HomeMy WebLinkAbout(P2) COUNCIL MEETING 4-12-22 - Stonegate and Lake Arthur Drainage Project Status - Presentation (2)Lake Arthur
and Stonegate
Drainage
HMGP Projects
Council Update
–April 2022
Stonegate
Drainage –Cost
and Status
Updates
City Council
Update –April
2022
PROJECT REVIEW
Phase I Engineering/Design -$491,314.00
Status –Complete and Approved
Funding Source –CDBG-DR
Reimbursement -In process
Phase II Construction -$16,120,000.00
Status –BCR of 1.16 reached; Project Submitted; RFI Answered; Pending FEMA Approval; Project at Pre-Bid Preparation
Funding Source –FEMA 404 HMGP
Reimbursement –Pending FEMA Approval
Stonegate
Drainage –
Current Actions
City Council
Update –April
2022
CURRENT EFFORTS
•Project reached a BCR of 1.16 which meets the FEMA requirement
•Submitted all project data; responded to all FEMA questions and Requests for Information as of February 2022
•No additional information requests or questions have been received
•Project remains in FEMA review-weekly inquiries to FEMA/TDEM are being made for updated information
Lake Arthur
Detention –Cost
and Status Updates
City Council
Update –April
2022
PROJECT REVIEW
Phase I Engineering/Design –$859,025.00
Status –Complete and Approved
Funding Source –FEMA HMGP 404
Reimbursement –$641K received, $218,025 in process
Construction –$19,115,915.00
Status –FEMA BCR < 1; exploring design modifications with street drainage as focus
Funding Source –Exploring $8M of CDBG-DR/$12M of CDBG-MIT alternatives
Reimbursement –Pending program approval
Lake Arthur
Detention –
Current Actions
City Council
Update –April
2022
CURRENT EFFORTS
•Compliance review for CDBG-DR funding
•Analysis of data within CDBG guidance
•Preparing application for CDBG-MIT funding as available
Questions ?