PR 22892: EXECUTE MAIN WASTEWATER PLANT (WWTP) IMPROVEMENT PROJECT CHANGE ORDER NO. 2
City of n rt rth u�r Texas INTEROFFICE MEMORANDUM WATER UTILITIES DEPARTMENT-ADMINISTRATION Date: December 2, 2022 To: The Honorable Mayor and City Council Through: Ronald Burton, City Manager From: Calvin Matthews, P.E., Water Utilities Director RE: PR No. 22892 —Execute Main Wastewater Plant (WWTP) Improvement Project Change Order No. 2 Introduction: The intent of this agenda item is to seek Council's authorization for the execution of deductive Change Order No. 2 with ALLCO, LLC of Beaumont, Texas for the rehabilitation and modification of the Main Wastewater Treatment Plant in Port Arthur, Texas with an updated projected budgetary impact of$67,335,613.43. Freese &Nichols, Inc. has submitted Change Order No. 2 for the contract with a cost increase for Primary Clarifiers subgrade stabilization, Drying Beds demo, Demo and Remove CSS, Helical Piles and Brentwood PVC TF Media price increase and reduction for the removal of VE Lighting Package, use of bank sand for pipe bedding, and remove Admin Building improvements. This Change Order No. 2 includes a 75-day time extension with a final project end date of December 17, 2026. Background: The Main Wastewater Treatment Plant is in need of major improvements. This project will include improvements to the Main Outfall Lift Station, Headworks, Primary Clarifiers and Vaults, Trickling Filters, Multipurpose Lift Station, Final Clarifiers and RAS/WAS Meter Station, Filters, Chlorine Contact Basins and Non-Potable Water System, Dewatering Building, Plant Drain Lift Station, Electrical & Instrumentation and Electrical Buildings, Mechanical Screens and Washer-Compactors. The Purchasing Division of the Finance Department advertised for bids in the Port Arthur News on November 17, 2021 and November 24, 2021, with one bid being received on January 12, 2022 from ALLCO, LLC of Beaumont, Texas. The bid amount received was $73,643,227.00 and the project was awarded to ALLCO, LLC of Beaumont, Texas by Council Resolution No. 22-147. On August 2, 2022, the City Council approved Resolution No. 22-329, approving Change Order No. 1 to the contract in the amount of ($6,234,049.00) due to value engineering performed by Freese & Nichols, Inc., ALLCO, LLC, Golden Triangle Consulting Engineers and the City of Port Arthur staff for a new contract amount of$67,409,178.00 The Main Wastewater Treatment Plant project is fully funded, with $56,237,412.00 from Account No. 404-40-000-8516-00-00-000, Project No. TW-0003-CON and $11,171,766.00 from 169-07-015-8516-00-40-000, Project No. ARP002-GRE-WWT. Budget Considerations: The total projected budgetary amount of this change order is ($73,564.57), reducing the total projected budgetary impact from $67,409,178.00 to $67,335,613.43. The Main Wastewater Treatment Plant project is fully funded, with $56,237,412.00 from Account No. 404-40-000- 8516-00-00-000, Project No. TW-0003-CON and $11,171,766.00 from 169-07-015-8516-00- 40-000, Project No. ARP002-GRE-WWT. Recommendation: I recommend City Council approve PR No. 22892 authorizing the execution of deductive Change Order No. 2 with ALLCO, LLC of Beaumont, Texas, reducing the project cost by ($73,564.57) as described/outlined above. PR No. 22892 12/2/22 bw Page 1 of 3 RESOLUTION NO. A RESOLUTION AUTHORIZING THE CITY MANAGER TO EXECUTE DEDUCTIVE CHANGE ORDER NO. 2 WITH ALLCO, LLC OF BEAUMONT, TEXAS, TO PROVIDE A COST REDUCTION OF ($73,564.57) TO A NEW TOTAL CONTRACT AMOUNT OF $67,335,613.43 FOR THE REHABILITATION AND MODIFICATION OF THE MAIN WASTEWATER TREATMENT PLANT WITH FUNDING AVAILABLE THROUGH THE FOLLOWING: $56,163,847.43 FROM ACCOUNT NO. 404-40-000-8516-00- 00-000, PROJECT NO. TW-0003-CON AND $11,171,766.00 FROM 169-07-015-8516-00-40-000, PROJECT NO. ARP002- GRE-WWT. WHEREAS, the City Council approved Resolution No. 22-147, awarding the Main Wastewater Treatment Plant Rehabilitation project to ALLCO, LLC of Beaumont, Texas; and, WHEREAS, on August 2, 2022, the City Council approved Resolution No. 22-329, approving Change Order No. 1 to the contract in the amount of ($6,234,049.00) due to value engineering performed by Freese & Nichols, Inc., ALLCO, LLC, Golden Triangle Consulting Engineers and the City of Port Arthur staff for a new contract amount of$67,409,178.00; and, WHEREAS, Freese & Nichols, Inc. has submitted Change Order No. 2 to the contract with a cost increase for Primary Clarifiers subgrade stabilization, Drying Beds demo, Demo and Remove CSS, Helical Piles and Brentwood PVC TF Media price increase and reduction for the removal of VE Lighting Package, use of bank sand for pipe bedding, and remove Admin Building improvements with a projected budgetary impact of($73,564.57) and includes a 75 day time extension with a final project end date of December 17,2026. NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PORT ARTHUR: THAT, the facts and opinions in the preamble are true and correct; and. THAT, the City Manager of the City of Port Arthur is hereby authorized and directed to PR No. 22892 12/2/22 bw Page 2 of 3 execute Change Order No. 2 for ($73,564.57) with ALLCO, LLC of Beaumont, Texas in substantially the form as attached hereto as Attachment "A", for the rehabilitation and modification of the main Wastewater Treatment Plant in Port Arthur, Texas, to a new projected budgetary amount of$67,335,613.43 and includes a 75 day time extension with a final project end date of December 17, 2026; and, THAT, this project will be partially funded by $56,163,847.43 from a Texas Water Development Board (TWDB) loan and charged to Account