INTEROFFICE MEMORANDUM
Date: November 10,2022
To: The Honorable Mayor and City Council
Through: Ron Burton; City Manager
From: John Cannatella,PE,City Engineer
RE: P.R. 22390: Arceneaux, Wilson&Cole, LC of Port Arthur,Texas: Master Drainage Plan
Contract Amendment No. 1 —Extension of contract time by 270 calendar days.Project
No.: DR1P05OTH
Introduction:
The intent of this Agenda Item is to authorize the City Manager to accept Contract Amendment No. 1 from
Arceneaux, Wilson&Cole,LLC of Port Arthur,Texas extending the contract time by two hundred seventy
(270)days from the original contract completion date of September 23,2022 to the new contract completion
date of June 20, 2023.
Background:
The City of Port Arthur proposed the development of a citywide master drainage plan and policy guide
that identified potential drainage concerns throughout the City. The City advertised for engineering
firms to submit their qualifications regarding their ability to develop a citywide master drainage plan.
Arceneaux, Wilson & Cole, LLC (AWC) of Port Arthur, Texas was selected to develop this plan.
Pursuant to Resolution No. 21-345, the City of Port Arthur City Council approved entering into a
contract with AWC for the not-to-exceed amount of$1,285,300.00 for a period of three hundred sixty-
five (365)days.
AWC is requesting approval of Contract Amendment No. 1 that will add an additional two hundred
seventy (270) calendar days to the contract completion date citing complexity of completing citywide
tasks, its desire to provide a quality product,weather delays, and COVID.
Budget Impact:
There is no budgetary impact associated with Contract Amendment No. 1.
Recommendation:
It is recommended that the City of Port Arthur City Council approve PR 22390 with Arceneaux, Wilson&
Cole,LLC of Port Arthur,Texas authorizing the City Manager to accept Contract Amendment No. 1.
"Remember,we are here to serve the Citizens of Port Arthur"
444 4th Street X Port Arthur,Texas 77641-1089 X 409.983.8182 X FAX 409.983.8294
PR No.22390
11/10/2022 mje
Page 1 of 3
RESOLUTION NO.
A RESOLUTION AUTHORIZING THE CITY MANAGER TO EXECUTE
CONTRACT AMENDMENT NO. 1, ADDING 270 CALENDAR DAYS TO THE
ORIGINAL CONTRACT COMPLETION DATE OF SEPTEMBER 23, 2022
AMENDING IT TO THE NEW CONTRACT COMPLETION DATE OF JUNE 20,
2023 FOR ARCENEAUX, WILSON & COLE, LLC OF PORT ARTHUR, TEXAS
TO COMPLETE ITS DEVELOPMENT OF A CITYWIDE MASTER DRAINAGE
PLAN FOR THE NOT-TO-EXCEED AMOUNT OF $1,285,300.00. FUNDS ARE
AVAILABLE IN PROJECT NO. DR1P05-OTH AND DR1P05-OTH-CDF.
WHEREAS, the City of Port Arthur proposes the development of a citywide master
drainage plan that identifies potential drainage problems with the goal of developing a road map
for future drainage-related activities; and,
WHEREAS, Arceneaux, Wilson & Cole, LLC of Port Arthur, Texas was selected by staff
as the most qualified submitter to produce the master drainage plan and policy; and,
WHEREAS, pursuant to Resolution No. 21-345, the City of Port Arthur City Council
approved entering into a contract with Arceneaux, Wilson & Cole, LLC of Port Arthur, Texas for
the not-to-exceed amount of $1,285,300.00; and,
WHEREAS, Arceneaux, Wilson & Cole, LLC of Port Arthur, Texas has submitted a
Proposal for Contract Amendment No. 1 for Master Drainage Plan to extend the contract time
by an additional two hundred seventy days (270) calendar days to the original contract
completion date, See Exhibit A; and,
WHEREAS, Arceneaux, Wilson & Cole, LLC of Port Arthur, Texas recommends the
additional time to allow for the complexity of completing the citywide tasks, its desire to provide
a quality product, weather delays, and COVID; and,
PR No. 22390
11/10/2022 mje
Page 2 of 3
WHEREAS, approval of Contract Amendment No. 1 for the addition of two hundred
seventy (270) calendar days amending the original contract completion date of September 23,
2022 to June 20, 2023 is herein deemed an appropriate action; now, therefore,
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PORT ARTHUR:
THAT, the facts and opinions in the preamble are true and correct; and,
THAT, the City Council hereby authorizes the City Manager to execute Contract
Amendment No. 1 submitted by Arceneaux, Wilson &Cole, LLC of Port Arthur, Texas, see Exhibit
B; and,
THAT, a copy of the caption of this Resolution No. be spread upon the Minutes of the
City Council.
