
2. The Contractor will perform work as stated in the Contract Documents.
3. During the term of this Contract, the Contractor will furnish at his own expense all of
the materials, supplies, tools, equipment, labor and other services necessary to
connection therewith, excepting those supplies specifically not required of Contractor
in the Specifications.
4. The CONTRACTOR agrees to perform all the work described in the quote and
contract documents and to comply with the terms therein for the amount of
$24,850.00.
5. The term"Contract Documents" means and includes the following:
a. Agreement
b. Quote—TIPS Reference# 200201
c. Notice of Award
d. Notice to Proceed
6. This Agreement shall be binding upon all parties hereto and their respective heirs,
executors, administrators, successors and assigns.
7. IN WITNESS WHEREOF,the parties hereto have executed, or caused to be executed
by their duly authorized officials, this Agreement in(2 copies) each of which shall be
deemed an original on the date first above written.
Signed on the day of , 2022.
ATTEST: CITY OF PORT ARTHUR
BY:
Sherri Bellard Ronald Burton
City Secretary City Manager
Signed on the day of , 2022.
CONSTRUCTION MANAGERS
OF SOUTHEAST TEXAS LLC
WITNESS:
BY:
Print Name:
Print Name:
Title:
Construction Managers
of Southeast Tex45, LLC
•
225 HIGHWAY 365—PORT ARTHUR,TEXAS 77640—PHONE(409)736—9010—FAX(409)7369020
February 17, 2022 TIPS Reference#: 200201
Port Arthur Police Department
645 4th Street
Port Arthur, TX 77640
Al:
Please find below the cost associated with installing the awning above the two rear back doors and canopy at
the smoking area. Pricing includes the following items:
• Installation of two awning above door ways (approx.. 9'X5')
• Install canopy over smoking area at table(approx. 11'X30')
• All canopy post to be 4x4 galvanized anchored into concrete
• All 4" c-channel galvanized
• All 4" closed c-channel galvanized
• All galvalume roof panels
• All metal flashing galvalume
• Remove existing flashing, repair holes in brick,reset damaged brick and paint to match existing as
close as possible
• Remove area of brick masonry that pulled out from wall
• Re-use all bricks that can be saved or replace with new brick as needed
• Patch all holes in brick walls with mortar
• Re-point mortar joints after flashing has been removed
• Install new gutters and downspouts -stainless steel-match existing profile in size and will tie into
existing gutters.
• Repair bent refrigerant lines
Cost for scope identified above: $24,850.00
If you have any questions,please feel free to give me a call.Note that proposal excludes sales tax.
Awnings/canopies will not be windstorm rated.
Sincerely,
Construction Managers
of Southeast Texas, LLC
ae--' 4
Jose Cardenas
Project Manager
CC:Bruce Reyes—CMOST