No. 404-40-000-8516-00-00-000, Project No. TW-0003-CON; and, THAT, the balance of $11,171,766.00 will be funded through an ARPA Grant and charged to 169-07-015-8516-00-40-000, Project No. ARP002-GRE-WWT; and, THAT, such funds shall be used only to make payments as required under this contract; and, THAT, a copy of the caption of this Resolution be spread upon the Minutes of the City Council. READ,ADOPTED AND APPROVED THIS day of , 2022 at a Regular Meeting of the City Council of the City of Port Arthur, Texas, by the following vote: AYES: Mayor Councilmembers NOES: Thurman Bill Bartie Mayor PR No. 22892 12/2/22 bw Page 3 of 3 ATTEST: APPROVED AS TO FORM: Sherri Bellard Valecia Tize o City Secretary City Attorney APPROVED FOR ADMINISTRATION: APPROVED FOR FUNDING: ' �Ct\./\ Ronald Burton Kandy Daniel J City Manager Interim Finance Director 64/ht,_ el) / i Calvin Matthews, P.E. Clifto' Williams, CPPB Water Utilities Director Purchasing Manager ATTACHMENT A (CHANGE ORDER NO. 2) r F7FREESE °NICHOLS 11200 Broadway St.,Suite 2320 + Pearland,Texas 77584 + 832-456-4700 + FAX 817-735-7491 www.freese.com December 1, 2022 Calvin Matthews, PE Director of Water Utilities City of Port Arthur Texas 444 4th Street Port Arthur,TX 77640 Re: Project No. R15056 Port Arthur Main WWTP Improvements: Change Order No.002 Dear Mr. Matthews: Included with this letter is Change Order No. 002 for the above referenced project.This letter is to serve as a narrative for the items included in this Change Order No. 002 with supporting documentation attached. Item No. 1: Demo and Remove Existing Concrete Drying Beds and Clay Pipes In order to install Primary Clarifier A per the plans,Allco had attempted to excavate the area and they discovered that there were abandoned concrete drying beds. The only option was to demolish and remove the concrete drying beds and associated clay pipes.Allco submitted CP-002 for this unforeseen condition with a total cost of $33,735.83 and 14 Calendar Days extension. Freese and Nichols, Inc. agrees with their proposed cost and time extension. This work has been completed. Total Cost: $33,735.83 Additional Days: 14 Calendar Days Item No. 2: Primary Clarifier A Unstable Subgrade Removal and Replacement After removal of the concrete drying beds (Item No. 1), it was discovered that the subgrade consisted of a mix of sand and gravel up to 4 feet below the surface. This sand and gravel mix could not bear the weight of the construction equipment driving over it and was deemed unstable. Freese&Nichols,Inc.and Arceneaux Wilson&Cole explored several options to stabilize the subgrade, but the most economical option was to remove the unstable material and replace it with imported select fill material. Allco submitted CP-001 for this unforeseen condition with a total cost of$99,104.00 and 75 Calendar Days extension.Freese and Nichols,Inc.agrees with their cost but at this moment can only recommend 42 Days.This work has been completed. Total Cost: $99,104.00 Additional Days:42 Calendar Days Item No. 3: Removal of Cement Stabilized Sand Surrounding Existing Primary Clarifier C During the demolition of Primary Clarifier C, it was discovered that the outer walls were encased with Cement Stabilized Sand. Due to the strength of the Cement Stabilized Sand it took a considerable amount of effort by Allco to remove and they submitted CP-003 with a proposed cost of $29,752.00 and 10 Calendar Days extension. Freese and Nichols, Inc. agrees with their proposed cost and time extension.This work has been completed. Total Cost: $29,752.00 Additional Days: 10 Calendar Days PTR22379 T:\4.0 CONSTRUCTION\4.40 Contract Mod\4.43 Chg Orders\Change Order No.2 Item No.4:Shared Cost for Helical Piles Price Escalation Steel prices continue to experience a cost increase due to external factors.The material cost for the Helical Piles had increased from the base bid price by$323,955.20. In order to stop any further escalation in price, and out of good faith, Allco paid a significant down payment to lock in the price. A meeting was held between the City of Port Arthur and Allco where it was agreed upon that the cost increase would be shared among the two. Total Cost: $161,977.60 Additional Days:0 Calendar Days Item No. 5: Brentwood Optimized Trickling Filter PVC Media with Cover While exploring value engineering options, CE Shepherd was chosen for the Trickling Filters PVC Media which resulted in a credit of($298,000.00).This credit was included in Change Order No. 001.Allco was recently contacted by CE Shepherd and informed that they would no longer be able to honor that price. Allco requested updated pricing from other manufacturers and Brentwood offered an optimized PVC Filter Media with Protective Cover, which would allow plant staff to walk on it to service the spraying arms, for $810,000.00. While this cost is lower than the base bid, it would be an increase to balance out what was credited in Change Order no. 001. Cost breakdown is as follows: Trickling Filter Media Cost Balance Brentwood (Base Bid) $987,500.00 CE Shepherd (CO-001 VE) $689,500.00 $ (298,000.00) Brentwood Optimized $810,000.00 $ 120,500.00 Total Cost: $120,500.00 Additional Days: 0 Calendar Days Item No. 6:Value Engineering Lighting Package Revised Pricing While exploring Value Engineering options, Freese & Nichols, Inc. coordinated with W-Industries (Electrical Sub) to find areas where project costs could be optimized. The initial VE Package that W-Industries provided had to be revised and was not included in Change Order No. 001. Their updated VE Package has been reviewed by Freese&Nichols, Inc. and is