READ, ADOPTED AND APPROVED this the day of , A.D.
2022 at a meeting of the City of Port Arthur, Texas by the following
vote: Ayes: Mayor:
Councilmembers:
Noes:
Thurman "Bill" Bartle
Mayor
ATTEST:
Sherri Bellard
City Secretary
PR No.22390
11/10/2022 mje
Page 3 of 3
APPROVED AS TO FORM: APPROVED FOR ADMINISTRATION:
Valecia Ti eno Ron Burton
City Attorney City Manager
APPROVED AS FOR AVAILABILITY OF
FUNDS:
Kandy Daniel
Interim Director of Finance
J n,Cannatella, PE
City Engineer
Clifton Williams, CPPB
Purchasing Manager
EXHIBIT A
CITY OF PORT ARTHUR
Public Works Engineering
DATE: NOVEMBER 10,2022
PROJECT: MASTER DRAINAGE PLAN
OWNER: CITY OF PORT ARTHUR
CONTRACTOR: ARCENEAUX,WILSON&COLE,LLC OF PORT ARTHUR,TEXAS
CONTRACT AMENDMENT NO.:01
THE FOLLOWING CHANGES IN THE PLANS AND/OR SPECIFICATIONS ARE HEREBY MADE:
Adjust the Estimated Quantities to reflect the Actual Quantities used in the completion of the project:
Item Item Original Original Final
Description Unit Unit Price
No. Code Quantity Amount Amount
NO CHANGE TO CONTRACT AMOUNT
ORIGINAL CONTRACT AMOUNT $ 1,285,300.00 $ 1,285,300.00
ORIGINAL CONTRACT AMOUNT: $ 1,285,300.00
NET FROM PREVIOUS AMENDMENTS: $
TOTAL AMOUNT OF THIS AMENDMENT NO.1: $
PERCENT OF THIS AMENDMENT NO.1:
TOTAL PERCENT AMENDMENT NO.1:
FINAL CONTRACT AMOUNT: $ 1,285,300.00
270 CALENDAR DAYS HAVE BEEN ADDED IN THE CONTRACT BY AMENDMENT NO.1
ORIGINAL CONTRACT COMPLETION DATE: SEPTEMBER 23,2022
ADDITIONAL CONTRACT DAYS: 270
NEW CONTRACT COMPLETION DATE: JUNE 20,2023
ACCEPTED BY: PREPARED BY:
Keith Zotzky,PE,CFM Arceneaux, M.Jennifer Edwards,BAAS,MPA CIP
Wilson&Cole,LLC Manager
APPROVED BY: APPROVED BY:
John Cannatella,P.E.,City Engineer Clifton Williams,CPPB,Purchasing Manager
APPROVED BY:
Ronald Burton,City Manager
EXHIBIT B
tv. emit
ARCENEAUX WILSON&COLE
engineering I surveying I planning
November 09, 2022
Mr. John Cannatella, P.E.
City of Port Arthur
City Engineer
444 4th Street
Port Arthur, Texas 77640
RE: Proposal For Contract Amendment No. 1 for
Master Drainage Plan
AWC Job No. CPA-1030
Mr. Cannatella:
Attached is Contract Amendment No.1 for the Master Drainage Plan project. This
contract amendment is for extending the contract time by two hundred seventy
(270) calendar days.
