HomeMy WebLinkAboutPR 15342: ARCENEAUX & GATES - CWSRF TWDB PROJECTSPUBLIC WORKS DEPARTMENT
COUNCIL ACTION MEMO
TO Stephen B. Fitzgibbons, City Manager
FROM Ross E. Blackketter, P.E., Director of Public Works
SUBJECT P. R. #15342 - Chg of Scope for Arceneaux & Gates for CWSRF TWDB Projects
DATE 24 June 2009
RECOMMENDATION:
I recommend that the City Council approve Proposed Resolution No. 15342, revising the scope of
the contract with Arceneaux & Gates Consulting Engineers, Inc. to include construction phase
services for the Sanitary Sewer Rehabilitation - CWSRF TWDB Projects, increasing the budget for
these services by $852,000 to a total of $1,217,000 and increasing the contract term by 580 days to
730 days.
BACKGROUND:
In Resolution 09-238, the City entered into a contract with Arceneaux & Gates Consulting Engineers,
Inc. (Arceneaux) for the engineering design services for sanitary rehabilitation that we expect to be
funded by a Texas Water Development Board Clean Water State Revolving Fund grant from the
American Reinvestment and Recovery Act (ARRA).
Due to their expertise and familiarity with the projects, we wish to increase the scope ofArceneaux's
contract to include Construction Phase Services. Arceneaux has proposed to do the additional work
for an amount of $852,000, bringing the contract to a total of $1,217,000. The term of the contract
also needs to be increased to include the construction period - a total of 730 days.
BUDGETARY/FISCAL EFFECT:
Funding is available in Project 426016, 426-1625-532.54-00.
EMPLOYEE/STAFF EFFECT:
None.
SUMMARY
I recommend that the City Council approve Proposed Resolution No. 15342, authorizing the City
Manager to execute Change of Scope No. 1, revising the scope of the contract with Arceneaux &
Gates Consulting Engineers, Inc. to include construction phase services for the Sanitary Sewer
Rehabilitation - CWSRF TWDB Projects, increasing the budget for these services by $852,000 to a
total of $1,217,000 and increasing the contract term by 580 days to 730 days.
Ross E. Blackketter, P.E.
Director of Public Works
REB/reb
Z:\engineer\Documents\~ ms\A&G-ChgofScope-CtiVSRF.doc
P.R. No. 15342
06/24/09 reb
RESOLUTION NO.
A RESOLUTION AUTHORIZING ADDITIONAL SERVICES FOR THE
CONTRACT APPROVED TUNE 2, 2009 BETWEEN THE CITY OF
PORT ARTHUR AND ARCENEAUX & GATES CONSULTING
ENGINEERS, INC. OF PORT ARTHUR, TEXAS FOR PROFESSIONAL
SERVICES RELATED TO THE TWDB CWSRF (ARRA) GRANT
INCREASING THE BUDGET FOR THIS ENGINEERING SERVICE BY
$852,000 TO A TOTAL OF $1,217,000. ACCOUNT 426-1625-
532.54-00, PROJECT 426016.
WHEREAS, on June 2, 2009, the City Council of the City of Port Arthur
authorized a contract with Arceneaux & Gates Consulting Engineers of Port Arthur,
Texas for professional services related to basic design services in the not-to-exceed
amount of $365,000; and,
WHEREAS, the Texas Water Development Board has allocated $15,075,000 for
sanitary sewer projects, pending completion of plans, specifications, permitting, etc. for
these projects; and,
WHEREAS, due to the scope and time frame required for these projects, hiring
an engineering firm for Construction Phase Services is required; and,
WHEREAS, Arceneaux & Gates Consulting Engineers, Inc. is most familiar with
these projects and is the most qualified engineer to provide this service; and,
WHEREAS, Arceneaux & Gates Consulting Engineers, Inc. has submitted a
proposal for professional services during the Construction Phase in the not-to-exceed
amount of $852,000 (see Exhibit "A'~; now, therefore,
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PORT
ARTHUR:
P.R. No. 15342
Page 2
THAT, the facts and opinions in the preamble are true and correct; and,
THAT, revising the scope of services to include Construction Phase Services,
increasing the budget for engineering design and construction phase services by
$852,000 to a total of $1,217,000 (Project 426016, 426-1625-532.54-00,), and
increasing the total contract term to 730 days is herein approved. City Manager is
authorized to execute said Change of Scope as attached in Exhibit "B"; and,
THAT, a copy of the caption of this Resolution be spread upon the Minutes of
the City Council.