recommended with a cost savings of($74,792.00). Total Cost: ($74,792.00) Additional Days: 0 Calendar Days Item No. 7:Switch Pipe Embedment from Class 3 & 10 Aggregate to Bank Sand As a Value Engineering option, Allco had proposed replacing the encasement material for pipes where the contract documents called for Class 3 & Class 10 aggregate to select fill. Freese & Nichols, Inc. investigated Allco's proposal and decided that select fill is not viable for pipe encasement. While looking into this option, Freese & Nichols, Inc.'s structural team recommended Bank Sand as an alternative to Class 3 & Class 10 aggregate. The TxDOT specifications for Bank Sand was provided to Allco and they provided pricing that would credit the project with ($254,390.00). Total Cost: ($254,390.00) Additional Days:0 Calendar Days [PTR22379]T:\4.0 CONSTRUCTION\4.40 Contract Mod\4.43 Chg Orders\Change Order No. 2 Item No. 8: Remove Alternate Bid Item D-08 Administration Building While looking at options to reduce project costs and balance out payment for Items 1 through 5 of this Change Order, it was decided to remove the Alternate Bid Item consisting of the improvements to the Administration Building. This activity was scheduled to be started towards the end of the project and the City of Port Arthur reserves the right to re-add this Alternate Bid Item to the project at a later date. The City of Port Arthur also has the option to deduct the duration of this alternate bid item that Allco has designated for it on their baseline schedule from the contract time. Total Cost: ($189,452.00) Additional Days:0 Additional Days. Item No. 9:Abnormal Weather Days from NTP (6/22/2022)through November: 9 Days. The contract documents designate a fixed amount of "Anticipated Bad Weather Delays" per a given month and when the number of"Bad Weather Days", where rain "equals or exceeds 0.25 inches", go over the "Anticipated Bad Weather" days, that is defined as an "Abnormal Weather Condition" and "the contractor is entitled to an equitable adjustment in the Contract Times". From the date of the Notice to Proceed,June 6, 2022, up through the month of November, 2022, the project has experienced 9 Abnormal Weather Days. Total Cost: $0.00 Additional Days: 9 Calendar Days To summarize, this Change Order No. 002 has an overall cost reduction of ($73,564.57) and a contract time extension of 75 days. I hope the above narrative, along with the supporting documentation, provides adequate information. Please don't hesitate to reach out to me if you need any further explanation or backup documentation. Sincerely, Rami Abusheikh, P.E. Construction Manager cc:Jess Liao,Hani Tohme,Brian Wallace,Murali Erat [PTR22379]T:\4.0 CONSTRUCTION\4.40 Contract Mod\4.43 Chg Orders\Change Order No. 2 Change Order No.2 Project Port Arthur Main Wastewater Treatment Plant Improvements Project Number Owner City of Port Arthur R15056 Contractor Allco, LLC TX 875 Construction Manager Rami Abusheikh, PE PTR22379 Design Professional Murali Erat, PE PTR22379 CoPA Account No. 169-07-015-8516-00-40-000;404-40-000-8516-00-00-000 CoPA Project No. ARP002-GRE-WWT; TW-0003-CON Change Order No. 002 Date 12/01/2022 Make the following modifications to the Contract Documents: Item Description Change Amount 1 Demolition of Concrete Drying Beds at Primary Clarifier A(Add 14 Days) $33,735.83 2 Primary Clarifier A Unstable Subgrade Removal and Replacement(Add 42 Days) $99,104.00 3 Removal of CSS Discovered Around Existing Primary Clarifier C(Add 10 Days) $ 29,752.00 4 Shared Cost for Helical Piles Price Escalation $ 161,977.60 5 Brentwood Optimized Trickling Filter PVC Media with Cover $ 120,500.00 6 VE Lighting Package Revised Pricing(Deduct) ($74,792.00) 7 Switch Pipe Embedment from Class 3& 10 Aggregate to Bank Sand (Deduct) ($254,390.00) 8 Remove Alternate Bid Item D-08 Administration Building(Deduct) 9 Abnormal Weather Days from NTP(6/22/2022)through November: 9 Days Net Change in Contract Price this Change Order ($73,564.57) Net Change in Contract Times this Change Order 75 days The compensation in this Change Order is the full, complete, and final compensation for all costs Contractor may incur because of or relating to this change whether said costs are known, unknown,foreseen, or unforeseen at this time, including without limitation, any cost for delay, extended overhead, ripple or impact cost, or any other effect on changed or unchanged Work because of this Change Order. The changes in Contract Times are the complete and final adjustments for impacts to the ability of Contractor to complete the Work within the Contract Times and are the only adjustments to which Contractor is entitled. All terms and provisions of the Contract Documents remain in effect except as specifically modified by this Change Order. a.Original Contract Price $73,643,227.00 b. Previously Approved Change Order/Contract Amendment Amounts ($6,234,049.00) c.Adjusted Contract Price(a+b) $67,409,178.00 d. Contract Amendment Amount ($73,564.57) e. Revised Contract Price(c+d ) $67,335,613.43 f. Percent Change in Contract Price to Date -8.6 % Original Previous Current Substantial Completion Date 7/5/2026 7/5/2026 9/18/2026 Final Completion Date 10/3/2026 10/3/2026 12/17/2026 Change Order No.2 Page 1 of 2 Change Order No. 2 Recommended by Design Professional: Recommended by Construction Manager: 12/02/2022 12/02/2022 • � Murali Erat, PE Date Refibusheikh, PE Date (Freese and Nichols, Inc.) (Freese and Nichols, Inc.) Approved by Contractor: Approved by Owner: 1147/2Z , Brandon Harrison Date Ronald Burton Date Vice-President City Manager Allco, LLC City of Port Arthur