INTEROFFICE MEMORANDUM
Date: August 18, 2022
To: The Honorable Mayor and City Council
Through: Ronald Burton, City Manager
From: Calvin Matthews, P.E., Water Utilities Director
RE: PR 22731 —Approval of Change Order No. 2 for the Rehabilitation Project of
the Pioneer Park Lift Station
Introduction:
The intent of this Agenda Item is to seek City Council's approval of Change Order No. 2 for the
Rehabilitation Project at the Pioneer Park Lift Station. In April of 2021, the Council passed
Resolution No. 21-133, awarding the Rehabilitation of the Pioneer Park Lift Station contract to
BDS Constructors, LLC dba MK Constructors of Vidor, Texas. The project engineer is
Arceneaux, Wilson, &Cole, LLC of Port Arthur, Texas as delineated in Resolution No. 19-264.
In August of 2021,the Council passed Resolution No. 21-340, awarding Change Order No. 1 as
a non-monetary change order extending the contract time by sixty (60) days due to shipping
delays by the equipment supplier for the project's submersible pumps. Change Order No. 2 is
also a non-monetary change order extending the contract time by one hundred eighty-eight(188)
days due to delays by Entergy and various equipment shipment delays.
Background:
In April of 2021, the Council passed Resolution No. 21-133, awarding the Rehabilitation of the
Pioneer Park Lift Station contract to BDS Constructors, LLC dba MK Constructors of Vidor,
Texas.Per Rresolution, 19-264,the project engineer is Arceneaux, Wilson,&Cole,LLC of Port
Arthur, Texas.
Budget Impact:
No impact.
Recommendation:
It is recommended that City Council adopt Proposed Resolution No. 22731, which authorizes
the acceptance of Change Order No. 2 for the Rehabilitation Project at the Pioneer Park Lift
Station.
"Remember, we are here to serve the Citizens of Port Arthur"
PR No. 22731
8/18/2022 ta/bw
Page 1 of 2
RESOLUTION NO.
A RESOLUTION AUTHORIZING THE CITY MANAGER
TO EXECUTE CHANGE ORDER NO. 2 BETWEEN THE
CITY OF PORT ARTHUR AND BDS CONSTUCTORS, LLC
DBA MK CONSTRUCTORS OF VIDOR, TEXAS,
EXTENDING THE CONTRACT TIME BY ONE HUNDRED
EIGHTY-EIGHT (188) DAYS FOR THE PIONEER PARK
LIFT STATION REHABILITATION PROJECT.
WHEREAS, per Resolution No. 19-264, the City Council approved a contract with
Arceneaux, Wilson& Cole, LLC to provide engineering design and construction services for the
rehabilitation of Pioneer Park Lift Station in the not to exceed amount of$126,200.00; and,
WHEREAS, per Resolution No. 21-133, City Council approved the Rehabilitation
Project at the Pioneer Park Lift Station in the amount of $774,065.00, made with BDS
Constructors, LLC dba MK Constructors of Vidor,Texas; and,
WHEREAS, per Resolution No. 21-340, City Council approved Change Order #1,
extending the contract time by 60 days due to shipping delays by the equipment supplier; and,
WHEREAS, the project engineering firm, Arceneaux Wilson & Cole LLC, has
submitted Change Order #2 (attached hereto as Exhibit "A") for the Rehabilitation Project at the
Pioneer Park Lift Station, extending the contract time by one hundred eighty-eight (188) days
due to Entergy's delays and various equipment shipment delays.
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE
CITY OF PORT ARTHUR:
THAT,the facts and opinions in the preamble are true and correct; and,
THAT,the City Manager of the City of Port Arthur is hereby authorized and directed to
execute Change Order No. 2 with BDS Constructors, LLC dba MK Constructors of Vidor,
Texas, for the Rehabilitation Project at the Pioneer Park Lift Station, extending the contract time
by one hundred eighty-eight (188) days due to Entergy's delays and various equipment
PR No. 22731
8/18/2022 ta/bw
Page 2 of 2
shipment delays; and,
THAT, a copy of the caption of this Resolution be spread upon the Minutes of the City
Council.
READ,ADOPTED,AND APPROVED THIS day of , 2022 at
a Regular Meeting of the City Council of the City of Port Arthur, Texas, by the following vote:
AYES: Mayor ;
Councilmembers ;
;
NOES: •
Thurman"Bill" Bartie
Mayor
ATTEST: APPROVED AS TO FORM:
/A- tte a-Pt-- Li/Leff/3
Sherri Bellard Valecia zeno
City Secretary City Attorney
APPROVED FOR ADMINISTRATION: APPROVED FOR FUNDING:
KCA.,,( //) (A.A.,x.,_ _0
Ronald Burton Kandy Da iel
City Manager Interim Finance Director
cor lit" .! , 64,,:,
Calvin Matthews, P.E. Clifton illiams, CPPB
Water Utilities Director Purchasing Manager
EXHIBIT A
(Change Order No. 2)
®®.
rff ARCENEAUX WILSON&COLE
e..Igi,rr,u„l,,,�,r ,r,�,l Pl".'' nA
August 09, 2022
Mr. Calvin Matthews, P.E.