During preliminary project planning with the City, AWC recommended an 18-
month contract time for completion of the scope of work. This recommended
timeframe took into consideration the complexity of completing a city wide
hydrologic & hydraulic (H&H) model, and the amount of field survey time
necessary to build an accurate database of the City's entire drainage
infrastructure system. As part of the executed contract between the City and
AWC, the City would only allot for and initial 12-month contract time to complete
the final scope of work. Currently, AWC is working through the final stages of
QA/QC of all the gathered field data necessary to build an accurate GIS database
and existing system model. At the request of the City, an H&H model has been
completed for the far southwestern portion of the existing storm sewer system
due to recent flooding events. AWC has also been working concurrently towards
completing the Drainage Criteria Manual. Given the number of tasks remaining
409.724.7888
3120 Central Mali Drive
Port Arthur,TX 77642 Engineering Surveying
awceng.com F-16194 10194049
.A0) •
.M
to complete, we feel it is inherently important to request the City consider
extending the contract time to 21-months in order to not jeopardize the quality
of final deliverable products. AWC has also experienced obstacles such as
inaccessible and buried manholes, and delays due to weather and COVID-19 since
commencing work on this project.
This change order will add 270 Calendar Days (9-months) to the original contract
time. There are no costs associated with this change order. We recommend that
the City of Port Arthur authorize this change order to the contract as submitted.
We have attached Contract Amendment No. 1 which modifies the contract to
reflect this change for your consideration and action.
Should you have any questions or require additional information, please contact
our office.
ARCENEAUX WILSON & COLE LLC
Keith Zotzky, . ., CFM
Attachments:
Revised Design Schedule
k
4DA ARCENEAUX WILSON&COLE
engineering I surveying I planning
MASTER DRAINAGE PLAN REVISED DESIGN SCHEDULE
PHASE CALENDAR DAYS
1. Data Acquisition (30%) 390
2. System Analysis (60%) 180
3. Draft of Master Drainage Plan (90%) 40
4. Final Master Drainage Plan (100%) 25
409.724.7888
3120 Central Mall Drive
Port Arthur,TX 77642 Engineering Surveying
awceng.com F-16194 10194049
'fa 416/r
..
1. DATA ACQUISITION 30% (390 Days- October 18, 2022)
A. A Data Acquisition Memorandum shall be completed in this phase
and will include the following:
B. Survey and verification evaluation of soil conditions for surficial
drainage of existing system.
C. Condition assessment of existing storm water facilities.
D. Applicable floodplain data.
E. Acquire data USACE, DD7 and previous drainage studies.
F. Existing drainage boundaries.
G. Potential problem areas in the City's drainage system.
H. Outline template for GIS inventory map, as determined by the City.
I. Review/analysis of City's existing design criteria for development.
2. SYSTEM ANALYSIS SUBMITTAL 60% (180 Days-April 16, 2023)
A. A system Analysis Memorandum shall be completed in this phase and
will include the following:
B. Hydrology study and results.
C. Hydraulic analysis and results.
D. Proposed system improvements per basin as determined by
hydraulic analysis.
E. Identification of growth areas in the city and their impact on system.
F. 1st draft of city design criteria for development.
G. Development of improvement ranking system.
3. DRAFT of FINAL REPORT SUBMITTAL 90% (40 Days- May 26, 2023)
A. The Draft of Final Report shall include the following:
B. All items in the 30% and 60%submittals in draft form.
C. All maps and exhibits as indicated by reports and findings.
D. Recommendations with schedule for improvements and
implementation.
E. Cost Estimate for recommended improvements.
F. City design criteria for development.
4. FINAL MASTER DRAINAGE PLAN 100% (25 Days -June 20, 2023)
A. Final Master Drainage Plan will be finalizing the 90% plan submittal
by addressing comments received as a result of the City review.
B. The ENGINEER shall provide the Final Master Drainage Plan in
electronic format as well as (5) bound sets of the final document.