INTEROFFICE MEMORANDUM
WATER UTILITIES DEPARTMENT-ADMINISTRATION
Date: July 22, 2022
To: The Honorable Mayor and City Council
Through: Ronald Burton, City Manager
From: Calvin Matthews, P.E., Water Utilities Director
RE: PR No. 22479—Execute Main Wastewater Plant (WWTP) Improvement Project
Change Order No. 1
Introduction:
The intent of Proposed Resolution No. 22479 is to seek Council's authorization for the
execution of deductive Change Order No. 1 with ALLCO, LLC of Beaumont, Texas for the
improvements of the Main Wastewater Treatment Plant in Port Arthur, Texas with an updated
projected budgetary impact of$67,409,178.00. The proposed cost reduction of$6,234,049.00
is a result of value engineering performed by Freese & Nichols, Inc., ALLCO, LLC, Golden
Triangle Consulting Engineers, and the City of Port Arthur staff.
Background:
The Main Wastewater Treatment Plant is in need of major improvements. This project will
include improvements to the Main Outfall Lift Station, Headworks, Primary Clarifiers and
Vaults, Trickling Filters, Multipurpose Lift Station, Final Clarifiers and RAS/WAS Meter
Station, Filters, Chlorine Contact Basins and Non-Potable Water System, Dewatering
Building, Plant Drain Lift Station, Electrical & Instrumentation and Electrical Buildings,
Mechanical Screens and Washer-Compactors. The Purchasing Division of the Finance
Department advertised for bids in the Port Arthur News on November 17, 2021 and
November 24, 2021, with one bid being received on January 12, 2022 from ALLCO, LLC of
Beaumont, Texas. The bid amount received was $73,643,227.00 and the project was awarded
to ALLCO, LLC of Beaumont, Texas by Council Resolution No. 22-147. The Main
Wastewater Treatment Plant project is fully funded, with $56,237,412.00 from Account No.
404-40-000-8516-00-00-000, Project No. TW-0003-CON and $17,405,815.00 from 169-07-
015-8516-00-40-000, Project No. ARP002-GRE-WWT.
Budget Considerations:
The total projected budgetary amount of this change order is $6,234,049.00, reducing the total
projected budgetary impact from $73,643,227.00 to $67,409,178.00. $56,237,412.00 will still
be funded from a Texas Water Development Board (TWDB) loan, Account No. 404-40-000-
8516-00-00-000, Project No. TW-0003-CON, and $11,171,766.00 will be funded through an
ARPA Grant and charged to Account No. 169-07-015-8516-00-40-000, Project No. ARP002-
GRE-W WT.
Recommendation:
I recommend City Council approve PR No. 22479 authorizing the execution of deductive
Change Order No. 1 with ALLCO, LLC of Beaumont, Texas, reducing the project cost by
$6,234,049.00 as described/outlined above.
PR No. 22479
7/22/22 bw
Page 1 of 2
RESOLUTION NO.
A RESOLUTION AUTHORIZING THE CITY MANAGER
TO EXECUTE DEDUCTIVE CHANGE ORDER NO. 1
WITH ALLCO, LLC OF BEAUMONT, TEXAS, TO
PROVIDE A COST REDUCTION OF $6,234,049.00 TO A
NEW TOTAL CONTRACT AMOUNT OF $67,409,178.00
FOR THE REHABILITATION AND MODIFICATION OF
THE MAIN WASTEWATER TREATMENT PLANT WITH
FUNDING AVAILABLE THROUGH THE FOLLOWING:
$56,237,412.00 FROM ACCOUNT NO. 404-40-000-8516-00-
00-000, PROJECT NO. TW-0003-CON AND $11,171,766.00
FROM 169-07-015-8516-00-40-000, PROJECT NO. ARP002-
GRE-WWT.
WHEREAS, Council approved Resolution No. 22-147, awarding the Main Wastewater
Treatment Plant Rehabilitation project to ALLCO, LLC of Beaumont,Texas; and,
WHEREAS, a proposed cost reduction of$6,234,049.00 is a result of value engineering
performed by Freese & Nichols, Inc., ALLCO, LLC, Golden Triangle Consulting Engineers and
the City of Port Arthur staff.
