INTEROFFICE MEMORANDUM
Date: April 29, 2022
To: The Honorable Mayor and City Council
Through: Ronald Burton, City Manager
From: Calvin Matthews, P.E., Water Utilities Director
RE: PR 22537—Approval of Time-Extension Change Order No. 3
Introduction:
The intent of this Agenda Item is to seek City Council's approval of Change Order No. Three
(3) for the Remediation and Mitigation of the Twelve (12) Harvey Lift Stations as a time-
extension change order.
The original contract amount was awarded by Resolution No. 21-134 on April 13, 2021 for
$1,278,248.00 and 210 days from the start date on the Notice to Proceed. Contract Change
Order No. One (1) was a time extension only change order, but due to an oversight, was not
processed. Contract Change Order No. Two (2), approved by Resolution No. 22-125, was for a
time extension of sixty(60) days. This Change Order No. Three (3) is a time-extension change
order of 120 days, which includes the time extension not processed from Change Order No.
One (1), making the contract end date June 27, 2022.
Background:
In April of 2021, the Council passed Resolution No. 21-134, awarding the Remediation and
Mitigation of the Twelve (12) Harvey Lift Stations contract to BDS Constructors, LLC DBA
MK Constructors of Vidor, Texas. The project is managed by Arceneaux, Wilson& Cole, LLC
of Port Arthur, Texas.
Budget Impact:
The original contract amount was $1,278,248.00; Change Order No. Two (2) was a deductive
change order for $10,000.00. This Change Order No. 3 is a time-extension change order,of 120
days with no budget impact. The current contract value is $1,268,248.00. Funds are available
in Account No. 405-40-000-8516-00-00-000, Project No. WS0005-CON.
Recommendation:
It is recommended that City Council adopt Proposed Resolution No. 22537, which extends the
duration of the project for 120 days, as discussed/outlined above.
"Remember,we are here to serve the Citizens of Port Arthur"
PR No. 22537
4/29/22 bw
Page 1 of 3
RESOLUTION NO.
A RESOLUTION AUTHORIZING THE CITY MANAGER
TO EXECUTE CHANGE ORDER NO. 3 TO THE
CONTRACT BETWEEN THE CITY OF PORT ARTHUR
AND BDS CONSTRUCTORS, LLC DBA MK
CONSTRUCTORS OF VIDOR, TEXAS FOR THE
REMEDIATION AND MITIGATION OF THE TWELVE
(12) HARVEY LIFT STATIONS, EXTENDING THE
DURATION OF THE PROJECT WITH A TIME
EXTENSION OF 120 DAYS; ACCOUNT NO. 405-40-000-
8516-00-00-000, PROJECT NO. WS0005-CON.
WHEREAS, pursuant to Resolution No. 21-134, City Council awarded a contract to
BDS Constructors, LLC DBA MK Constructors of Vidor, Texas, for the remediation and
mitigation of the twelve (12) Harvey lift stations for the amount of$1,278,248.00; and,
WHEREAS, Change Order No. One (1) was submitted by Arceneaux, Wilson and Cole,
LLC, for a proposed time extension of 60 (sixty) days, but due to an oversight, it was not
processed; and,
WHEREAS, pursuant to Resolution No. 22-125, City Council approved deductive
Change Order No. Two (2) to the Remediation and Mitigation of the Twelve (12) Harvey Lift
Stations in the amount of $10,000.00, to a new total of $1,268,248.00, and extending the
completion date by 60 days; and,
WHEREAS, Arceneaux Wilson & Cole LLC, Project Engineers, has submitted Change
Order No. Three (3) (attached hereto as Exhibit "A") to the Remediation and Mitigation of the
Twelve (12) Harvey Lift Stations, extending the completion date by 120 days to the project to a
new term of 390 days (June 27, 2022) and has no cost impact; and,
WHEREAS, Charge Order No. Three (3) will reconcile the previously requested time
extension of sixty(60) days in Change Order No. 1 that was not processed; and
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE
CITY OF PORT ARTHUR:
PR No. 22537
4/29/22 bw
Page 2 of 3
THAT, the facts and opinions in the preamble are true and correct; and,
THAT, the City Manager of the City of Port Arthur is hereby authorized and directed to
approve Change Order No. Three (3) to the contract with BDS Constructors, LLC DBA MK
Constructors of Vidor, Texas, Texas, increasing the duration of the project with a time extension
of 120 days due to material changes to a new term of 390 days (June 27, 2022) and has no cost
impact, in substantially the same form as attached hereto as Exhibit"A".