READ, ADOPTED AND APPROVED this the day of A.D. 2009
at a meeting of the City of Port Arthur, Texas by the following vote:
Ayes: Mayor:
Councilmembers:
Noes:
Mayor
Attest:
City Secretary
P.R. No. 15342
Page 3
APPROVED AS TO FORM:
City Attorney
APPROVED FOR ADMINISTRATION:
Stephen B. Fitzgibbons
City Manager
Deborah Echols, C.P.A.
Director of Finance
~ ~ _~~'~~
Ross E. Blackketter, P.E.
Director of Public Works
Z:\engineer\Documents\Resolutions\PR15342.doc
d lI9IHX3
ARCENEAUX
GATES
ARCENEAUX & GATES
Consulting Engineers, Inc.
Engineers • Surveyors • Planners
June 24, 2009
Mr. Ross Blackketter, PE
Director of Public Works
CITY OF PORT ARTHUR
PO Box 1089
Port Arthur, Texas 77641-1089
RE: Request for Amendment to Contract
Sewer System Rehabilitation - CWSRF TWDB Projects
A&G Project No. CPA-490
Dear Mr. Blackketter:
We are pleased to be of continuing service to the City in this sewer system improvement project. We
have discussed the need to assist the City with professional services during the Construction Phase
and preparing information for Grant-in-Aid Application relating to projects to be funded from the
TWDB State Revolving Fund (SRF).
We request authorization for Construction Phase Services as outlined in Section A.3. of our Contrail
for Professional Services as well as for Additional Services listed under Section B. (6}, (11), (13), (14)
and (22).
COMPENSATION AND S[HEDULE
For these services described above, we propose to be compensated on a reimbursable basis
according to the schedule of rates in our contract and will not exceed the sum of Eight Hundred Fifty-
two Thousand Dollars ($852,000.00) without your prior written authorization, bringing the total
contract amount authorized to $1,217,000.00. We request that the period of service be extended to
a total of 730 calendar days from the date of the contract. We look forward to your favorable review
of this proposal and if you have any questions, please contact me.
Very truly yours,
ARCENEAUX & GATES CONSULTING ENGINEERS, INC.
Ronald J. r neaux, PE, PLS
Presiders EO
One IUrtle Creak Square 3501 lhrtle Creak Dr., Suite 102 Port Arthur, iX 77642 409/724-7898 FAX 40 917 2 4 149 7
81I8IHX3
CHANGE OF SCOPE NO. 01
DATE: June 30, 2009
ORIGINAL AGREEMENT DATE: June 2, 2009
ARCENEAUX & GATES CONSULTING ENGINEERS, INC.
A&G PROJECT NUMBER: CPA~90
PROJECT DESCRIPTION: Sewer System Rehabilitation - CWSRF TWDB Projects
CHANGE IN SCOPE: Additional services to include Construction Phase Services.
CHANGE TO CONTRACT AMOUNT:
ORIGINAL CONTRACT amount: $365,000
CURRENT CONTRACT PRICE (adjusted by previous SCOPE CHANGE): $365,000
The Contract Amount due to this SCOPE CHANGE will be (increased/decreased) by:
$852,000
The new CONTRACT AMOUNT including the SCOPE CHANGE will be: $1,217,000
CHANGE TO CONTRACT TERM:
ORIGINAL CONTRACT term: 150 days
CURRENT CONTRACT TERM (adjusted by previous SCOPE CHANGE): 150 days
The Contract Term due to this SCOPE CHANGE will be (increased/decreased) by:
580 days
The new CONTRACT TERM including the SCOPE CHANGE will be: 730 days
ARCENEAUX & GATES CONSULTING ENGINEERS, INC.
Signature
Ronald J. Arceneaux, P.E. _
Printed Name
CITY OF PORT ARTHUR
Stephen B. Fitzgibbons
City Manager
Z:\engineer\DocumentslContracts\Change OrderslA&G ScopeChg No. 1 30Jun09.doc