Approved by Owner: Calvin Matthews, PE Date Director of Water Utilities City of Port Arthur Change Order No. 2 Page 2 of 2 Item No. 1 ll CO Design Build Construction Management General Contractors P.O. Box 3684, Beaumont,Texas 77704 Phone:409-860-4459 Fax:409-860-3857 Email:allco@allco.com October 12, 2022 Freese& Nichols 10497 Town &Country Way, Suite 500 Houston,TX 77024 Attn: Murali Erat Re: City of Port Arthur WWTP Improvements Project Change Proposal 2—Drying Bed and Piping Demo Dear Mr. Erat: Allco proposes the following change order to demo and remove concrete drying beds and associated pipe. DESCRIPTION/COST SUMMARY Demo and remove concrete drying beds which were not marked on the plans along with the associated underground clay drainage pipes. Time Extension-14 Calendar Days ITEM LABOR MATERIALS EQUIPMENT/FUEL SUBCONTRACTOR MARKUP/OH TOTAL Drying Bed $9,415.50 $00.00 $19,920.00 $0.00 $4,400.33 $33,735.83 and Piping Demo Please contact the undersigned if you have questions or issues regarding this matter. Respectfully, Allco, LLC Brandon Harrison 00 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 8 c • 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 c o 7' v 00 0 0 .o 0 0 Ji P ut o ,n n - v M a a. cJ o r- ut r - ao ,++ E. o Irv., cc O N EO+ M 4. C EF F col 0 O a. 0 69 69 69 69 69 69 69 69 69 69 69 69 69 69 69 69 69 w d+ 69 69 w w 6 69 69 = M 5 — — OD L O h 61 R C. N a o Z F y L M ° Z ' R 6. °- ee a" 6M4 d .O a. ' ' ' ' ' ' ' ' 8 8 8 8 8 8 8 8 8 8 ' ' , . . S O 4. cs .i S '8 0 0 ,o 4 o o .c o of o "a S .6 u LO O y � c F- e < rn N P a ,, o o, 4 C ."j 1 O. W M n - O. J O L C I. c 01 U c 0 W W = p O W U 69 69 69 69 69 69 69 69 AA69 VI VI w 69 69 w 69 EA69 w 69 69 69 Uj V6 („) ^' 8 8 8 8 8 8 8 8 8 g U o 8 N oN o 8 No E-' 0 a < F r r r a o N C.1 N 3 3 O P P C.O W W N : : : : : i : : itt E To F- w © Im eo c• U '� w i w 6 a n IF '? 5 5 o{n �7 F E-. o O E a H ^ 0 5 a _ o 7 > oFEo z F '5 7a _0- rvN p ,80 =• u '4 ' t .5a n o 0 0 F U U .0 o a E E o poQ No 2 LE = E-,a o cc — N-.F. v .c CC3 3 E o 3'-6 3'z W II! 2_> ❑5'C y a a o 0 0 0 0 0 0 0 o c o 0 0 0 0 M M W Z o 6W. o 0 0 0 0 0 0 0 0 0 ,n h o U1 'a C N O. o .L G .0 al < C OC Z NO 'O O t-�y CO `, '8 m O 1� ,-n M O r+ N y r, 0,..?: 0 0 n 0 M P. .a O U i F b F .D ,- Oi O` rn" C t- < E o o .- N ry M I 0.. .O y N :aenU g v CI▪ 0'L c la7 O o U 0 ao a E 4.° U .- f 69 w w 69 69 69 69 69 69 w 69 69 a 60 E0 69 69 69 69 69 6103 VI .D 8h88 8 08 8 d 3 E o aT c ory _ _ _ ^' - C e it u 69 69 69 w w w 6> 69 u O 1 E.' R. O O -a o g gaMrv ° rvry pC F O Ua. je s x t o c c -, O - E ° U c5 sU ag m �° PE o pa - 3 o 3 2 v ,:. z s F. u 3 3 C y z 2' E d E E m o a. v 6x g .F j N 0 1- LL-' 173' g tl vgL _ L E � O CN E - N • T y¢ c m Z . o C Q O 2m 0 L S -0 = L .o o ro ,. a .- -, c y aCc a p c a o . o .o o E U Q o: 2 i 9 ' 0 0.1 m 'c F 3 0 o _p,J t 6, A `a A d F E.., m o ' o ; .. .. C ? v `. P. a B F m 4' v.n .-w v e°'n .. J m �,° p. �g. 3 0 m a a d .o . u d .• c� « A L. u -ao � 2 ,E'a:: E o .- $ n o u f 4 =' v a t a U O o o` t .• °. d E o E E .d a o o • i `• Xtt e ta v ° g 0-. c c v •6 E A ° 3 0 0 •E .. ..] 2 [y U a CO O ii 'SO a 0 0 0 0 -- N M -4- V ho r al O. 2 Item No. 2 A ll Design Build Construction Management General Contractors P.O. Box 3684, Beaumont,Texas 77704 Phone:409-860-4459 Fax:409-860-3857 Email:allco@allco.com September 22, 2022 Freese& Nichols 10497 Town & Country Way,Suite 500 Houston,TX 77024 Attn: Murali Erat Re: City of Port Arthur WWTP Improvements Project Change Proposal 1—Primary Clarifier Subgrade Repairs Dear Mr. Erat: Allco proposes the following change order to remove drying bed backfill materials and replace with imported selected fill: DESCRIPTION/COST SUMMARY Remove drying bed backfill materials(gravel,sand,etc)and replace w/imported select fill per directive provided by AWC/FNI;spoil material to be hauled to onsite pond Time Extension-75 Calendar Days ITEM LABOR MATERIALS EQUIPMENT/FUEL SUBCONTRACTOR MARKUP/OH TOTAL PC Subgrade $27,953.00 $23,625.00 $34,600.00 $0.00 $12,926.00 $99,104.00 Repair Please contact the undersigned if you have questions or issues regarding this matter. Respectfully, Allco, LLC Brandon Harrison 0 0 o0. C S o . , o 0 EA 4 O No N 00 o CC r„.o\ CL HF VC. 69 69 69 69 69 69 69 69 69 69 69 69 69 69 69 69 65 69 69 69 9 69 68 to) 0 O • :n `n R Cr 0 z ° a1 s.. O\ z L _ I. b - yti ° a g g R .. F a` $ ° L 4.. o © ' g 1b E D O ° u .9 pRad b o M n.P C...) b C G o w W O c o W U 44 69 69 69 69 69 69 69 69 69 69 69 69 69 69 69 to V] ‘9•1 Co) c c_. F H a o U co cr E toLo v £ E . a 2, E U h . a 0R F" E C° 2 G 04 t o O_ X .O O o. :F. 0 G LEw L 69 tr.. to to 69 b9 69 6/9 O o O s U A o o 'n crzi 0 C.) ` o o 0 m o c Al NU co o Li_ o 69 69 G 69 FA 69 9 FA 5 J 5 E E o O '6' v a 5. o - ,D = e b W o o = ch i F io F c 0 V O. ° d y 2 v 2 A o 2 ;, 5 .. , 0 p a o Y N ❑ , . a o I21 ,2 '..'-- - cc 3 "a I' e v T o t b vv b it m d.o CC o m a > > - O o d • E i- 0 0 0 0 0 0 0 0 z a a; ,ba o o p A -o .O 2 m C .n to O o 0 0 0 o p W 4b. rn a '� `� N o N Y v O C N C U _ H N N H h r r- (n m 'o N Z P. P r N N O O N N N co oN Q W V] O :� h `.7 n R r ' b To -c E yip, p v L.) a W 2'0 o U 69 69 69 69 69 69 69 69 of n 969 69 69 .4 69 69 69 69 69 69 s: u 0 O II ` ° H y H U c - U . 5 [-° 5 © E °e ,2 F - E o o U .o c `o o u .a H CO) ea o U E o o E � e p E r c 2 w vh - F. U Y Y ro 2 i 33 `o `o a .? .c° Y°o 3 3 c yz E ¢ 3 „ :0”.. 3 c rt11' �� o o ` S v V iZ Lat.'0.3~ 0. � �3Jw YL° Y F, o a= H o - o O6. oV F. 75 o L. o ' Eo ow O 'Lz ht $ � c o bA ° aN 3 v a7 ° '. o c 2 U Q !t 2 R v o a 9 o a u Y E c 2 v o 5 8 E _ U 3 b L o ,4- w .. 9 tC U 'v 7 .o L .