THAT, a copy of the caption of this Resolution be spread upon the Minutes of the City
Council.
READ, ADOPTED, AND APPROVED THIS day of , 2022 at
a Regular Meeting of the City Council of the City of Port Arthur, Texas, by the following vote:
AYES: Mayor ;
Councilmembers
NOES:
Thurman"Bill" Bartie
Mayor
ATTEST: APPROVED AS TO FORM:
(iit -1W 12z'-- 412/t
Sherri Bellard .Valecia Tiz no
City Secretary City Attorney
PR No. 22537
4/29/22 bw
Page 3 of 3
APPROVED FOR ADMINISTRATION:
Ronald Burton
City Manager
alvin Matthews, P.E.
Water Utilities Director
APPROVED AS TO AVAILABILITY
OF FUNDING:
cil, ,tvi)CA 6,41,
Kandy Danikl Clifto • Williams
Interim Finance Director Purchasing Manager
EXHIBIT A
(Change Order 3)
Keith Zotzky
From: lon.hubbard epicengr.com <lon.hubbard@epicengr.com>
Sent: Monday, April 25, 2022 10:35 AM
To: Keith Zotzky
Subject: RE: Port Arthur Lift Stations
•
Keith
In review of the request I concur with the request for an extension of time.The materials issues are affection all our
projects in construction now.
Thank you
Lon A Hubbard PE
EPIC Engineering
409-267-1149
From: Keith Zotzky<Keith.Zotzky@awceng.com>
Sent: Monday,April 25, 2022 10:15 AM
To: lon.hubbard epicengr.com<lon.hubbard@epicengr.com>
Subject: RE: Port Arthur Lift Stations
Good Morning Lon,
Please see the email below from MK/ESI in regard to a necessary time extension for the 12 Lift Station. Let me know if
you agree with this request and the justification.
Thank you,
0 awc
APCENEAUX WILSON&COLE
Keith Zotzky,P.E.(TX,LA), CFM/Project Manager
Keith.Zotzky@awceng.com/281.543.2663
Arceneaux Wilson &Cole LLC
3120 Central Mall Drive
Port Arthur, TX 77642
409.724.7888
awceng.comn
+11.
.411i
.. ARCENEAUX WILSON&COLE
engineering l surveyIng I planning
April 28, 2022
Mr. Calvin Matthews, P.E.
City of Port Arthur
Director of Water Utilities
444 4th Street
Port Arthur, Texas 77640
RE: Proposal For Change Order No. 03 for
LIFT STATION REMEDIA T/ON&MI TIGA TION
AWC Job No. CPA-970
Mr. Matthews:
Attached is Change Order No. 3 for the Lift Station Remediation & Mitigation
project. This change order is for extending the contract time by one hundred
twenty(120) calendar days.
The electrical subcontractor for the project has informed the Contractor of
another additional 8-week delay beyond the last reported and anticipated
construction completion timeframe. This delay is due to equipment and material
delivery delays beyond the previously anticipated schedule. These materials were
necessary for the completion of the electrical control panels for each site. The
electrical subcontractor has now received all necessary appurtenances to begin
constructing the remaining electrical improvements at each lift station site. The
Contractor has completed all construction activities involving new fencing and
elevated platforms at the lift station sites. The remainder of the proposed
construction improvements is now scheduled to be completed within the next 60
calendar days and is directly related to the receipt of the delayed electrical
equipment.
409.724.7888
2901 Turtle Creek Dr.,Suite 320
Port Arthur,TX 77642 Engineering Surveying
awceng.com F-16194 10194049
AIM
.` CliAlle
A WM
TAW
This change order will add 120 Calendar Days to the contract time to account for
the experienced equipment delays and reconcile the previously requested 60 day
extension via Change Order No. 1. We recommend that the City of Port Arthur
authorize this change order to the contract as submitted. We have attached
Change Order No. 3 which modifies the contract to reflect this change for your
consideration and action.
Should you have any questions or require additional information, please contact
our office.
ARCENEAUX W/LSON&COLE LLC
TEXAS REGISTERE ENGINEERING FIRM F-16194
Keith Zotzky, P. ., CFM
Attached.'
