Loading...
HomeMy WebLinkAboutPR 22731: AWC, CHANGE ORDER NO. 2 FOR THE REHABILITATION PROJECT OF THE PIONEER PARK LIFT STATION J tirt rt :t 1 INTEROFFICE MEMORANDUM Date: August 18, 2022 To: The Honorable Mayor and City Council Through: Ronald Burton, City Manager From: Calvin Matthews, P.E., Water Utilities Director RE: PR 22731 —Approval of Change Order No. 2 for the Rehabilitation Project of the Pioneer Park Lift Station Introduction: The intent of this Agenda Item is to seek City Council's approval of Change Order No. 2 for the Rehabilitation Project at the Pioneer Park Lift Station. In April of 2021, the Council passed Resolution No. 21-133, awarding the Rehabilitation of the Pioneer Park Lift Station contract to BDS Constructors, LLC dba MK Constructors of Vidor, Texas. The project engineer is Arceneaux, Wilson, &Cole, LLC of Port Arthur, Texas as delineated in Resolution No. 19-264. In August of 2021,the Council passed Resolution No. 21-340, awarding Change Order No. 1 as a non-monetary change order extending the contract time by sixty (60) days due to shipping delays by the equipment supplier for the project's submersible pumps. Change Order No. 2 is also a non-monetary change order extending the contract time by one hundred eighty-eight(188) days due to delays by Entergy and various equipment shipment delays. Background: In April of 2021, the Council passed Resolution No. 21-133, awarding the Rehabilitation of the Pioneer Park Lift Station contract to BDS Constructors, LLC dba MK Constructors of Vidor, Texas.Per Rresolution, 19-264,the project engineer is Arceneaux, Wilson,&Cole,LLC of Port Arthur, Texas. Budget Impact: No impact. Recommendation: It is recommended that City Council adopt Proposed Resolution No. 22731, which authorizes the acceptance of Change Order No. 2 for the Rehabilitation Project at the Pioneer Park Lift Station. "Remember, we are here to serve the Citizens of Port Arthur" PR No. 22731 8/18/2022 ta/bw Page 1 of 2 RESOLUTION NO. A RESOLUTION AUTHORIZING THE CITY MANAGER TO EXECUTE CHANGE ORDER NO. 2 BETWEEN THE CITY OF PORT ARTHUR AND BDS CONSTUCTORS, LLC DBA MK CONSTRUCTORS OF VIDOR, TEXAS, EXTENDING THE CONTRACT TIME BY ONE HUNDRED EIGHTY-EIGHT (188) DAYS FOR THE PIONEER PARK LIFT STATION REHABILITATION PROJECT. WHEREAS, per Resolution No. 19-264, the City Council approved a contract with Arceneaux, Wilson& Cole, LLC to provide engineering design and construction services for the rehabilitation of Pioneer Park Lift Station in the not to exceed amount of$126,200.00; and, WHEREAS, per Resolution No. 21-133, City Council approved the Rehabilitation Project at the Pioneer Park Lift Station in the amount of $774,065.00, made with BDS Constructors, LLC dba MK Constructors of Vidor,Texas; and, WHEREAS, per Resolution No. 21-340, City Council approved Change Order #1, extending the contract time by 60 days due to shipping delays by the equipment supplier; and, WHEREAS, the project engineering firm, Arceneaux Wilson & Cole LLC, has submitted Change Order #2 (attached hereto as Exhibit "A") for the Rehabilitation Project at the Pioneer Park Lift Station, extending the contract time by one hundred eighty-eight (188) days due to Entergy's delays and various equipment shipment delays. NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PORT ARTHUR: THAT,the facts and opinions in the preamble are true and correct; and, THAT,the City Manager of the City of Port Arthur is hereby authorized and directed to execute Change Order No. 2 with BDS Constructors, LLC dba MK Constructors of Vidor, Texas, for the Rehabilitation Project at the Pioneer Park Lift Station, extending the contract time by one hundred eighty-eight (188) days due to Entergy's delays and various equipment PR No. 22731 8/18/2022 ta/bw Page 2 of 2 shipment delays; and, THAT, a copy of the caption of this Resolution be spread upon the Minutes of the City Council. READ,ADOPTED,AND APPROVED THIS day of , 2022 at a Regular Meeting of the City Council of the City of Port Arthur, Texas, by the following vote: AYES: Mayor ; Councilmembers ; ; NOES: • Thurman"Bill" Bartie Mayor ATTEST: APPROVED AS TO FORM: /A- tte a-Pt-- Li/Leff/3 Sherri Bellard Valecia zeno City Secretary City Attorney APPROVED FOR ADMINISTRATION: APPROVED FOR FUNDING: KCA.,,( //) (A.A.,x.,_ _0 Ronald Burton Kandy Da iel City Manager Interim Finance Director cor lit" .! , 64,,:, Calvin Matthews, P.E. Clifton illiams, CPPB Water Utilities Director Purchasing Manager EXHIBIT A (Change Order No. 2) ®®. rff ARCENEAUX WILSON&COLE e..Igi,rr,u„l,,,�,r ,r,�,l Pl".'' nA August 09, 2022 Mr. Calvin Matthews, P.E. City of Port Arthur Director of Water Utilities 444 4th Street Port Arthur, Texas 77640 RE Proposal For Change Order No. 02 for PIONEER PARK LIFT STATION REHABILITATION AWC Job No. CPA-975 Mr. Matthews: Attached is Change Order No. 2 for the Pioneer Park Lift Station Rehabilitation project. This change order is for extending the contract time by one hundred eighty-eight (188) calendar days. The Contractor has experienced delays regarding Entergy's involvement with the project. Over the past two months, Entergy has experienced supply chain delays with their necessary appurtenances for influent main power connection at the lift station site. The Contractor has now received all the necessary equipment from Entergy and can move forward with its installation. Also, the equipment supplier for the project's level transmitters has informed the Contractor of an 8-week shipping delay beyond the original anticipated delivery timeframe. The Contractor has currently completed all the project's scope of work,with exception to final electrical connection, pump start-up, and existing force main tie-in. These remaining scope items are scheduled to be completed within the next 75 calendar days and are dependent on receipt of the wet well level transmitters and Entergy's final site inspection. 409.724.7888 2901 Tuttle Creek Dr.,Suite 320 Port Arthur TX 77642 Engineering Surveying awceng.com F 16194 10194049 anivc TO FA .. This change order will add 188 Calendar Days to the original contract time to account for the experienced equipment and Entergy delays, and reconcile the previously requested 113 day extension via the original Change Order No. 2. There are no costs associated with this change order. We recommend that the City of Port Arthur authorize this change order to the contract as submitted. We have attached Change Order No. 2 which modifies the contract to reflect this change for your consideration and action. Should you have any questions or require additional information, please contact our office. ARCENEAUX W/LSON&COLE LLC TEXAS REGISTERED ENGINEERING FIRM F-16194 Keith Zotzky, . ., CFM Attached Change Order#02 MK Constructors Time Suspension Request Original Change Order#02 ig /'_ ♦ W e" ARCENEAUX WILSON&COLE CHANGE ORDER NO. 2 DATE: August 9, 2022 JOB NO.: CPA-975 AGREEMENT DATE: April 13, 2021 NAME OF PROJECT: Pioneer Park Lift Station Rehabilitation OWNER: CITY of PORT ARTHUR CONTRACTOR: MK CONSTRUCTORS The following changes are hereby made to the CONTRACT DOCUMENTS: 1. Extend Contract Time by 188 Calendar Days to account for Entergy and equipment delivery delays, and account for previously requested extension via original Change Order#02. TOTAL $0.00 CHANGE TO CONTRACT PRICE: ORIGINAL CONTRACT PRICE: $774,065.00 CURRENT CONTRACT PRICE adjusted by previous CHANGE ORDER(S): $774,065.00 The CONTRACT PRICE due to this CHANGE ORDER will be by: $0.00 The new CONTRACT PRICE, including this CHANGE ORDER, will be $774,065.00 1 of 2 CHANGE ORDER NO. 2 •:Ii .i August 9, 2022 '� Job No. CPA-975 ARCENEAUX WILSON�&COLE CHANGE TO CONTRACT TIME: ORIGINAL CONTRACT TIME: 180 Calendar Days CURRENT CONTRACT TIME adjusted by previous CHANGE ORDER: 60 Calendar Days CURRENT DATE OF COMPLETION: March 12, 2022 CONTRACT TIME due to this CHANGE ORDER will be increased by 188 Calendar Days The New DATE OF COMPLETION: September 16, 2022 No other Terms and Conditions of the Contract are changed as a result of this Change Order. Contractor's acceptance of Change Order relieves OWNER of any liability for additional costs incurred by Contractor in his performance of the work covered by the Change Order. RECOMMENDED BY ENGINEER: ACCEPTED BY: .,,„,-; ki . \— (_,. .__., ' -7- ' ' .., .,- , A . ARC NEAWCW1b5 N & COLE LLC ; (CONTRACT ,OFFICER-et OWNER) -MK CONSTRUCTORS G } �p ACCEPTED BY: c3 t ,,,k ;\.S-L #t'..) 1 �" 1'I ' (�-e. J Al&I CITY of P RT ARTHUR 2 of 2