__ .a p .. g `° e E,o o .. CA i 1 v E a o a o 0 0 •y _. K y O c .5 c b •• 0 6: .j Al...9., .0 A C L N -o V tG L y •V L c 0 N E O E .` 2 Fa 4: 0 L 'F o = a y t ,d b y v d 3 i m 5 ` b . ° c > c a` o O 4 PP 0 0 0 6t. r oo o RI M TT, v1 � F. CO Item No. 3 AL' Design Build Construction Management General Contractors P.O. Box 3684, Beaumont,Texas 77704 Phone:409-860-4459 Fax:409-860-3857 Email:allco@allco.com September 22, 2022 Freese& Nichols 10497 Town &Country Way, Suite 500 Houston,TX 77024 Attn: Murali Erat Re: City of Port Arthur WWTP Improvements Project Change Proposal 3—Existing Primary Clarifier CSS Removal Dear Mr. Erat: Allco proposes the following change order to remove cement stabilized material around perimeter of existing Primary Clarifier C and replace with select fill: DESCRIPTION/COST SUMMARY Remove cement stabilized sand and haul to onsite pond; Import and place select fill in its place; Per RFI-10 response Time Extension-10 Calendar Days ITEM LABOR MATERIALS EQUIPMENT/FUEL SUBCONTRACTOR MARKUP/OH TOTAL CSS Removal $11,557.00 $3,375.00 $10,940.00 $0.00 $3,880.00 $29,752.00 & Fill Replacement Please contact the undersigned if you have questions or issues regarding this matter. Respectfully, AIIco, LLC Brandon Harrison 1 0 0 0 , 8 , 8 , 0 0 0 a, a n N in N O M n To en tn N 0. O C Y 0 N o0 p ^ N co) C4 FX = U 69 v, us rA v, v> 64 v, us v, v, w v, d, H u, 69 61 69 v, 65 69 69 0 O h • O 4 ce G N o 0 u a+ - u F� e3 8 L4. a o $ 3 6 L .L. O 0�. 1 is, F-. or, a EO- p c aJ u y O O t1 C L • o W = C w u 69 vi vi .. EA vi 69 69Y Y 69 vi » 69 vi sv V: vi Uo U E- E a ❑ a •0 v cr 2 W W L •XC , , N aE C F F F en O W ,0 C G W 0 y O , AA A A A A V9 L Z O S C CL tri eri 69 L. a• o t rv, ,n _ ., t., 1 cc d, N C7 v t3. I- LL ' Io .9 `E 0 N ,,` V F " oc T..) O Q N a 2 -- ' . ' O > AE -o U V1 o a • en al a _ v7 7 c O v F E 0 G. o, ai, ° 5v A -.].9 Ai o O .o N 3 C W v, N aCC 2o.� 0 5 T o T CC a CD �a O C4 W 0. C . U 2 E a d' O w d m 0 0 0 0 0 0 0 0 O 2 0 O N nd o o c o 0 0 0 0 o p `° .a .� Y a a, N 0 n o0o N a z . CO U y F - M o omo" r TO' ti O ° y . 'n � ^ N 01 z 0. u �p ^ TO N < euUv w O 10 .„1ra o O 2 A ;. w„ E '� E 2 V U al co CC C.) u U " v, v, w v, zv v,,v, rA v, v, 9 sn 44 L v, v, v, cA v, v, 6A v O E v. O L o T T O J N O O R O O L _ i 2 2 v F o f o o G.i 2 c I a F U ea 2 - V 2 2 a0 C, = .O c ..- 2 L y ... LU v = s A - * - `o 3 3 � o W ve.— v F 5 ° v 3 ' r A �0. t V — 6, W 'Y 2" o 0 0 o E A N 0. o v F a 7 3 u r U ,- E dF a - -o 0 3 0.0. j p Ci7 •0 `v i. O o vi '? 0 .� -Eo 3 O 0 o ¢ _ o a W px 3 R .•- 2 A 'U e3 m w N = aL., R 7 V y' p y •_ E 4 V 2 U c4 2 i ` o a O p 8 .�o 2 v .. V a y U c d 2 w . ,-v see .. `oj 5 . o .� a ° o " a 2 ° U `'' o a 2 is A .5 a 2 0 .. .. u • .$ o A ' `�u .a `o E ' .a a o ° o D V o s` a 2 . A a 2 E D o .a c v 2 'g u u A A .F v u a c E .c 0 = a ? � 4s, = - a, u d z - 2 V P� � N ' •492a2 > 2o0 E o 0 .5 W ma2mUcmOi,. x 0. U U O ^r. o -- Nmvv�o�wa 1 Item No. 4 BRON & CLAUDE Engineering I Construction bronclaude.com Port Arthur Wastewater Treatment Project-Price increase Summary Intended Recipient:ALLCO, LLC Date:June 14th,2022 As witness to the following individual Brandon Harrison Vice President ALLCO, LLC Dear Customer, Steel prices have increased roughly over 20%since the time of our base bid price submitted January 27, 2022. Following the proposal, our base bid price was held additionally for 30 days with the expectation that the project would begin shorty after. We were unable to secure raw materials at the February market price. The steel market has been in on an upward trend since quarter one 2022. It is expected to continue to rise throughout the year with other premium cost related to our industry such as welding materials, supplies, labor, etc. Attached is supporting documentation. Inflation has had a tremendous pressure on the price of steel. For these reasons there has been a 20% price increase from our base bid price effective on all orders received after June 1st,2022. In order to honor the current bid price, and approved design as well as material will need to be secured no later than June 24th,2022. These changes will not affect our service in any way, and we will continue to provide you with top-quality piling products. We greatly appreciate your understanding. if you have any questions, please do not hesitate to contact me. Bronson Burke Executive Director Engineering I Construction CV el VI in N -Z -� - L _u j -PO -I� -uq^ - �:s PS _ p r 't-p la- '.•-• --4 tlit < , ... -Z ri - - i .i.z t1. • - 1.-1 L -1,,-u L ••. - t,.-p ea 0. cmoo PC c, °!0 -c L-u ct to -iI.-InI • v N .; N rl - G Y a ice„ <> N C O j -V�" W r p 1 V x - L�� V . . . H ' :',... ew V? - -U L" Q r �v -I iked tit -7 LA t/) �G x ,8. ao a ��d V, o Q-,_ - PQ' a 1�, o Q Y I- - -rtID 41) CD ft :i Ili , , , r . . , , , . iire 8 8 8 8 8 8 $ 8 N N N auuoi 31.1i0w Jad sieiioa 11 Item No. 5 Rami Abusheikh From: Rami Abusheikh Sent: Friday, December 2, 2022 04:57 To: Rami Abusheikh Subject: RE:Trickling Filter Plastic Media Categories: PTR22379 - Port Arthur WWTP From: Murali Erat<mue@freese.com> Sent:Tuesday, November 8, 2022 16:31 To: Danny Thibodeaux<Danny.Thibodeaux@portarthurtx.gov>;JESS LIAO<jess.liao@portarthurtx.gov>; Calvin Matthews<calvin.matthews@portarthurtx.gov>;tohmehani@yahoo.com Cc: Rami Abusheikh<Rami.Abusheikh@freese.com> Subject: RE:Trickling Filter Plastic Media All, I met with Brentwood trickling filter media manufacturer last week to understand the optimized design they are proposing. Below is a summary of my understanding of their proposal: • The original design specified PVC as the type of material for the trickling filter media and required a bearing capacity of 40 pounds per