Lake Arthur and Stonegate Drainage HMGP Projects
Council Update – April 2022
1
Stonegate Drainage – Cost and Status Updates
City Council Update – April 2022
PROJECT REVIEW
Phase I Engineering/Design - $491,314.00
Status – Complete and Approved
Funding Source – CDBG-DR
Reimbursement - In process
Phase II Construction - $16,120,000.00
Status – BCR of 1.16 reached; Project Submitted; RFI Answered; Pending FEMA Approval; Project at Pre-Bid Preparation
Funding Source – FEMA 404 HMGP
Reimbursement – Pending FEMA Approval
2
Stonegate Drainage – Current Actions
City Council Update – April 2022
CURRENT EFFORTS
Project reached a BCR of 1.16 which meets the FEMA requirement
Submitted all project data; responded to all FEMA questions and Requests for Information as of February 2022
No additional information requests or questions have been received
Project remains in FEMA review- weekly inquiries to FEMA/TDEM are being made for updated information
3
Lake Arthur Detention – Cost and Status Updates
City Council Update – April 2022
PROJECT REVIEW
Phase I Engineering/Design – $859,025.00
Status – Complete and Approved
Funding Source – FEMA HMGP 404
Reimbursement – $641K received, $218,025 in process
Construction – $19,115,915.00
Status – FEMA BCR < 1; exploring design modifications with street drainage as focus
Funding Source – Exploring $8M of CDBG-DR/$12M of CDBG-MIT alternatives
Reimbursement – Pending program approval
4
Lake Arthur Detention – Current Actions
City Council Update – April 2022
CURRENT EFFORTS
Compliance review for CDBG-DR funding
Analysis of data within CDBG guidance
Preparing application for CDBG-MIT funding as available
5
Questions ?