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE
CITY OF PORT ARTHUR:
THAT,the facts and opinions in the preamble are true and correct; and,
THAT,the City Manager of the City of Port Arthur is hereby authorized and directed to
execute Change Order No. 1 for ($6,234,049.00) with ALLCO, LLC of Beaumont, Texas in
substantially the form as attached hereto as Attachment "A", for the rehabilitation and
modification of the main Wastewater Treatment Plant in Port Arthur, Texas, to a new projected
budgetary amount of$67,409,178.00; and,
THAT, this project will be partially funded by $56,237,412.00 from a Texas Water
Development Board (TWDB) loan and charged to Account No. 404-40-000-8516-00-00-000,
Project No. TW-0003-CON; and,
THAT, the balance of $11,171,766.00 will be funded through an ARPA Grant and
charged to 169-07-015-8516-00-40-000, Project No. ARP002-GRE-WWT; and,
PR No. 22479
7/22/22 bw
Page 2 of 2
THAT, such funds shall be used only to make payments as required under this contract;
and,
THAT, a copy of the caption of this Resolution be spread upon the Minutes of the City
Council.
READ, ADOPTED AND APPROVED THIS day of . 2022 at a
Regular Meeting of the City Council of the City of Port Arthur,Texas, by the following vote:
AYES: Mayor •
Councilmembers
NOES:
Thurman"Bill"Bartie
Mayor
ATTEST: APPROVED AS TO FORM:
aria ‘Xity07
Sherri Bellard Valecia Ti eno U
City Secretary City Attorney
APPROVED FOR ADMINISTRATION: APPROVED FOR FUNDING:
CA-j i )
Ronald Burton Kandy Danie
City Manager Interim Finance Director
4411
V46L
alvin Matthews, P.E. Clifton Williams, CPPB
Water Utilities Director Purchasing Manager
ATTACHMENT A
(CHANGE ORDER NO. 1)
Change Order No. 1
Project Port Arthur Main Wastewater Treatment Plant Improvements Project Number
Owner City of Port Arthur FNI: PTR22379
Contractor Allco, LLC CoPA: PR22416
Construction Manager Rami Abusheikh, PE
Design Professional Murali Erat, PE
CoPA Account No. 169-07-015-8516-00-40-000;404-40-000-8516-00-00-000
CoPA Project No. ARP002-GRE-WWT; TW-0003-CON
Change Order No. 001 Date 07/21/2022
Make the following modifications to the Contract Documents:
Item Description Change Amount
1 Delete Extra Work in Base Bid (Items C-01 through C-06). $ 405,500
2 Delete Alternate Bid Item D-02 (Aeration Basin Blower Building Improvements
(w/Multi-Stage Centrifugal Blowers) from scope of work. $ 402,900
3 Change concrete pavement to HMA pavement (8"flex base w/2.5" asphalt
surface). See civil sheets attached. $ 110,000
4 Change above ground flange nuts and bolts material type from 316 stainless
steel to high-strength low-alloy corrosion resistant steel with cadmium plating.
Change mechanical joint tee head bolts and nuts material type from 316
stainless steel to standard t-bolt that are high-strength low-alloy steel
manufactured by Star Pipe Products. See revised specification Section 33 05
01.02 Ductile Iron Pipe and Fittings, 2.01. C. attached to this change order. $ 664,063
5 Provide insulation for exposed smaller diameter piping 2-inch in size and
smaller instead of 4-inch as indicated in several contract drawings. Insulation
shall be a minimum of%-inch in thickness. $ 70,000
6 Change lining type for all gravity ductile iron pipe and fittings from Protecto 401
Ceramic Epoxy Lining by Enduron or American Polybond Plus to cement mortar
lining in accordance with AWWA C104 and bituminous seal coat. See revised
specification Section 33 05 01.02 Ductile Iron Pipe and Fittings, 2.01. G.