square foot (PSF) per foot of media height or 1,000 PSF, whichever is greater(this is for the top and bottom media layer). Because of the shallow depth of the trickling filter, 1,000 PSF will be the governing criteria which is pretty conservative. • Brentwood's alternate design reduces the bearing capacity from 1,000 PSF to 640 PSF for the top layer and 700 PSF for the bottom layer. This will still meet the industry standard of 40 PSF per foot of media height. Additionally, Brentwood will be supply their protective grating for the entire surface of the filter.This grating will allow the operator to walk the entire surface of the filter and also provide some UV protection for the media. See email below from Danny.The plant currently has only a narrow access walkway that has the grating. With the new media there will be grating over the whole surface. In my opinion, the optimized design proposed by Brentwood is acceptable.The lower bearing capacity which results in thinner gauge for the media does not compromise the structural integrity of the media. Additionally, the protecting grating over the entire surface of the filter will provide additional protection for the media. Below is a cost comparison of the all the trickling media options provided by Allco. With change order no. 1 we changed the media type to CE Shepherd's PP and took a cost credit of$298,000 which is no longer available. You can see that Brentwood's optimized design will provide the maximum savings. No. Trickling Filter Media Type Cost Cost Savings Original Base Bid 1. Jan 2022 $987,500 $0 Brentwood PVC Media 2 Original VE Option $689,500 $298,000 May 2022 (Price no longer valid) (No longer available) CE Shepherd PP Media Updated Pricing as of November 2022 1 Brentwood PVC Media $889,000 $98,500 (Per Original Spec) 2. Brentwood PVC Media —Optimized Design $810,000 $177,500 3 CE Shepherd PVC Media $892,500 $95,000 (Per Original Spec) 4 CE Shepherd PP Media $830,500 $157,000 (Per spec issued in Change Order No. 1) Please review and let us know how you would like to us to proceed. I will give you a call tomorrow to discuss. Thanks, Murali Erat, PE 1832-456-4709 I murali.erat@freese.com FREESE �'!�<NICHOLS 2 Item No. 6 Rami Abusheikh From: Brandon Harrison <bharrison@allco.com> Sent: Monday,August 29, 2022 08:12 To: Murali Erat; Michael Schuster; Rami Abusheikh Subject: Fw:VE Lighting Package Follow Up Flag: Follow up Flag Status: Completed Categories: PTR22379 - Port Arthur WWTP This is an email from an EXTERNAL source. DO NOT click links or open attachments without positive sender verification of purpose. Never enter USERNAME, PASSWORD or sensitive information on linked pages from this email. Please report all suspicious messages using the Report Message button in Outlook. See below email from W-Industries and link for revised lighting package submittal. The original Lighting Package credit was for $110,000. After adding the Site Light Poles back, this reduced the credit amount by $35,208 for a revised credit amount of $74,792. https://www.dropbox.com/s/vru466zch2xg6c5/%233A 26%2050%2000%20Light%20Fixtures%20%28 V.E%29%20%281%29.pdf?d1=0 Thank You, EfUtotd44 qQ 1.400 Vice-President Division Manager—Heavy/Civil A LCO P.O. Box 3684 Beaumont, Texas 77704 Ph: (409)860-4459 Fax: (409)860-3857 Email: bharrisonc allco.com Forwarded Message From "Stetson Dorrough" <Stetson Dorrough@w-industries.com> To "Brandon Harrison" <bharrison@allco.com> Cc "Javier Avila" <Javier Avila@w-industries.com> Date 8/23/2022 10:29:42 AM Subject VE Lighting Package Brandon, • The$35,208 mentioned in our last emails and phone call is to include just the Site light poles for the P1 and P2 lights. The S-type lights on the catwalks do not have any change to the package.They will be mounted on aluminum conduit, not actual light poles. The cost of the aluminum conduit is already included in the package. So, in short the only change to the package is the site light poles and the addition of those poles are the only price difference. The dollar value to add site light poles back to the package has increased since April due to the rising cost of inflation. Let me now if you have any questions. Stetson Dorrough Jr. Project Manager- Field Services P: 713-466-9463 I C: 832-656-4068 E: stetson dorrough@w-industries.com VV-INDUSiTRIES 11500 Charles Rd., Houston,TX 77041 NEW "Whatever It Takes" in ,VCIUW US ON L N W N Disclaimer The content of this email is confidential and intended for the recipient specified in message only. It is strictly forbidden to share any part of this message with any third party, without a written consent of the sender. If you received this message by mistake, please reply to this message and follow with its deletion, so that we can ensure such a mistake does not occur in the future. 