City of Port Arthur
Director of Water Utilities
444 4th Street
Port Arthur, Texas 77640
RE Proposal For Change Order No. 02 for
PIONEER PARK LIFT STATION REHABILITATION
AWC Job No. CPA-975
Mr. Matthews:
Attached is Change Order No. 2 for the Pioneer Park Lift Station Rehabilitation
project. This change order is for extending the contract time by one hundred
eighty-eight (188) calendar days.
The Contractor has experienced delays regarding Entergy's involvement with the
project. Over the past two months, Entergy has experienced supply chain delays
with their necessary appurtenances for influent main power connection at the lift
station site. The Contractor has now received all the necessary equipment from
Entergy and can move forward with its installation. Also, the equipment supplier
for the project's level transmitters has informed the Contractor of an 8-week
shipping delay beyond the original anticipated delivery timeframe. The
Contractor has currently completed all the project's scope of work,with exception
to final electrical connection, pump start-up, and existing force main tie-in. These
remaining scope items are scheduled to be completed within the next 75
calendar days and are dependent on receipt of the wet well level transmitters and
Entergy's final site inspection.
409.724.7888
2901 Tuttle Creek Dr.,Suite 320
Port Arthur TX 77642 Engineering Surveying
awceng.com F 16194 10194049
anivc
TO FA
..
This change order will add 188 Calendar Days to the original contract time to
account for the experienced equipment and Entergy delays, and reconcile the
previously requested 113 day extension via the original Change Order No. 2. There
are no costs associated with this change order. We recommend that the City of
Port Arthur authorize this change order to the contract as submitted. We have
attached Change Order No. 2 which modifies the contract to reflect this change
for your consideration and action.
Should you have any questions or require additional information, please contact
our office.
ARCENEAUX W/LSON&COLE LLC
TEXAS REGISTERED ENGINEERING FIRM F-16194
Keith Zotzky, . ., CFM
Attached
Change Order#02
MK Constructors Time Suspension Request
Original Change Order#02
ig
/'_
♦ W
e" ARCENEAUX WILSON&COLE
CHANGE ORDER NO. 2
DATE: August 9, 2022 JOB NO.: CPA-975
AGREEMENT DATE: April 13, 2021
NAME OF PROJECT: Pioneer Park Lift Station Rehabilitation
OWNER: CITY of PORT ARTHUR
CONTRACTOR: MK CONSTRUCTORS
The following changes are hereby made to the CONTRACT DOCUMENTS:
1. Extend Contract Time by 188 Calendar Days to account for Entergy and
equipment delivery delays, and account for previously requested
extension via original Change Order#02.
TOTAL $0.00
CHANGE TO CONTRACT PRICE:
ORIGINAL CONTRACT PRICE: $774,065.00
CURRENT CONTRACT PRICE adjusted by previous CHANGE ORDER(S): $774,065.00
The CONTRACT PRICE due to this CHANGE ORDER will be
by: $0.00
The new CONTRACT PRICE, including this CHANGE ORDER, will be $774,065.00
1 of 2
CHANGE ORDER NO. 2
•:Ii .i August 9, 2022
'� Job No. CPA-975
ARCENEAUX WILSON�&COLE
CHANGE TO CONTRACT TIME:
ORIGINAL CONTRACT TIME: 180 Calendar Days
CURRENT CONTRACT TIME adjusted by previous CHANGE ORDER: 60 Calendar Days
CURRENT DATE OF COMPLETION: March 12, 2022
CONTRACT TIME due to this CHANGE ORDER will be increased by 188 Calendar Days
The New DATE OF COMPLETION: September 16, 2022
No other Terms and Conditions of the Contract are changed as a result of this Change Order.
Contractor's acceptance of Change Order relieves OWNER of any liability for additional costs incurred
by Contractor in his performance of the work covered by the Change Order.
RECOMMENDED BY ENGINEER: ACCEPTED BY:
.,,„,-; ki . \— (_,. .__., ' -7- ' ' .., .,- , A .
ARC NEAWCW1b5 N & COLE LLC ; (CONTRACT ,OFFICER-et OWNER)
-MK CONSTRUCTORS G } �p
ACCEPTED BY: c3 t ,,,k ;\.S-L #t'..) 1 �" 1'I ' (�-e.
J
Al&I
CITY of P RT ARTHUR
2 of 2