attached to this change order. $ 150,346
7 a) Change electrical conduit elbows 1.5 inches and larger from Sweeping
PVC coated ARC to RNC,Type EPC-40-PVC. See revised specification
Section 26 05 33, attached to this change order.
b) Change all electrical rack mounting to handrail mounting. $ 152,605
9 In-lieu of galvanization of the helical piles, provide thicker wall material with a
portion allocated as sacrificial steel under the worst-case corrosion of 1/8-inch
material loss for all steel in contact with the soil over the 100-year design of the
project. See revised specification Section 31 68 30 Helical Piles. $ 668,129
10 Change trickling filter media material from PVC to PolyPropyelene (PP). See
revised specification Section 46 53 24 Trickling Filter Media attached to this
change order. $ 298,000
11 Change material type for the double-wall chemical storage tank for sodium
bisulfite from fiberglass reinforced plastic(FRP) to High-Density Polyethylene
(HDPE). Replace specification Section 43 4145 Fiberglass Reinforced Plastic
Storage Tanks with the attached Section 43 4143 Polyethylene Chemical
Storage Tanks. $ 110,000
Change Order No. 1 Page 1 of 3
Change Order No. 1
12 Reduce scum trough length from full-radius to standard 6' beach and provide 4'
cage/trough in lieu of 5'cage/trough for the Final Clarifiers. See attached
changes to FC Sheets and specification Section 46 43 21.02 Circular Suction
Header Collectors. $ 44,117
13 Remove one filter unit to reduce the total capacity from 45 MGD to 30 MGD.
See revised FIL sheets and specifications Section 46 6141 Automatic Backwash
Disk Filters. $ 1,604,700
14 Remove grit removal equipment from scope of supply. Remove specification
Section 46 23 23 Grit Removal Equipment from the contract documents $ 997,500
15 Discount in contract price offered by the contractor without change in scope of
work:
a. Temporary bypass piping at headworks
b. Suction clarifiers
c. Gates
d. Vertical centrifugal pumps
e. Submersible pumps—Main Outfall Lift Station
f. Building/architectural items
g. Mechanical screen and washer compactor equipment
h. Turbo blowers
_._. __ ......__ $ 556,189
Net Change in Contract Price this Change Order $ 6,234,049
Net Change in Contract Times this Change Order 0 days
The compensation in this Change Order is the full, complete, and final compensation for all costs Contractor may
incur because of or relating to this change whether said costs are known, unknown,foreseen, or unforeseen at this
time, including without limitation, any cost for delay, extended overhead, ripple or impact cost, or any other effect
on changed or unchanged Work because of this Change Order. The changes in Contract Times are the complete and
final adjustments for impacts to the ability of Contractor to complete the Work within the Contract Times and are
the only adjustments to which Contractor is entitled. All terms and provisions of the Contract Documents remain in
effect except as specifically modified by this Change Order.
a. Original Contract Price $ 73,643,227
b. Previously Approved Change Order/Contract Amendment Amounts $ 0
c.Adjusted Contract Price( a+ b) $ 73,643,227
d. Contract Amendment Amount $ -6,234,049
e. Revised Contract Price(c+d ) $ 67,409,178
f. Percent Change in Contract Price to Date -8.5
Original Previous Current
Substantial Completion Date 7/5/2026 N/A 7/5/2026
Final Completion Date 10/3/2026 N/A 10/3/2026
Change Order No. 1 Page 2 of 3
Change Order No. 1
Recommended by Design Professional: Recommended by Construction Manager:
07/21/2022 07/21/2022
Mural!Erat, PE Date Rami Abusheikh, PE Date
(Freese and Nichols, Inc.) (Freese and Nichols, Inc.)
Approved by Contractor: Approved by Owner:
Tom Harrison Date Ronald Burton Date
President City Manager
Alko, LLC City of Port Arthur
Approved by Owner:
Calvin Matthews, PE Date
Director of Water Utilities
City of Port Arthur
Change Order No. 1 Page 3 of 3