2 Item No. 7 ALLCO LLC PORT ARTUR WWTP BANK SAND VS 57 Rock ITEM QTY UNIT UNIT COST TOTAL #57 ROCK 15,225 TONS $33.00 $502,425.00 BANK SAND 11,300 CY $21.95 $248,035.00 TOTAL SAVINGS $254,390.00 Item No. 9 0133 05 CONSTRUCTION PROGRESS SCHEDULE PART 1- GENERAL 1.08 DELAYS IN CONTRACTOR'S PROGRESS D. Contractor is to include time associated with normal weather-related delays in the Baseline Schedule and assume the risks, including costs, associated with delays related to normal weather conditions. Contractor is entitled to an equitable adjustment in the Contract Times, but not Contract Price, if Contractor's performance or progress is delayed or disrupted by abnormal weather conditions.Abnormal weather conditions exist when the number of bad weather days for a given month exceed the number of anticipated bad weather delays per month indicated in the table below: Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 4 4 3 3 4 6 6 5 5 4 3 4 1. Bad weather days are determined on a month by month basis in accordance with the following: a. Total precipitation occurring between midnight on the preceding day(regardless of whether such preceding day is a workday)through midnight on the workday in question equals or exceeds 0.25 inches of precipitation. b. Ice or snow at the site make working conditions hazardous. c. Heat index at 3:00 p.m.falls into the Extreme Risk Category per NIOSH Criteria for a Recommended Standard: Occupational Exposure to Heat and Hot Environments and working hours cannot be adjusted to avoid exposure to heat. Anticipated Bad Float (neg) / Abnormal Days Over 0.25" Days (pos) June-22 6 1 -5 July-22 6 5 -1 August-22 5 10 5 September-22 5 0 -5 October-22 4 3 -1 November-22 3 7 4 1 Climatological Data for Beaumont-Port Arthur Area,TX(ThreadEx)-June 2022 1 II Temperature Date HDD CDD Precipitation New Snow Snow Depth M ximum Minim m Avera De artur 2 2-0 1 9 /9181. 2 00.2006- 93 0.6 1 0.7 .0 /4/ 22- -03 6 .0 .6 0 13 .00 M2 -0 4 9 -0 0 0.20 06- 9079. -1.9 1 0.0 .0 /' NTP 2022-06-06 89 73 81.0 -0.1 0 16 0.00 0.0 M 2022-06-07 91 75 83.0 1.8 0 18 0.00 0.0 M 2022-06-08 92 76 84.0 2.6 0 19 0.00 0.0 M 2022-06-09 94 75 84.5 3.0 0 20 0.00 0.0 M 2022-06-10 94 72 83.0 1.4 0 18 0.00 0.0 M 2022-06-11 94 77 85.5 3.8 0 21 0.00 0.0 M 2022-06-12 94 77 85.5 3.6 0 21 0.00 0.0 M 2022-06-13 95 77 86.0 4.0 0 21 0.00 0.0 M 2022-06-14 94 78 86.0 3.9 0 21 0.00 0.0 M 2022-06-15 95 76 85.5 3.3 0 21 0.00 0.0 M 2022-06-16 98 73 85.5 3.2 0 21 0.00 0.0 M 2022-06-17 95 75 85.0 2.7 0 20 T 0.0 M 2022-06-18 97 76 86.5 4.1 0 22 0.00 0.0 M 2022-06-19 100 75 87.5 5.0 0 23 0.00 0.0 0 2022-06-20 98 78 88.0 5.4 0 23 0.00 0.0 M 2022-06-21 97 77 87.0 4.4 0 22 0.00 0.0 0 2022-06-22 94 76 85.0 2.3 0 20 0.00 0.0 0 2022-06-23 100 73 86.5 3.8 0 22 0.00 0.0 0 2022-06-24 98 76 87.0 4.2 0 22 0.00 0.0 M 2022-06-25 99 70 84.5 .1.7 0 20 0.00 0.0 0 2022-06-26 101 75 88.0 5.1 0 23 0.05 0.0 M 2022-06-27 96 76 86.0 3.1 0 21 0.00 0.0 M 2022-06-28 95 77 86.0 3.0 0 21 0.00 0.0 M 2022-06-29 94 75 84.5 1.5 0 20 0.01 0.0 M 2022-06-30 80 73 76.5 -6.6 0 12 1.38 0.0 M Sum 2824 2233 - - 0 584 3.54 0.0 - Average 94.1 74.4 84.3 2.3 - - - - 0.0 Normal 90.9 73.1 82.0 - 0 510 6.70 M - Observations for each day cover the 24 hours ending at the time given below(Local Standard Time). Max Temperature:midnight Min Temperature:midnight Precipitation:midnight Snowfall:midnight Snow Depth:6am Climatological Data for Beaumont-Port Arthur Area,TX(ThreadEx)-July 2022 Temperature Date IIDD CDD Precipitation New Snow Snow Depth Maximum Minimum Average Departure _ 2022-07-01 83 72 77.5 75.6 0 13 6.20 0.0 M 2022-07-02 93 75 84.0 0.9 0 19 0.33 0.0 M 2022-07-03 94 76 85.0 1.8 0 20 0.00 0.0 M 2022-07-04 94 76 85.0 1.8 0 20 0.00 0.0 M 2022-07-05 94 75 84.5 1.3 0 20 0.00 0.0 M 2022-07-06 92 77 84.5 1.2 0 20 0.29 0.0 M 2022-07-07 95 76 85.5 2.2 0 21 0.00 0.0 M 2022-07-08 95 75 85.0 1.7 0 20 0.00 0.0 M 2022-07-09 97 76 86.5 3.1 0 22 0.00 0.0 M 2022-07-10 97 75 86.0 2.6 0 21 0.11 0.0 M 2022-07-11 97 77 87.0 3.6 0 22 0.00 0.0 M 2022-07-12 98 78 88.0 4.5 0 23 0.00 0.0 0 2022-07-13 94 77 85.5 2.0 0 21 0.00 0.0 0 2022-07-14 94 70 82.0 -1.5 0 17 2.37 0.0 M 2022-07-15 92 75 83.5 -0.1 0 19 0.03 0.0 M 2022-07-16 94 74 84.0 0.4 0 19 0.00 0.0 M 2022-07-17 95 74 84.5 0.9 0 20 0.00 0.0 M 2022-07-18 95 75 85.0 1.3 0 20 0.00 0.0 M 2022-07-19 93 77 85.0 1.3 0 20 0.00 0.0 M 2022-07-20 94 78 86.0 2.3 0 21 0.00 0.0 M 2022-07-21 94 75 84.5 0.7 0 20 0.00 0.0 M 2022-07-22 86 73 79.5 -4.3 0 15 1.05 0.0 M 2022-07-23 93 75 84.0 0.2 0 19 0.00 0.0 M 2022-07-24 94 76 85.0 1.1 0 20 T 0.0 M 2022-07-25 94 76 85.0 1.1 0 20 0.00 0.0 M 2022-07-26 94 77 85.5 1.6 0 21 0.04 0.0 M 2022-07-27 93 76 84.5 0.5 0 20 0.01 0.0 M 2022-07-28 93 77 85.0 1.0 0 20 0.08 0.0 M 2022-07-29 94 77 85.5 1.5 0 21 0.00 0.0 M 2022-07-30 89 77 83.0 -1.1 0 18 0.01 0.0 M 2022-07-31 94 74 84.0 -0.1 0 19 0.00 0.0 M Observations for each day cover the 24 hours ending at the time given below(Local Standard Time). Observation times may have changed during this period. Max Temperature:midnight Min Temperature:midnight Precipitation:midnight Snowfall:unknown,midnight Snow Depth unknown Climatological Data for Beaumont-Port Arthur Area,TX(ThreadEx)-August 2022 Temperature Date HDD CDD Precipitation New Snow Snow Depth Maximum Minimum Average Departure 2022-08-01 94 76 85.0 0.9 0 20 0.02 0.0 M 2022-08-02 95 77 86.0 1.9 0 21 0.23 0.0 M 2022-08-03 94 77 85.5 1.4 0 21 0.00 0.0 M 2022-08-04 94 77 85.5 1.4 0 21 0.00 0.0 M 2022-08-05 88 74 81.0 -3.2 0 16 0.90 0.0 0 2022-08-06 90 76 83.0 -1.2 0 18 0.12 0.0 0 2022-08-07 92 76 84.0 -0.2 0 19 0.01 0.0 M 2022-08-08 93 75 84.0 -0.1 0 19 0.54 0.0 M 2022-08-09 93 77 85.0 0.9 0 20 0.56 0.0 M 2022-08-10 91 75 83.0 -1.1 0 18 0.42 0.0 M 2022-08-11 91 75 83.0 -1.1 0 18 0.15 0.0 M 2022-08-12 92 75 83.5 -0.6 0 19 0.01 0.0 M 2022-08-13 90 76 83.0 -1.1 0 18 0.56 0.0 M 2022-08-14 92 76 84.0 0.0 0 19 0.08 0.0 M 2022-08-15 93 75 84.0 0.0 0 19 0.00 0.0 M 2022-08-16 93 73 83.0 -0.9 0 18 0.00 0.0 M 2022-08-17 96 74 85.0 '1.1 0 20 0.00 0.0 M 2022-08-18 94 74 84.0 0.2 0 19 0.46 0.0 M 2022-08-19 83 73 78.0 -5.8 0 13 0.26 0.0 M 2022-08-20 88 74 81.0 -2.7 0 16 1.17 0.0 M 2022-08-21 92 76 84.0 0.3 0 19 T 0.0 M 2022-08-22 91 78 84.5 0.9 0 20 T 0.0 M 2022-08-23 91 75 83.0 -0.5 0 18 0.10 0.0 M 2022-08-24 85 76 80.5 -2.9 0 16 0.23 0.0 M 2022-08-25 91 75 83.0 -0.3 0 18 0.02 0.0 M 2022-08-26 90 75 82.5 -0.7 0 18 0.26 0.0 M 2022-08-27 91 73 82.0 -1.1 0 17 0.39 0.0 M 2022-08-28 91 77 84.0 