Change Order#03
MK Constructors Time Extension Request
Original Submitted CO#1
1'_
lkl
4(SD
V ARCENEAUX WILSON&COLE
engineering I surveying I otanning
CHANGE ORDER NO. 3
DATE: April 28, 2022 JOB NO.: CPA-970
AGREEMENT DATE: April 19, 2021
NAME OF PROJECT: Lift Station Remediation & Mitigation
OWNER: CITY of PORT ARTHUR
CONTRACTOR: MK CONSTRUCTORS
The following changes are hereby made to the CONTRACT DOCUMENTS:
1. Extend Contract Time by 120 Calendar Days to account for electrical equipment &
materials delivery delay and reconcile previously requested contract time
via Change Order No. 1.
TOTAL $0.00
CHANGE TO CONTRACT PRICE:
ORIGINAL CONTRACT PRICE: $1,278,248.00
CURRENT CONTRACT PRICE adjusted by previous CHANGE ORDER(S): $1,278,248.00
The CONTRACT PRICE due to this CHANGE ORDER will be
by: $0.00
The new CONTRACT PRICE, including this CHANGE ORDER, will be $1,278,248.00
1 of 2
1__ rIaANc to t Rt t=ku No. .
'_ April t , 3
Job No. CPA978
+ YM
" ARCENEAUX WILSON&COLE
engineering I surveying I Pionning
CHANGE TO CONTRACT TIME:
ORIGINAL CONTRACT TIME: 210 Calendar Days
CURRENT CONTRACT TIME adjusted by previous CHANGE ORDER: 60 Calendar Days
CURRENT DATE OF COMPLETION: February 27, 2022
CONTRACT TIME due to this CHANGE ORDER will be increased by 120 Calendar Days
The New DATE OF COMPLETION: June 27, 2022
No other Terms and Conditions of the Contract are changed as a result of this Change Order.
Contractor's acceptance of Change Order relieves OWNER of any liability for additional costs incurred
by Contractor in his performance of the work covered by the Change Order.
RECOMMENDED Y ENGINEER: ACCEPTED BY:
ARCENEAUX N & COLE LLC (CONTRACTOR, OFFICER OR OWNER)
MK CONSTRUCTORS
ACCEPTED BY:
CITY of PORT ARTHUR
2of2
Keith Zotzky
From: lon.hubbard epicengr.com <lon.hubbard@epicengr.com>
Sent: Monday, April 25, 2022 10:35 AM
To: Keith Zotzky
Subject: RE: Port Arthur Lift Stations
Keith
In review of the request I concur with the request for an extension of time.The materials issues are affection all our
projects in construction now.
Thank you
Lon A Hubbard PE
EPIC Engineering
409-267-1149
From: Keith Zotzky<Keith.Zotzky@awceng.com>
Sent: Monday,April 25, 2022 10:15 AM
To: lon.hubbard epicengr.com<lon.hubbard@epicengr.com>
Subject: RE: Port Arthur Lift Stations
Good Morning Lon,
Please see the email below from MK/ESI in regard to a necessary time extension for the 12 Lift Station. Let me know if
you agree with this request and the justification.
Thank you,
/ APCENE4OX W LSON&COLE
Keith Zotzky, P.E.(TX,LA),CFM/Project Manager
Keith Zotzky gawceng corn /281.543.2663
Arceneaux Wilson &Cole LLC
3120 Central Mall Drive
Port Arthur, TX 77642
409.724.7888
awceng.com
From: Mike Suire<mikes@mkconstructors.com>
Sent: Monday,April 25,2022 9:41 AM
To: Keith Zotzky<Keith.Zotzky@awceng.com>
Subject: Fw: Port Arthur Lift Stations
1
[External Message]
/I//i <fu%1'e
MK Constructors
16736 IH 10 (physical) 77662
PO Box 1208 (mailing) 77670
Vidor TX
409 769 0089 office
409 769 1288 fax
409 730 3451 cell
mikes@mkconstructors.com
From:Justin Burns<justin@esibmt.com>
Sent: Monday,April 25, 2022 9:39 AM
To: Mike Suire<mikes@mkconstructors.com>
Subject: Port Arthur Lift Stations
Mike, ESI is requesting more time for completion on this project. We have just received all of the pieces needed and are
going to start installing this week.The control panels have just been completed and we can now install them as well. We
needed all components in to begin with gear due to the fact that size is an issue with the platforms. Everything was
needed to insure proper fit. Let us know what we can do... Entergy will have to be involved in most of these so we are
requesting an additional 60 days.
Regards,
Justin Burns
Electrical Specialties Inc.
409-860-5211
2
External Message:This message originated from outside of the awceng.com domain or is not from an authorized AWC
sender. Please use caution when clicking any links, entering any login information, replying to a message,or opening
any attachments. For a judgement-free second opinion,forward this message to fishv@awceng.com.
3