1.0 0 19 0.09 0.0 M 2022-08-29 90 76 83.0 0.1 0 18 0.15 0.0 M 2022-08-30 92 76 84.0 1.2 0 19 T 0.0 M 2022-08-31 93 74 83.5 0.8 0 19 0.00 0.0 0 Sum 2833 2336 - - 0 573 6.73 0.0 - Average 91.4 75.4 83.4 -0.4 - - - - 0.0 Normal 93.1 74.4 83.8 - 0 581 6.89 M - Observations for each day cover the 24 hours ending at the time given below(Local Standard Time). Max Temperature:midnight Min Temperature:midnight Precipitation:midnight Snowfall:midnight Snow Depth:unknown Climatological Data for Beaumont-Port Arthur Area,TX(ThreadEx)-September 2022 Temperature Date HDD CDD Precipitation New Snow Snow Depth Maximum Minimum Average Departure 2022-09-01 94 75 84.5 1.9 0 20 T 0.0 0 2022-09-02 94 74 84.0 1.5 0 19 T 0.0 M 2022-09-03 86 75 80.5 -1.8 0 16 0.12 0.0 M 2022-09-04 80 73 76.5 -5.7 0 12 0.21 0.0 M 2022-09-05 86 73 79.5 -2.5 0 15 T 0.0 M 2022-09-06 87 71 79.0 -2.9 0 14 T 0.0 M 2022-09-07 92 70 81.0 -0.7 0 16 0.03 0.0 M 2022-09-08 91 69 80.0 -1.6 0 15 0.00 0.0 M 2022-09-09 90 70 80.0 .1.4 0 15 T 0.0 M 2022-09-10 91 69 80.0 -1.3 0 15 T 0.0 M 2022-09-11 92 71 81.5 0.4 0 17 T 0.0 M 2022-09-12 89 72 80.5 -0.4 0 16 T _ 0.0 M 2022-09-13 88 66 77.0 -3.7 0 12 0.00 0.0 M 2022-09-14 89 65 77.0 -3.5 0 12 0.00 0.0 M 2022-09-15 89 69 79.0 -1.3 0 14 T 0.0 M 2022-09-16 85 73 79.0 -1.2 0 14 0.17 0.0 M 2022-09-17 91 73 82.0 2.1 0 17 T 0.0 M 2022-09-18 92 77 84.5 4.8 0 20 T 0.0 M 2022-09-19 93 75 84.0 4.5 0 19 T 0.0 M 2022-09-20 95 74 84.5 5.2 0 20 0.00 0.0 M 2022-09-21 94 72 83.0 3.9 0 18 0.00 0.0 M 2022-09-22 96 72 84.0 5.1 0 19 T 0.0 M 2022-09-23 96 73 84.5 5.9 0 20 T 0.0 M 2022-09-24 94 70 82.0 3.6 0 17 0.00 0.0 M 2022-09-25 94 69 81.5 3.4 0 17 0.00 0.0 M 2022-09-26 91 71 81.0 3.1 0 16 0.00 0.0 M 2022-09-27 87 60 73.5 -4.1 0 9 0.00 0.0 M 2022-09-28 87 61 74.0 -3.3 0 9 0.00 0.0 M 2022-09-29 83 61 72.0 -5.1 0 7 0.00 0.0 M 2022-09-30 82 53 67.5 -9.3 0 3 0.00 0.0 M Observations for each day cover the 24 hours ending at the time given below(Local Standard Time). Max Temperature:midnight Min Temperature:midnight Precipitation:midnight Snowfall:midnight Snow Depth:unknown Climatological Data for Beaumont-Port Arthur Area,TX(ThreadEx)-October 2022 Temperature Date HDD CDD Precipitation New Snow Snow Depth Maximum Minimum Average Departure 2022-10-01 86 55 70.5 -6.0 0 6 0.00 0.0 M 2022-10-02 86 54 70.0 -6.2 0 5 0.00 0.0 M 2022-10-03 88 56 72.0 -3.9 0 7 0.00 0.0 M 2022-10-04 85 58 71.5 -4.1 0 7 0.00 0.0 M 2022-10-05 87 60 73.5 -1.8 0 9 0.00 0.0 M 2022-10-06 90 59 74.5 -0.5 0 10 0.00 0.0 M 2022-10-07 92 60 76.0 1.3 0 11 0.00 0.0 M 2022-10-08 90 68 79.0 4.6 0 14 0.00 0.0 M 2022-10-09 87 62 74.5 0.4 0 10 0.00 0.0 M 2022-10-10 85 61 73.0 -0.7 0 8 T 0.0 M 2022-10-11 85 61 73.0 -0.4 0 8 0.00 0.0 M 2022-10-12 86 70 78.0 4.9 0 13 0.25 0.0 M 2022-10-13 87 65 76.0 3.3 0 11 0.43 0.0 M 2022-10-14 86 57 71.5 -0.9 0 7 0.00 0.0 M 2022-10-15 87 63 75.0 3.0 0 10 0.00 0.0 M 2022-10-16 90 67 78.5 6.8 0 14 0.00 0.0 0 2022-10-17 73 58 65.5 -5.8 0 1 0.01 0.0 M 2022-10-18 67 45 56.0 -15.0 9 0 0.00 0.0 M 2022-10-19 66 38 52.0 -18.6 13 0 0.00 0.0 M 2022-10-20 81 40 60.5 -9.8 4 0 0.00 0.0 M 2022-10-21 84 53 68.5 -1.4 0 4 0.00 0.0 M 2022-10-22 84 59 71.5 1.9 0 7 0.00 0.0 M 2022-10-23 85 64 74.5 5.3 0 10 0.00 0.0 M 2022-10-24 86 71 78.5 9.7 0 14 0.00 0.0 M 2022-10-25 77 48 62.5 -6.0 2 0 0.14 M M 2022-10-26 77 45 61.0 -7.1 4 0 0.00 0.0 M 2022-10-27 77 47 62.0 -5.8 3 0 0.00 0.0 M 2022-10-28 74 62 68.0 0.6 0 3 3.93 0.0 M 2022-10-29 68 57 62.5 -4.6 2 0 0.15 0.0 M 2022-10-30 76 55 65.5 -1.2 0 1 0.00 0.0 M 2022-10-31 80 52 66.0 -0.4 0 1 0.00 0.0 M Sum 2552 1770 - - 37 191 4.91 0.0 - Average 82.3 57.1 69.7 -1.9 - - - - 0.0 Normal 82.1 61.1 71.6 - 26 231 5.47 M - Observations for each day cover the 24 hours ending at the time given below(Local Standard Time). Max Temperature:midnight Min Temperature:midnight Precipitation:midnight Snowfall:midnight Snow Depth:6am Climatological Data for Beaumont-Port Arthur Area,TX(ThreadEx)-November 2022 Temperature Date HDD CDD Precipitation New Snow Snow Depth Maximum Minimum Average Departure 2022-11-01 66 54 60.0 -6.1 5 0 0.30 0.0 M 2022-11-02 75 60 67.5 1.8 0 3 0.01 0.0 M 2022-11-03 80 68 74.0 8.6 0 9 0.00 0.0 M 2022-11-04 82 71 76.5 11.4 0 12 0.01 0.0 M 2022-11-05 77 56 66.5 1.7 0 2 1.31 0.0 M 2022-11-06 86 59 72.5 8.1 0 8 0.00 0.0 M 2022-11-07 85 66 75.5 11.4 0 11 0.00 0.0 M 2022-11-08 86 66 76.0 12.2 0 11 0.00 0.0 M 2022-11-09 85 64 74.5 11.0 0 10 0.00 0.0 M 2022-11-10 80 57 68.5 5.3 0 4 0.00 0.0 M 2022-11-11 83 53 68.0 5.1 0 3 0.50 0.0 0 2022-11-12 59 43 51.0 -11.7 14 0 0.07 M 0 2022-11-13 59 36 47.5 -14.9 17 0 0.00 0.0 M 2022-11-14 59 47 53.0 -9.1 12 0 1.01 M M 2022-11-15 52 43 47.5 -14.3 17 0 0.00 0.0 M 2022-11-16 54 41 47.5 -14.1 17 0 0.00 0.0 M 2022-11-17 58 38 48.0 -13.3 17 0 0.00 0.0 M 2022-11-18 60 41 50.5 -10.6 14 0 0.01 M M 2022-11-19 50 43 46.5 -14.3 18 0 0.75 M M 2022-11-20 59 40 49.5 -11.1 15 0 T M M 2022-11-21 48 43 45.5 -14.8 19 0 0.20 M M 2022-11-22 57 45 51.0 -9.1 14 0 0.01 M M 2022-11-23 73 45 59.0 -0.9 6 0 0.00 0.0 M 2022-11-24 70 59 64.5 4.8 0 0 3.66 0.0 M 2022-11-25 63 60 61.5 2.1 3 0 0.16 0.0 M 2022-11-26 69 51 60.0 0.8 5 0 2.12 0.0 M 2022-11-27 76 46 61.0 2.0 4 0 0.00 0.0 M 2022-11-28 74 46 60.0 1.2 5 0 0.00 0.0 M 2022-11-29 M M M M M M M M M 2022-11-30 M M M M M M M M M Sum 1925 1441 - - 202 73 10.12 0.0 - Average 68.8 51.5 60.1 -2.0 - - - - 0.0 Normal 72.6 51.7 62.1 - 143 63 3.61 M - Above Normals represent the month through 2022-11-28. Observations for each day cover the 24 hours ending at the time given below(Local Standard Time). Max Temperature:midnight Min Temperature:midnight Precipitation:midnight Snowfall:midnight Snow Depth:unknown